DEVELOPMENT OF OPF HOUSING SCHEME ZONE-V, ISLAMABAD (PACKAGE-I)

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

CONTRACT COSTING Contract costing is that form specific order costing which applies where the work is undertaken according to customer’s requirements and.
CONTRACT PAYMENTS & VARIATIONS
VISION & MISSION OF KeNHA VISION : Quality, safe and adequate National Road Network. MISSION : Provide quality National Road Network for sustainable social.
Troubled Debt Restructuring (TDR)
 Fulfillment of Contractual obligations within the stipulated time frame is the essence of any contract.  LIQUIDATED DAMAGES (LD) are charged as a compensation.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
COSTS AGREEMENTS AND DISCLOSURES BAR ASSOCIATION CPD SEMINAR 2 AUGUST 2007 By Roger Traves SC.
Completion Outstanding work and Remedying Defects In order that the Works and Contractor's Documents, and each Section, shall be in the condition required.
Resolve Business Disputes and Select and Prepare a Construction Contract Lesson Seven Cert IV - M. S. Martin March 2012.
5/25/ Introduction  SLB is defined as the temporary exchange of securities with an obligation to redeliver the same securities in the same number.
Time for a new standard - AS General Conditions of Contract
Circular A-110 Everything You Didn’t Want to Know.
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT 20. Claim, Disputes and Arbitration [Construction Contract Administration]
ISLAMIC UNIVERSITY OF GAZA FACULTY OF ENGINEERING CIVIL ENGINEERING DEPARTMENT Defects Liability [Construction Contract Administration] Chapter 11.
Construction Contracts
Performance of Contractor Agreements: Practical Issues Kyiv, September 2012 Kristina ARTEMENKO EU Project "Harmonisation of Competition and Public Procurement.
Structures for Investors Presented by: Kerrie-Anne Bailey KAS Tax & Business Solutions Phone: (07) April.
> taking best practice to the world International Experience with Performance Based Maintenance Contracts.
Completing the State Aid Payment Request (SAPR). Tips Each spring check on the State Aid Finance web page for the current version of the State Aid Pay.
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
Compensation events and claims Presented by Prof. Khem Dallakoti.
Special Rating Areas Financial Roles and Responsibilities January 2014.
CONSTRUCTION CONTRACTS DOCUEMENTS
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
1 March 20, 2014 Rural Water Supply and Sanitation Project for Low Income States March 20, 2014.
Construction Contracts
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
National Department of Housing Thubelisha Homes Voluntary Liquidation Closure Progress Status Report 19 February 2014.
Varteg Hill – Coal Recovery and Land Reclamation Pre-Application enquiry by Glamorgan Power Ltd. Members Seminar 31/3/14.
1 DUAL LISTED COMPANIES (DLCs) Jon Webster. 2 DLC by Agreement … contractual arrangement between two companies under which they operate as if they were.
Joint Report to Select Committee on Appropriations by Northern Cape Department of Health Northern Cape Department of Roads & Public Works supported by.
Contract Pricing Principles. What is pricing? Pricing: The process of establishing a reasonable amount or amounts to be paid for supplies or services.
Technical Assistance Office TCP Projects 2005 Contractual and Financial Management Administrative and Financial Handbook Prepared by IA, 14/12/2001 SOCRATES.
Joint Energy Auction Implementation Proposal of PG&E, SCE and SDG&E California Public Utilities Commission Workshop – November 1, 2006.
Margin Trading System Based on Securities (Leveraged Markets and Pledging) Rules, 2011 and Concept Paper.
Accounting (Basics) - Lecture 5 Impairment of assets
Mike Ellis Executive Director – Property + Projects
PRESENTATION TO THE STANDING COMMITTEE ON PUBLIC ACCOUNTS (SCOPA) ON IRREGULAR, FRUITLESS AND WASTEFUL EXPENDITURE by SANRAL 16 November 2016.
Chapter 9 Impairment of Assets.
Auditing & Investigations II
Administration of a FIDIC Contract - Project Control
Fair Go Rates System Dr Ron Ben-David Chairperson
Administration of a FIDIC Contract - Commencement Date to + 28 Days -
Bills of Quantities Introduction to FIDIC - Bills of Quantities -
Financial Clauses and Procedures.
Revised Features Securities Lending & Borrowing (“SLB”)
Administration of a FIDIC Contract - Financial Management
Community pharmacy in 2016/17 and beyond – final package
Extension of time and how it is granted to a contractor (Referencing JCT 2005)
Section 28 Employee Benefits
Report back on the review of budgetary allocation for Land Reform
PRE-BID MEETING ITB UNDP Design and Construction of a new medical warehouse in Bissau, Guinea Bissau 15th August 2017 Presented by Antoine Fadoul UNDP-
Financing Land Development Projects
COST PLANNING AND ESTIMATION
Completing the State Aid Payment Request
Fair Go Rates System Dr Ron Ben-David Chairperson
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
ENGINUITY TUTORIAL Job Risk Copyright Virtual Management Simulations.
Provisions, contingent liabilities and contingent assets
In The Name of ALLAH the Most Gracious the Most Merciful
ARCH 435 PROJECT MANAGEMENT
Public works contract Clauses 10.5 & 11.5 Explored
COGAIN Kick-Off 5-6 September, 2004 FINANCIAL GUIDELINES
EASTERN CAPE HOUSING DELIVERY
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
AUTHORS: JUAN GARCIA RYAN CHERRINGTON LEE McMELLON.
Bridge forms critical path (6 months to construct)
Presentation transcript:

DEVELOPMENT OF OPF HOUSING SCHEME ZONE-V, ISLAMABAD (PACKAGE-I) (2 May 2017)

Satellite View as on Dec 2015 OPF Housing Scheme Zone-V, Islamabad Satellite View as on Dec 2015

SALIENT Cost of the Proj : Rs 2404 Mn Date of Start 08-Sep-2008 Date of Completion 28-Feb-2011 (30 Months) EOT (x5) 30-Dec-2015 (57 Months) (Total 87 Months till 30 Dec 15) Scope of Work 8 Blocks and 8 Main Roads 6.4 Km Paved Roads* 23.17 Km Paved Streets* Designed by NESPAK; EACL; OPF Total Area 4600 Kanal

SALIENT Site handover 3925 Kanal (Sep-08) – [Bal: 675 Kn (15%)] 193 Kanal (Jan-11) – [Bal: 482 Kanal (10%)] 100 Kanal (Jan-16 - after latest EalT) – [Bal: 382 Kanal (8%)] Total 4218 of 4600 rel Consultant/Supervision NESPAK (Sep 08 to Jun 09) OPF (Jul 09 to Jan 10) EACL (Feb 10 to Sep 14) OPF (Oct 14 till date) Suspension Periodic suspension by OPF for Dam, Block D, Block H Suspension due to litigation (Jun-Jul & Sep 14)

PROGRESS Progress - 98% Item Progress (Completed) Earth Work Asphalt Bal Works Svc incl Ft Path Litigation Item Progress (Completed) Earth Work (149 Mn Cft) 100% Sewerage (58 Km) Water Supply (35 Km) 92% Drains (2.9 Km) Foot paths (54 Km) Roads (26.5 Km) Bridge (01) Soft Landscaping 16% Hard Landscaping 0% 100 Kanals handed over on 6 Jan 2016 Progress - 98%

01: OUTSTANDING AMOUNTS Ser Measured Works Rs (Millions) FWO’s Remarks Work done   a. Total work done as per BoQ rates after rebate 2373.319 After rebate (6.936%) b. Amount paid by client 2317.427 Balance outstanding 55.892 IPA 25 submitted on 22.07.16 2 Price Adjustment a. Price Adjustment due 335.147 Inclusive of Adjustment against IPA 25 (as per OPF formula contrary to Contract allowance) 290.564  3. 44.583  4. Measured works Subtotal (items 1-2) 100.475

02: UNSETTLED AMOUNTS Ser Disputed Amounts Rs (Millions) FWO’s Remarks 1 Price Adjustment   a. Price Adjustment as per Contract allowance 417.897 Due to conflicting view on bid date between OPF & FWO as per Contract clause 70 b. Price Adjustment as per OPF assessment 335.147 OPF considering bid date 11 Aug 2008 after giving rebate Price Adjustment disputed amount 82.75 Bid submission date 24 Jul 2008 2 Profiling of plot areas a. Profiling of plot areas (initial FWO valuation) 56 b. Profiling as vetted by EA Consultants 47.2 Duly approved by OPF BoG in 02 Nov 2012 meeting c. Amount paid by client Balance outstanding Payment due since Jan 2013 3 Damage Rectification a. Damages repair due to insufficient drainage capacity 143.219 The site is a flood plain and consultants failed to provide sufficient drainage. New 32 drainage/ protective structures were built w.e.f May 2015 b. Amount paid by client (Notified)

02: UNSETTLED AMOUNTS Ser Disputed Amounts Rs (Millions) Contractor Remarks 4 Prolongation / Resource Idling   a. 59 months prolongation 533.183 Projected forecast over Rs 433 Mn and Rs 33 Mn already forwarded to OPF in Jul 2014 and Oct 2014 against Prolongation and Involuntary Idling respectively b. Rise in materials prices not covered within Price Adjustment Mechanism (Ser 1) 97.586 Covering the granted EOT period c. Subtotal Item 4 630.769  5 Total Unsettled and Un-agreed Amount (items 1 to 4) 903.938 A marginal figure would have accommodated by FWO within its risk but the scale of uncertainty is beyond reasonable comprehension of a competent contractor

MATTERS OF CONCERN Site constraints Site is essentially a flood plain with natural flow lines now interrupted after construction Rain damages being permanent feature on site seriously questions adequacy of design. FWO has made it clear to the Employer that there is no provision for maintenance in the BoQ as it stands, therefore FWO cannot be held responsible for future damages that may occur. Future site re-profiling either by OPF or residents will be detrimental to roads Opening of streets and areas by services network providers such as IESCO etc is a serious matter of concern for FWO

MATTERS OF CONCERN Payments Payments have not been timely and in accordance with the contract terms/ commitments leading cash flow shortfall against the project impairing FWO’s capacity to undertake further works It took OPF seven months to clear payments (466 Mn) for Works completed in Dec 2015 (Payment initiated in Jan 16 (vide IPA 23 and latest payment received in Aug 2016). IPA-25 (62 Mn) along with its Price adjustment (18 Mn) non-contractually returned to FWO undetermined. A substantial sum of Rs 904 Mn against variations remains undetermined and unsettled despite notifying this effect to OPF numerous times. A considerable amount (124.426 Mn) retained against Security which has now gone way beyond planned period of 3 years

MATTERS OF CONCERN Takeover & Defects Liability OPF’s reluctance to take over completed Segment-I works is delaying commencement of Defect Liability Pd. Circumstances beyond FWO control impairing its capacity to undertake further works

RECOMMENDTIONS Segment-I Takeover, which comprises 3925 Kanals fully developed from FWO and settle final accounts. Although numerous EOTs have been granted to the Contractor but no corresponding VOs (Variation Orders) have been issued, allowing Contractor to recover the over spend. FWO cannot operate on an indefinite Defects Liability Period and it is for this reason that takeover should commence and conclude as a matter of urgency Segment-I works should not be linked to the undeveloped land which is being released after Extension of Time (EOT) which expired on 31 Dec 2015. If this proposal is not adopted, FWO will not be able to provide competitive rates and allocate resources as the legacy of Segment-I will continue to impact productivity. Therefore, a clear line must be drawn between these two work streams

RECOMMENDTIONS Completed works (Segment-I) are ready for final measurement, needs settlement in full Release of Retention Money against Bank Guarantee FWO liabilities and re-evaluate the project cost incorporating scope change and time prolongation. Corresponding VOs to be issued. (refer Appendices) Speedy settlement of contested amounts including timely payment of agreed Price Adjustments and surplus soil All new works (Segment-II) to be carried out under a separate order on market rate Employer to ensure no damages are caused by svc network providers

RECOMMENDTIONS Effective security be ensured to avoid theft / damage to build assets. Independent maintenance contractor to be deployed for regular de-silting. Strict control on heavy vehicles using the roads. Special measures to be taken for levelling of terrain. Regarding development of newly released land, FWO offers conditional cooperation until and unless all with held payments are released, unapproved variations are settled and Segment-I is taken over.

THANK YOU