Yesterday Issue of injection kicker not pulsing:

Slides:



Advertisements
Similar presentations
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Advertisements

R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Saturday 6:13 – 15:00 STABLE BEAMS  scans etc. 15:00 moved to ADJUST Squeeze to 2 m in two steps 11 – 5 – 2  remarkably smooth  tertiary collimators.
LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Tuesday 26 th April – morning shift 08:00 Great news, cryo is back! Unluckily it was followed by many other problems, one after the other one. So, spent.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
LHC Beam Commissioning Meeting V. Kain & R. Alemany
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Beam dump at 03:00:
SPS extraction, transfer lines, injection
Injection BIS – next iteration
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Friday 15th June 01:11 Injection.
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Summary Friday h38: Ramp down and pre-cycle.
Summary of week 7 Hardware Commissioning:
Monday 14th March Second fill with pilot + 3 nominal bunches
Monday fill with 1092 bunches (6 h stable beams)
Monday 11/07: Recovery Plenty of accesses.
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Wednesday 31 October: Morning
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
LHC commissioning Week 38
Bernhard Holzer, Joerg Wenninger
Friday 31st August & night
Planning at 5 o’clock meeting Friday
Thursday :00: Physics fill from the night shift
Yesterday Power back around lunchtime Access until 12:30
Yesterday morning Held 1647 for a while – SPS kicker problem
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Saturday 7th May Sat – Sun night
Programme for Saturday 10 July
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Summary week 18 Intensity ramp up & production
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Friday 28 October 2011.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Thursday 30th September De-bunching test
Thursday
Saturday 24 September 2011.
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Wednesday h18: 228b fill lost just before start of ramp.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Another Immortal Fill….
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Wednesday 14:30 Fill 2011 dumped.
Saturday 26 November 2011.
Tuesday
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Daniel, Gianluca and Belen (for the Collimator team)
Presentation transcript:

Yesterday Issue of injection kicker not pulsing: Second pulse after a SoftStart is missed due to a voltage reduction issue inside kicker timing system. Voltage reference goes to 0V instead of 95% of the last pulse. Once this happens, primary cannot be recharged properly to the nomal volatge during th 1000ms before injection. First pulse is always correct.20:52 Checked B1 LBDS synch with buckets 1, 501 and 34500, after 1.5 us adjustment by Etienne. Synchronisation now OK for both dump systems. 02-12-09 LHC status

LBDS 02-12-09 LHC status

Philippe Baudrenghien RF work from 16:30 to 19:30 COGGING: move reference ring 2 by full two RF periods (5 ns). Check with CMS. Told that we were left with remaining 880ps. Move phase further by 120 degrees. CMS intersect error now 15 ps. May not stay that well centered for long.... CAPTURE: adjust gains of Phase PU chain to prepare for higher bunch intensity. So far it had been optimized for 5E9, now adjusted for 2E10 per bunch. This was first done with circulating beam in ring 1 and 2 (~ 3E9). Then we requested Circulate and Dump conditions to fine-tune capture. Finished in Ring1 by 19:30. Waiting for handshake on Beam 2 till 20:05. 20:30 still no Beam back in ring2. Beam dump problem. We leave... Philippe Baudrenghien 02-12-09 LHC status

01:10:36 18 kV fault at Pt 1- all FMCM triggered the BIS. MPS Checks: threshold studies for BLM's at last IR7 TCLA (tungsten) collimators, IR7 primary collimators, and IR7 skew primary collimators. Create known beam loss by scraping full beam with collimator jaw moving at 2mm/s. No very big dependence on angle. Example for TCLAs we see a factor 2 for 600 murad angle change of collimator jaw. 01:10:36 18 kV fault at Pt 1- all FMCM triggered the BIS. 02-12-09 LHC status

18 kV cut 01:23 18 kV Cell SEM12 – point 1 Short circuit - breaker Auto-transfer not successful SIG not available to Meyrin site Diesels cut in OK EL went manual on transfer connected Meyrin to Prevessin via MP6 limited power 40 MW LHC Lost 6/8 sectors – external on PCs Cryo OK LINAC2, booster, PS dropped SPS OK – flat lined 02-12-09 LHC status

02-12-09 LHC status

02-12-09 LHC status