HIE-ISOLDE Project: Status Report

Slides:



Advertisements
Similar presentations
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
HIE-ISOLDE Project: Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January 2013 Yacine Kadi.
201 MHz NC RF Cavity R&D for Muon Cooling Channels
HIE-ISOLDE contribution packages M. Pasini BE/RF.
1 Nb Sputtered Cu QWR: a 20 years experience from an idea to the routine beam acceleration A.M. Porcellato S. Stark V. Palmieri F. Stivanello.
Status of crab crossing studies Presented by NAKANISHI Kota (KEK) 2008/1/25.
Summary of WG 2 - cavities W. Weingarten 15th SPL Collaboration Meeting CERN - 25/26 Nov Cavity WG.
HIE-ISOLDE Project Status Report
Revised SPL-study work-plan W. Weingarten 3 May 20101SPL Cavity WG Meeting.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
Accelerator/ Medium Beta Cavities Paolo Michelato INFN Milano - LASA April 21, 2015.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
New plans for high power RF tests places at CERN O. Brunner BE/RF/KS – January ‘10.
October, 2009 Cost of SRF Components Gary McIntyre October, 2009 Internal Review.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
High power RF tests places at CERN O. Brunner, CERN 4th SPL Collaboration Meeting jointly with ESS.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
TE-CRG Activities D. Delikaris, TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
HIE ISOLDE commissioning of the cryogenic control system installation at CERN. LNL-INFN 22/07/2015 Dr. Marco Pezzetti (CERN )
O. Kester, NuSTAR annual meeting, 27/02/2013
7th SRF Materials Workshop FRIB SRF Cavities 7/16/12 Chris Compton.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
SRF Test Facilities – Functions and Costs Alexander Romanenko Test Facilities Review 17 Mar 2015.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Infrastructure status and plans at CERN 1) W. Weingarten/CERN TTC Milano 28 February - 3 March W. Weingarten/CERN 1)Most of the slides are based.
ASTA Latest Update E. Harms April Photoelectrons first produced at ASTA on 20 June 2013 –Molybdenum (uncoated) cathode ‘Routine’ Electron operation.
WP1: Superconducting Cavity Developments and Tests Walter Venturini Delsolaro Mid Term Review Meeting, 26 September 2012 CATHI Marie Curie Initial Training.
Guillaume Olry on behalf the IPN Orsay SPIRAL2 team TTC Meeting – Milan, 28 Feb-3 March 2011.
HIE ISOLDE Linac Short Technical Description W. Venturini Delsolaro Material from: L. Alberty, J. Bauche, Y. Leclerq, R. Mompo, D. Valuch, D. Voulot, P.
Crab Cavity Technical Coordination meeting:
CERN – Zanon discussions
WP5 Elliptical cavities
at STFC Daresbury laboratory
ILC-SCRF Test Facilities considerations
HIE-ISOLDE Report Jose Alberto Rodriguez on behalf of Yacine Kadi and the HIE-ISOLDE project team.
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
on behalf of the RF group
SPS cryogenic proximity equipment and SM18 validation
THE HIE-ISOLDE SUPERCONDUCTING CAVITIES:
Update on HW commissioning
Hosting Orsay Walid KAABI
ILC Cryogenic Systems Draft EDR Plan
HIE-ISOLDE Status Report
UK RFD Pre-Series cryomodule
SRF Section Cuvée 2014.
HIE-ISOLDE Project Status Report
HIE-ISOLDE Project: Planning & Resources
HIE-ISOLDE Status & Summary of HIE-ISOLDE SC
Operation experience of cryogenic system and cryomodules for the superconducting linear accelerator at IUAC, New Delhi. T S Datta ( On behalf of Cryogenics.
HIE-LINAC status report
IHEP Cryomodule Status
Report on HIE-ISOLDE Status
CERN’s MidTermPlan and the consequences for HIE-ISOLDE
HIE-ISOLDE contribution packages
Cryomodules Challenges for PERLE
Prototype cryomodule development
as a prototype for Super c-tau factory
SNS-PPU upgrades the existing accelerator structure
QCM and C50-12 Status Update
Presentation transcript:

HIE-ISOLDE Project: Status Report EXTRA COSTS AND ADDITIONAL RESOURCES CERN, 29 January 2013 Yacine Kadi

Phase 1 Updated Schedule 2013 2014 2015 J F M A S O N D LS1 & shutdowns   Refurbishment of the old ALEPH Cryo-Plant Compressor installation and commissioning Cryo-plant installation (cold box and transfer line) Cryo-plant commissioning HIE-ISOLDE SC Linac Cryomodule 1 Tests (SM18) Cryomodule 2 Tests (SM18) Cryomodule 1&2 installation (ISOLDE) Cryomodule 1&2 Commissioning (ISOLDE) HIE-ISOLDE High-Energy Beam Transfer Lines Power converters installation & Commissioning Magnet installation & Commissioning BI installation & Commissioning (HW) Vacuum installation & Commissioning Beam commissioning (phase1) Start of the Physics at 5.5 MeV/u 2016 2017 2018 LS2 & shutdowns Physics at 5.5 MeV/u Initially planned to start in May 2015, the Physics Program at 5.5 MeV/u is now expected to start in October 2015. The above schedule is could be affected by unforeseen emergency activities that could arise during LS1. Reprioritization of phase 2 and 3 is unavoidable.

Cost: External Funding Phase 1 1.084.845 (*) to be considered additional expenses on salaries of 6.0 MCHF (2011-2014) already covered by EU-FP7-ITN Marie-Curie program: CATHI The missing income of 0.7 MCHF should be covered through new applications: Belgian Big Science Project #2 through K.U. Leuven => Phase-2 Local funds from Sweden through U. Lund COSA EU-FP7-ITN Innovative Doctoral Program 24 man x years

CERN Extra Costs Phase 1 (*) re-use of ALEPH cryo-plant

Missing Resources for Phase 1 For the CRYOMODULE: HR needs (8 man years) All of these needs (the 5 man years listed above) have been filled by redeploying personnel from other projects. However, a short-term (3 year LD contract) position is requested to ensure the continuation of the experienced Mechanical Engineer currently assigned to the HIE-ISOLDE project beyond July 2013.

Missing Resources for Phase 1 For the CRYOGENIC PLANT: HR Needs (2.3 man years) HR needs are estimated to a total of 8.3 man years for the period (2013-2015). The need is for Engineers and technicians to be involved in “Cold box reinstallation” and “Compressor station reinstallation” mainly in the activities of: Project engineer, Mechanics/drawing, Process control, Instrumentation and Commissioning. All of these needs but, 2.3 man years, have been secured for the project. For the Beam Instrumentation: HR Needs (2 man years) HR needs are estimated to a total of 2 man years during the period (2013-2015). Two electronic engineers are needed for a period of 12 months to develop: (i) the front-end analogue electronics for the Faraday Cup (in intensity and profile measurement modes) and the Silicon detector and (ii) the motion control for the beam diagnostic boxes.  All of these needs will be filled by redeploying personnel from other projects.

CRYOMODULE: Status General Priorities Conceptual design 100% Detailed design 60% Detailed drawings 20% Priorities Start procurement processes for components requiring long delays Validate last active components solutions Instrumentation consideration Done In progress Pending Active components Mechanical & cryogenics interfaces Assembly procedures redaction, current leads Quench protection system, RF interfaces Alignment Concept and procedures Adjustment mechanism design Jacks procurement Detailed design, drawings of supporting frame assembly Vacuum Concept, interfaces, instru. and product identification Interfaces drawings Vacuum vessel drawings Procurement and contract follow-up Cryogenics Concept, procedures, reservoir drawings, instrumentation list Aleph fridge compatibility study Thermal shield specifications redaction Response to cryogenics stop scenario. Thermal shield drawings Survey Concept, interfaces Targets definition Detailed design of supports Assembly Concept, general assembly sequence Clean room procurement Detailed procedure redaction Tooling detailed design Instrumentation Requirements - Selection, procurement, installation Safety Risk identification, calculations Products selection Procurement, installation Contracts follow-up Adjustment mechanism, helium reservoir Vacuum vessel, thermal shield, supporting frame, bellows, instrumentation, tooling

Cavity development work in 2012

Cavity Test Results Parameter/feature HIE ISOLDE cavity CERN ALPI cavity INFN-LNL Substrate treatment SUBU Tumbling, EP then SUBU Rinsing water pressure 5-6 bar 100 bar Bake out temperature 670ᵒC (~ sputtering T) 600ᵒC (>sputtering T) Sputtering temperature 450ᵒC 690ᵒC 300  500 ᵒC Sputtering pressure 3 10-1 mbar 2 10-1 mbar Number of layers 12 12-20 layers Power 2 kW11 kW 5 kW (for 2.5 times smaller surface) Cathode voltage 1 kV Bias voltage -80 V -120 V Total electrical energy 46 kWh 15 kWh Auxiliary electrode 2 cm diameter, bias potential 4 cm diameter (2/3 of inner conductor), rounded, bias potential Film minimum thickness To be measured 2 µm Sputtering gas Argon Venting gas N2 vacuum joint Viton CF

Comparison of HIE ISOLDE and ALPI QWRs The slope of our best cavities is independent on Q0 and close to the best ALPI cavities (rounded substrates) Q2_7 ranks 9th out of 13 in terms of Q0 and initial slope Looks as if we were entering the distribution of the LNL cavities from below Data from Legnaro vertical test courtesy of Anna Porcellato

Summary Most recommendations of the previous cavity review were implemented: Reconsidered mechanical tolerances 4 prototypes available since summer 2012 Focused on dc bias sputtering Dummy copper cavity available and used for sample studies in autumn 2012 Increasing cavity turnaround up to 2 weeks Setting up a backup test place in Orsay Continuing work on cavity ancillaries (tuning plate, coupler, RF line) Cavity performance improved significantly in one year: 1 MV/m @ 10 W in September 2011 5 MV/m @ 10 W in October 2012 Remaining issues for cavity performance Film thinness on cavity top (high current region) Bad film quality on tip of the inner conductor (peak E field emission) Stability Statistics