ELCITA UPDATE July 2016
Estate Management Skywalk E – Toilets 16 e-toilets operational. M/s mayaPRAXIS have submitted the draft report - Preliminary Feasibility Study on Skywalk system for Electronics city phase 1. E – Toilets 16 e-toilets operational. Estate survey Roads & common area survey completed for Phase 1& 2. Plot Inventory of the Industries 100 % completed. GIS Web Application Software Installed in ELCITA server. Testing work in progress.
Road Works – Under Progress Laying DBM work from Wipro Gate No 5 to 16 Concrete Pavements along Doddanagamangala Village Road
Drain Works – Under Progress Drain Work From Wipro Gate 5 to Wipro Gate 16 Drain Work in front of CDac
Construction of Shoulder Drain along Café Corner Road Drain Works – Under Progress Removing the existing pavers & laying the new Pavers at Salarpuria Info Zone Construction of Shoulder Drain along Café Corner Road
Drain Works – Under Progress Drain Work along ITI property Drain Work in front of Venkatadri
Drain Works - Completed Laying Kerbstone & Pavers at MSME building Laying Kerbstone & Pavers at Wipro Gate No 5
Drain Works - Completed Drain works backside of DMart Drain Work in front of HCL
Drain Works - Completed Drain works along Police Station Road Drain works from RS Junction to Rajakaluve
Drain Work in front of Police Station Drain Works – Completed Drain Work in KSSIDC Complex Drain Work in front of Police Station
MS Fencing for E-Toilet Below Fly Over Misc Works – Completed MS Fencing for E-Toilet Below Fly Over
Misc Works - Completed Chain link Fencing work at Schneider Electric (Ph 2) Rectification & Plastering Work in ELCITA water sump
Misc Works - Completed Rectification work for cauvery water at Pumphouse Pot Hole Filling Work at Various Location
Misc Works - Completed Painting work at Electronics City Police Station Providing Purified UV Drinking water facility at Pump House
Drain Cleaning Work along Tech Mahindra Road Misc Works - Completed Fixing of SS Railing at KFC, Svenska Drain Cleaning Work along Tech Mahindra Road
Misc Works - Completed Providing PCC to Changing the drain slope towards gollahali Village Providing & laying WMM/Debris at KIADB land
Sustainability Projects RWH works – Under Progress SI.NO DESCRIPTION NO OF PITS STATUS 1 RAIN WATER HATVESTING PIT 38 COMPLETED 2 12 TO BE AWARDED
20 feet deep well Rainwater Harvesting Pit at Various locations
Estate Management Contract Awarded Providing and laying of Asphalting using 60/70 grade bitumen along Café Corner & JP IT Park Road
Estate Management Tender Published Providing and laying of Asphalting using 60/70 grade bitumen along MSME Entry Gate to Exit Gate for 300KLD STP Construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs along TCS Road Petrol bunk Road & Golden Tulip Road
Estate Management Contracts on Anvil Providing and laying of Asphalting using 60/70 grade bitumen along KSSIDC Complex Road Landscaping work below fly over (Phase 1 & 2) Providing UGD to connect industries in cluster 2 & 3 to the 300 KLD STP. Construction of 500 KLD STP in KIADB Land, Electronics City Phase 2