Mississippi Riverbank Project (Final Presentation) May 14, 1999 Architect: . . . . . . . . . . . . Steve GEORGALIS . . . . . . Georgia Institute of Technology Structural Engineer: . . . Tomo CEROVŠEK . . . . . . University of Ljubljana Construction Manager: . Jacky HO . . . . . . . . . . . . . . Stanford University Owner: . . . . . . . . . . . . . Ali AL-ALI . . . . . . . . . . . . .
Agenda Project Introduction Four Preliminary Design Alternatives Final Design - A / E / C Solutions and Interactions Learning Experience
Introduction Building for Riverbank University in Sacramento Virtual Project (Year 2010) Produce 4 Alternatives and 1 Final Design Practice A/E/C Interaction
Requirements Architectural Requirements Structural Requirements Maintain Footprint & Transportation / Circulation Occupancy, Security, Environmental (3 stories, total height 35’) Structural Requirements Load: Earthquake and Total Height of 35’ Construction Requirements Budget : $5,500,000 (Structural $550,000) Time Budget : 12 months (ready in May 2012)
4 Alternatives 1 2 3 4 $4,500,000 $4,900,000 $4,700,000 $4,100,000
Building Site
Alternative 1
Alternative 1
Alternative 2
Alternative 2
Alternative 3 3rd floor
Alternative 3
Alternative 4
Reasons for choosing Alternative 2 Owner’s Decision Aesthetic and Challenging Design Team’s Preference Attracting Glass Atrium Challenging Structural Systems Feasible in Time and Cost
Further Iterations and Evaluations Meeting with Owner Height Limit Faculty Lounge Atrium Design Structural Materials Revised design Feedback on cost Suggestions and changes Revised design material choice E C Revised design Feedback on cost and constructibility
Discussion on Faculty Lounge
Discussion on Structural Materials Prefab Steel Frame for Atrium Cast-in-place Concrete Columns
Final Design
Final Design
Architecture: 1st Floor
Architecture: 2nd Floor
Architecture: 3rd Floor
Architecture: Section
Architecture: Footage Evaluation
Engineering: Structural Model
Engineering: Structural Model
Engineering: Loads Live Loads: Dead Loads: Classrooms: 40 psf Offices: 50 psf Halls: 100 psf Dead Loads: Self weight, floor and partitions 30 psf MEP 10 psf Seismic Load: zone 3 (solid rock)
Engineering: SAP2000 Model
Engineering: Framing System
Engineering: Moments of the Plate
Engineering: Mode Shapes
Engineering: Moment Diagram
Typical members and connection Beam spacing: 19’ Typical column: 18’’x18’’ Reinforcement: 3.5% Typical beam: 16’’x20’’ Foundations: 4’x4’
Construction: Cost
Construction: Cost Breakdown
Construction: Cost Breakdown
Construction: Schedule Total Duration: 10 months Milestone 1: Start of Concrete Superstructure Milestone 2: Finish of Concrete Superstructure Milestone 3: Finish of Glass Atrium
Construction: Milestone 1 June 20, 2011 Completion of Foundation and Auditorium Start Concrete Frames
Construction: Milestone 2 Sept 20, 2011 Completion of Concrete Frame Start Atrium
Construction: Milestone 3 Dec 10, 2011 Completion of Atrium Continue Interior Construction
Construction: Site Layout
Construction: Equipment Excavation 90,000 CF of soil Excavator Dump truck Cast-in-place Concrete 3,500 LF of Columns and Beams Pumper Truck Concrete Mixer Atrium Steel Frame Max height: 36 feet Crane Truck
PUT A FINAL MODEL HERE FOR WRAP UP
Learning from AEC A A C C E E Roles of A / E / C New communication technology New team working environment Using 3D Model A E C A E C