XFEL Collimation and Beam Switchyard Vacuum Issues

Slides:



Advertisements
Similar presentations
HISTORY, EVOLUTION AND DESIGN OF THIN SEPTUM MAGNETS AT BNL Michael Mapes The 14 th ICFA mini-workshop on septa devices.
Advertisements

RF Cavity Module G. Gosling Dept. of Mechanical Engineering Imperial College London.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
The Preassembling Installation Survey & Alignment Accelerator Center of IHEP Qu Huamin 2006 / 4 / 27.
Upgrade Plan of KEKB Vacuum system Pre-kickoff KEK1 Y. Suetsugu KEKB Vacuum Group Contents Challenges for vacuum system Designs for.
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Progress and Plan for Superconducting RF Cavity RF Group.
MICE RF Cavity Design and Fabrication Update Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 27, 2004.
TAGGER MAGNET DESIGN Presented by Tim Whitlatch Hall D Tagger Magnet Design Review July 10,
Engineering Integration of the Double- Double Bend Achromat (DDBA) into the Diamond storage ring Jim Kay Diamond Light Source Low emittance ring 2013 workshop.
Vacuum Pressures at IR Contents Y.Suetsugu KEKB Vac. Group 1.Outline of Vacuum System at IR 2.Behavior of Pressures 3.Remedies for Heating of Vacuum Components.
Vacuum system in the main Linacs C. Garion CERN/TE/VSC CLIC09 workshop, October.
High Density Cooling Air conditioning for high density applications
1 Tetsuhiko Yorita JASRI/SPring-8 Acc. Div. SPring-8 Vacuum System Contents - Outline of Vacuum system - Pressure behavior - Some topics.
1 BROOKHAVEN SCIENCE ASSOCIATES Vacuum Systems H.C. Hseuh, Vacuum Group Leader 8 th ASAC Meeting for NSLS-II Project May 10-11, 2011.
SuperFRS Multiplett and Dipole Vacuum Interfaces Multiplett: Insulation vacuum: Insulation Vacuum Pumping flanges: Two CF flanges of the size DN160 must.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
DR Vacuum Component Overview April 25, 2012 Joe Conway.
Impedance and Collective Effects in BAPS Na Wang Institute of High Energy Physics USR workshop, Huairou, China, Oct. 30, 2012.
Review of the European XFEL Bunch Compression System Summary Torsten Limberg.
CLASSE prototype: mechanical concepts G. De Michele, EPFL-PSI-CERN on behalf of CERN team SLAC, 16 th April, 2012.
BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.
SuperKEKB Vacuum System - for the positron ring - Y. Suetsugu KEKB Vacuum Group Outline Design and production status of key components Beam pipes for arc.
G5 Beam Line Vacuum System. G5 Beamline Vacuum System Design  Bakeable and Particulate free to Class 100 Clean Room quality Require Clean room QA and.
ELENA Vacuum System R. Kersevan, TE-VSC-IVM R. Kersevan, “ELENA Vacuum System”, - ELENA Project Review, Oct14-15, 2013, CERN.
1 Progress of IR Vacuum Chambers Chen Peng May 11,2007.
XFEL-INJ1/2 DUMPS Remarks / Requirements, Injector Beam Dynamic Review Meeting, DESY, Mon. 23. October 2006 ‹#› XFEL - INJ 1/2.
41 st IUVSTA Workshop, Brdo pri Kranju, 21/06 – 24/06/2004 L. Schulz SLS Vacuum System Lothar Schulz Theo Bieri Nazareno Gaiffi Martin Steinacher.
1.3GHz Input Coupler for ILC
Plans for in-situ coating with a robotic mole at BNL Ady Hershcovitch 1, Michael Blaskiewicz 1, Wolfram Fischer 1, H. Joseph Poole 2, Mark Erickson 2,
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
Study Plan of Clearing Electrode at KEKB Y. Suetsugu, H. Fukuma (KEK), M. Pivi, W. Lanfa (SLAC) 2007/12/191 ILC DR Mini Work Shop (KEK) Dec.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Eric Montesinos - CERN - First SPL collaboration meeting - CERN December 11th 2008 First SPL collaboration meeting Experience with the LHC Main power Coupler.
Accelerator Vacuum Systems at DESY M.Seidel, DESY Workshop on Vacuum Systems of Synchrotron Light Sources Barcelona,
Sven Lederer (MVS) Lutz Lilje (MVS) Torsten Wohlenberg (MVS)
1 Vacuum chambers for LHC LSS TS Workshop 2004 Pedro Costa Pinto TS department, MME group Surface Characterization & Coatings Section.
SKEKB Mini Work SKEKB Vacuum System – Arc Section – Contents Y.Suetsugu KEKB Vacuum Group 1.Beam Chambers 2.Pumps: Pump, Pressure,
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.
RFQ – Design, Components and Fabrication 1 We aim to design and manufacture a Radio Frequency Quadrupole (RFQ).
7-Sep-2011 CLIC RF Structure Development Meeting «BE/RF» TD26 WITH COMPACT COUPLER FOR CLEX (TD26 CC SiC) ENGINEERING DESIGN this structure will be used.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM25 at RAL, UK November 6, 2009.
MAIN LINAC CRYOMODULE DESIGN REVIEW INPUT COUPLER September 5, 2012V. Veshcherevich.
Preparation procedure and RF processining of cERL-ML power coupler at KEK Hiroshi Sakai, Takaaki Furuya, Masato Sato, Kenji Shinoe, Kensei Umemori, Kazuhiro.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
ESS DTL: Prototyping M.Comunian - F. Grespan – P. Mereu Lund– 10/04/2013F.Grespan.
2008/12/10 INFN R&D on Low Impedance Beam Chamber and Components Y. Suetsugu, for KEKB Vacuum Group Contents Introduction Beam Chamber Components Connection.
Vacuum conditions in PANDA pbar-line Alexander Gruber, SMI, Vienna, Austria.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Extra / Discussion Slides. 2 1.Helium Top Fill Port Add extra CF/ISO flange as collar so that the weld-region is not disturbed 2.Helium bottom FillCF.
325 MHz Superconducting Spoke Cavity Coupler status. T. Khabiboulline Power Coupler design for Superconducting Spoke cavities. Originally.
Two-beam module layout
LCWS11 WG4 Fully featured accelerating structure engineering design
Vacuum System P. Chiggiato TE-VSC
HFM Test Station Main Cryostat
RTML Vacuum System RDR Summary FermiLab October 24, 2007
General remarks about the HESR and PANDA vacuum system
Options and Recommendations for TL and Dumps
Teleconference ACS – FREIA 18th April 2017
Challenges of vacuum chambers with adjustable gap for SC undulators
Preliminary Y-chamber specifications – First draft
Vacuum System Failures at HERA
EBTF Design Review Technical Meeting Group
CEPC Vacuum System Dong Haiyi 2017/11/5.
XFEL Vacuum System Commissioning
V. Veshcherevich Cornell University
IHEP Cryomodule Status
XFEL Bunch Compressor BC1 and BC2 Vacuum Issues
Single Detector Design
Presentation transcript:

XFEL Collimation and Beam Switchyard Vacuum Issues Torsten Wohlenberg XFEL Beam Dynamic Meeting

Collimation and Beam Switchyard general remarks Lengths of the Collimation and Beam Switchyard vacuum system : Collimation: total length ~ 226m Beam Switchyard: total of TL+T1+T2~150m+132m+112m~394m (Description from Winfried Decking http://www.desy.de/xfel-beam/data/component_list.xls )

Collimation and Beam Switchyard general remarks Vacuum requirements after the COLD LINAC: Pressure needs to be in the range of 10-10 mbar the next 30m of the collimation beam line (next to cold sections) Pump system: sputter ion pumps and titan sublimations pumps 30m beam line after the COLD LINAC have to be particle free : The design of all vacuum components needs to be according to the particle free conditions. Early discussion of the concept of all components including beam diagnostic is necessary! All vacuum components have to be cleaned under the particle free conditions (clean room class 100). Installations needs to be done under local clean room class 100 conditions.

Collimation and Beam Switchyard general remarks Vacuum requirements after 30m in the Collimation and Beam Switchyard: Pressure requirements are much relaxed in comparison to the storage ring pressure. The range of 10-8 mbar after 30m of the COLD LINAC seems to be acceptable. Pump system: sputter ion pumps (60 l/s )

Collimation and Beam Switchyard general remarks Beam line design: Inner diameter of the beam line is 40mm(?) for the main parts of both sections. Copper tubes are connected with stainless steel conflate flanges (inductive brazing) - also copper coated stainless steel will be used for some components. copper tube vacuum chamber at FLASH inductive brazing

Collimation and Beam Switchyard general remarks RF losses minimizing : To minimize the RF losses all bellows behind 30m from the COLD LINAC will be shielded, also the pump ports and gate valves. Early discussion of the concept of these components including beam diagnostic is necessary. The goal should be to minimize the RF losses where it is technical praticable !

Collimation and Beam Switchyard special components Collimator section: Four main collimators, tow for each beam direction (horizontal, vertical) Choose Ti for high stress resistance in case of mis-steered beam hit (N.Golubewa, V.Balandin) Important as well: acceptance of significant average beam power from dark current (don’t know how much, planning for a few kW) Concept: Ti insert with brazing connection to water cooled Cu block Ti-Block with tapered beam holes Cu- Block with water channels Principe simular to FLASH

Collimation and Beam Switchyard special components Switchyard section: Ceramic vacuum kicker chamber: inner diameter 18-20mm (?) abt. 500mm long with thin coating inside of stainless steel or titaniumnitrid (under development). For XFEL we need 48 devices Kicker chamber with kicker at FLASH Ceramic chamber with onside coating

Collimation and Beam Switchyard girders frames and support Support for the vacuum chambers will be designed by the vacuum group. In the concept to mount the collimator section and the switchyard from the top or button, all girders and frames or concrete pylon with girder should be designed by the group MEA(?). We prefer to mount these systems from the button in analogous manner to BC1 and BC2: concrete pylon with girder are cheaper then a frame with girder construction! An examination with respect to stability, oscillation behavior etc. must be done in both cases!

Collimation and Beam Switchyard schedule Draft: Design of collimation and beam switchyard~ 1.5 year Fabrication of all components ~ 1.5 years 2008, A rough concept should be settled for the girders/frames concept including electronics and diagnostics as well as part of the layout of the components.→ layout for the arrangement of the components should be available! 2009, The detailed concept for the layout of the components, electronic concept and the girder and frames concept should be finished.

Collimation and Beam Switchyard open issues Do we have to mount both system from the top or from the bottom? → we prefer to mount these systems from the bottom ! Do all components need to be copper coated in both systems? Can the RF-shielding remain the same as for FLASH or do we have to design a new concept for the flange connections, bellows, valves and pump connections? What diagnostic installations will be needed next to the beam line?

Collimation and Beam Switchyard Thank you for your attention!