Summary of Week 13 G. Arduini, B. Holzer

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC progress Report LHCC Wednesday 23 rd March 2011.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ion Commissioning: Thursday & Friday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Wednesday September 14th
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
Machine availability reaching well over 80%
Summary of Week 11: 14 – 21 March
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
LHC commissioning Week 38
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 36 plan Todo’s: And also: 12+b injection.
Week 35 – Technical Stop and Restart
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Planning at 5 o’clock meeting Friday
LHC Morning Meeting - G. Arduini
Finally.... We had to wait a long time.... We had many problems....
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
Yesterday morning Held 1647 for a while – SPS kicker problem
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Summary week 18 Intensity ramp up & production
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
MD Planning Fri – Sat (1. – 2.7.)
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
LHC - Week 38 Technical stop: Katy Foraz
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
Summary Tuesday h23: Machine closed. Precycle started.
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Tuesday 20 September 2011.
Wednesday 23/2 Thanks CRYO!!!.
Thursday
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Monday 10th December - morning
Tuesday 6th April 8:00 Injection studies 16:00 RF studies
Tuesday
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Summary of Week 13 G. Arduini, B. Holzer Main aim: Recovery from Technical stop and start preparations for high intensity

Sun 3/4 – Mon 4/4 08:00-15:30: Collimation setting-up at 450 GeV and 3.5 TeV 15:30-17:30 Ramp-down and start injection setting-up with 75 ns beam 17:30 – 05:50: Electrical problem (400 V transformer tripped 3 times on temperature interlock) in UJ76 and recovery: Collimator control expert working the whole night to recover the correct position of the collimators Vacuum, current leads temperature controls, QPS, ....

Technical stop from Monday 28/3 (6 AM) to Thursday 31/3 (6 PM): Anti e-cloud solenoid wrapping at point 8 and test of all points. Replacement of the power switches on quench heater power supplies (last sector) X ray of QRL in sector 45  confirming problem on bellow in line C Replacement of the compressor at point 4 Control cabling for the vacuum pump in sector 45 Survey and alignment of 3 collimators following beam measurments during the start-up Delay in the recovery of the Cryogenics for Sector 45 and problem on generator MKB.B2  End of technical stop on Friday 1/4

Friday 1/4 Cryo OK at 11:00 for Sector 45 Debugging the machine without beam in the shadow of the SPS recovery: Collimator controls TCDQ controls QPS communication Injection kicker control card (Beam 1)  access Short to ground detected on circuit RQTD.A45.B1  access SPS recovery delayed by: outgassing of MKDH and MKE kickers following interventions to replace magnets and install new scraper Beam based re-alignment of a quadrupole replaced during the technical stop (likely issue in the fiducialization of the magnet)

Installation of thermal protection of current leads of 600 A during TS Problem with RQTD.A45B1 Installation of thermal protection of current leads of 600 A during TS

Verifications with beam Finally beam on at 22:00 on Friday New calibration curves for lattice sextupoles, measurement and correction of chromaticity Before correction After correction

Collimation set-up (F. Burkart, G. Valentino, D. Wollmann) Set-up of TCLA.A7R7.B1, TCTH.4L2.B1, TCSG.A5L3.B2 re-aligned during TS. Loss maps: TGSG.D5R7.B1(BLM at the TCSM.D5R7.B1 behind) only factor 2 below TCP which causes a 0.5% leakage into the TCTs in IR8

Collimation set-up (F. Burkart, G. Valentino, D. Wollmann) Re-setup of skew B1 collimators: The main changes here were found in the beam sizes at: TCSG.A6L7.B1 (delta -13%), which relates to a 0.76 mm smaller half gap after the setup. TCSG.A4R7.B1 (delta -14%), which relates to a 0.95 mm smaller half gap after the setup. Beta-beating?  measurement at 450 GeV Before set-up After set-up

Collimation set-up (F. Burkart, G. Valentino, D. Wollmann) TCTH.4L2.B1 (measured beam size ratio 121%/137% [new/old]) and TCLA.A7R7.B1 (104%/128%) seem to be parallel to the beam after the re-alignment during the technical stop. The TCSG.A5L3.B2 (126%/174%) seems to have still a misalignment of ~560urad. We found changes of the beam offset at flat top for the 3 re-aligned collimators up to 404um. The measured beam size shrank from about max 229% to smaller than 140%. Loss maps at 3.5 TeV (unsqueezed) with the new settings for the 3 collimators seem to be fine (no unexpected losses). The detailed analysis will be performed offline. ToDo: incorporate the new settings of the skew collimators and the re-aligned ones into the injection beam processes re-setup the TCTH.4L2.B1 squeezed and at collision. incorporate the new collimators settings into ramp functions qualify the new settings at injection with B1V and off momentum (pos and neg) re-qualify collimation at flat top (positive off-momentum), squeezed (all cases) and in collision (all cases)

Injection region aperture check (B. Goddard) Scanned all vertical phases 0, 30, ...,330 deg B1 and B2 amplitudes upto 6-7 sigma (limited by losses on TDI and not wanting to put too large oscillations through arcs). No sign of any aperture restrictions in area between MSI exit and Q5 where intermodule inserts were added in 2010/11 TS Plots compare measurements end 2009 and today - solid points where aperture was reached, V error bars show where it was not. In this regard OK for injection of higher intensity

Injection setting-up (V. Kain, J. Uythoven, D. Valuch) Abort gap cleaning working and tested for both beams with 'first' and 'last' bunch in the machine and tests with debunched beams. Tested BPMS with 3 nominal bunches in the machine: OK Injection gap cleaning tested with a series of pilot injections for both beams: OK Then tried injection of 24 bunches, as before TS. Losses much higher than before and needs to be sorted out before being able to take reference loss measurements of TDI BLMs with the different cleaning configurations.

Effect of CMS solenoid OFF Injection of 2 trains of 24 bunches each with 75 ns spacing in an unconditioned area (close to Q3) because of the presence of stray fields from CMS solenoid

Issues Still noise on wire scanners B1 Timing alignment errors between BICs observed. Being monitored Trips of RF cavity 6B2 (power reflected from the cavity to circulator) Orbit oscillations due to RT trim appear intermittently Noise on 60 A power converter (RCBV16.L1B2)

SPS status 75 ns beam OK up to 4 trains (96 bunches) 50 ns beam OK up to 2 trains, still MKDH outgassing when 4 trains are injected (144 bunches) 25 ns to be re-tested today

Plan Sun N Beta beating measurements at injection Mon M Injection setting-up (24+ bunches - 75 ns) A Collimation setting-up (TCT) and loss maps Scrubbing of IR5 with 75 ns beam Next: Completion of setting-up of the collimators (functions generation and validation) Setting-up of injection with 75 (ongoing) and 50 ns beams Scrubbing with 50 ns beam