Beam Dumping System and Abort Gap

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Friday, h10: Stable beams at 1.38 TeV. 09h03: Beam dump.  One bunch dropped too much in intensity and gave BPMS interlock (dump protection). 10h36:
1 MKBH Erratic Jan Uythoven On behalf of the ABT team (Viliam, Nicolas M., Etienne, Laurent, Francesco etc…..) MPP meeting 8/5/2015.
Failure mode impact studies and LV system commissioning tests
B.Goddard 08/11/04 HHH 2004 Workshop, CERN Beam Dump Brennan GODDARD CERN AB/BT The existing LHC beam dump is described, together with the relevant design.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
1 LBDS Testing Before Operation Jan Uythoven (AB/BT) Based on the work of many people in the KSL, EC and TL sections.
What will we do for Beam Preparation: Injection and Beam Dump Jan Uythoven Thanks to M.Barnes, E.Carlier, L.Ducimetière, B.Goddard, R.Jones, Y.Kadi, V.Kain,
1 Beam Dumping System MPP review 12/06/2015 Jan Uythoven for the ABT team.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
LMC 27 November 2013 Status of LBDS LS1 activities and plans for 2014 reliability run Jan Uythoven for the many, many people working on the mentioned equipment.
18 July Reminder Dilution kicker system MKB is staged (2H, 2V) –Limits extracted intensity at 7 TeV to 50% of nominal –For 25ns spacing, this is.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Aperture measurements during LHC commissioning 2017
LHC Beam Commissioning Meeting V. Kain & R. Alemany
Data providers Volume & Type of Analysis Kickers
The TV Beam Observation system - BTV
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Dependability Requirements of the LBDS and their Design Implications
Beam dump XPOC analysis
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
The LHC Beam Dumping System
LHC beam dump 7.56 TeV operation
SPS extraction, transfer lines, injection
LHC Beam Dumping System Reliability Run Summary
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Chamonix 2009 – LHC Performance Workshop
Jan Uythoven For discussion
Saturday 21st April 00:33 Interlock during ramp on BLM HV
LHC Risk Review: Kicker Magnet Reliability
Monday 14th March Second fill with pilot + 3 nominal bunches
Monday 11/07: Recovery Plenty of accesses.
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Initial Experience with the Machine Protection System for LHC
Tue :25 Beams dumped due to RF vacuum interlock
Thursday morning – optics correction
LHC Injection and Dump Protection
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Planning at 5 o’clock meeting Friday
Chamonix 2006 – LHC Project Workshop
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Will We Ever Get The Green Light For Beam Operation?
Can operation put the MPS in a unsafe state?
Saturday Nov Stop proton operation. Switch back to ions
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Machine protection and closed orbit
07/08/2010 Fill #1264 dump at 02:14:38.
Jan Uythoven For the LBDS Team
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Wednesday 23/2 Thanks CRYO!!!.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Tuesday
HI2011 Commissioning Status
Presentation transcript:

Beam Dumping System and Abort Gap LHC Beam Commissioning Workshop Evian 19 -20 January 2010 Session 4: Machine Protection Systems Jan Uythoven TE/ABT For the LBDS and Abort Gap Teams

Outline Only 10 minutes from the Chairman Performance of the Beam Dumping System Some Operational Statistics Beam Dumping System ‘Failures’ and Issues Kicker systems XPOC Operational Experience Beam Dump Aperture and Trajectory Abort Gap Cleaning Experience so far Is it ready for higher intensities and higher energies? Conclusions Are we ready for higher intensities and higher energies? Outstanding issues Only 10 minutes from the Chairman Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

Beams for physics dumped, at the right place! 450 GeV Beam dumps, 16 bunches + pilot, 14/12/09 around 21:00 BTVDD image = position on beam dump block TDE Comparison with calculated positions from measured kicker magnet waveforms. Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

XPOC Statistics Beam 1 Number of times dump triggered XPOC = eXternal Post Operational Check MKB (dilution) only 1 x false XPOC during Synch.-Asynch Dump OK Not OK Total XPOC1 1355 11 1366 XPOC2 1309 57 Energy 450 GeV 600 GeV 1200 GeV # Dumps 1358 1 7 27 days from 20 Nov. to 16 Dec. MKD = beam dump extraction kicker MKD Gen. K pulse length. Limit enlarged. OK. See later. No false last 10 days Jan Uythoven, TE/ABT

XPOC Statistics Beam 2 MKB no false XPOCs OK Not OK Total XPOC1 1159 16 1175 XPOC2 1166 9 Energy 450 GeV 600 800 1200 # Dumps 1159 1 7 27 days from 20 Nov. to 16 Dec. Most errors due to ‘Energy Error’ in XPOC analysis. See later. Fixed. XPOC 1 errors due to noisy signal. See later. Fixed. No false last 10 days Jan Uythoven, TE/ABT

Beam Dumping System ‘Failures’ All dump ‘failures’ were caught by the XPOC and/or IPOC system There were no beam dump failures which were ‘unacceptable’ Protected against asynchronous dumps with TCDQ Would normally expect about 1 asynchronous dump per year However, 11 ”Synchronous-Asynchronous” dumps due to problem with TSU Dump request received during the 1.5µs Frev pulse duration Dump request inhibited for the current turn Original inhibition mechanism lets a “glitch” going out Synchronous trigger of the 15 kicker generators Asynchronous trigger w.r.t. the circulating beam TSU firmware upgraded and successfully tested - Generator synchronisation OK - Kick delay w.r.t. beam abort gap FAULTY Evian, 18 - 19 January 2010

Other Beam Dump System Hardware Problems 2 x fuse on MKB power trigger converter broken Needed access to change – no safety issue Reduced the power consumption of converter in this Techn.Stop BPM signal used for synchronisation: 2µs off-set Being checked… Resistors used for re-triggering in case of MKD switch conduction not via stack: 15/60 broken Masked in the generator interlock Still one per generator active, but no redundancy left For this reason we should not operate present system above 5 TeV and high beam intensities Switch erratics issue above 5 TeV, More important after installation of generator cooling = dry air Replacement resistors available in some wks, need about 2 wks for swap Reliability of Pelletier cooling of MKD generators Some failures of cooling, but still ok because little heating at low energies Gives interlock when outside ± 1 C temperature range Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

LBDS XPOC: eXternal Operational Check Operational modules at the end of operation: MKD and MKB kickers Vacuum Beam loss monitors: proven to trigger in case there is beam in the abort gap at the moment of dump Modules present, but not interlocking – need more work and time to commission Beam dumped current – BCTD BTVDD image BPMD Abort Gap Monitor Working within the PM framework General BI checks to be deployed (BTVDD, BCTD etc.) Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

False XPOC / IPOC results …. Signaling a REAL hardware Problem I Synchronisation errors due to TSU problem Real problem – solved MKD XPOC1 Analysis based on Rogowski current measurement which is known to be more noisy than the Pearson signal used for XPOC2 Occasional bad XPOC1 OK after doubling the acceptance window As the systems are redundant, this is acceptable Raw SDDS data XPOC1 Raw SDDS data XPOC2

False XPOC / IPOC results …. Signaling a REAL hardware Problem II MKD Beam Generator K Varying pulse length – ‘sign of something changing’ Under investigation in this Technical Stop K-reference value Original limit MKD B1 Generator K, Pulse length drops during operational period but ‘jumps back’ when dumps at 1.2 TeV Lim. Enlarged limit G-Ref. Lim. MKD B1 Generator G, for comparison 5 Nov 12 Dec Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

False XPOC / IPOC results …. Signaling an XPOC / IPOC Problem XPOC sequencer task picking up different time stamps from MKD and MKB IPOC Solved during operation by applying the correct tolerance XPOC MKD analysis failed because of different energies IPOC MKD analysis failed, giving some analysis points ‘dangling in the air’ Solved during in Technical Stop by small change in algorithm (same problem as for MKI IPOC used for IQC) These false XPOCs were annoying for both the operators and the experts, however I’m convinced that we have to maintain the Expert Reset for XPOC, as the LBDS is too safety critical. Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

Beam Dump Channel Aperture Aperture limits measured with all phases in H and V plane for B1 and B2  as expected MSD MKD Can dump without losses with 1.67 MKD for B1, +1.333 and -1.67 MKD for B2. Spec: + 0, -1 MKD. Jan Uythoven, TE/ABT

Point 6 – Circulating Beam Aperture Circulating beam aperture in H and V for B1 and B2 checked carefully at TCDS, TCDQM, MSDC and MKD, with bumps through the region  beam lost where expected “Official aperture model” IR6 H Beam2, circulating TCDQM MSD TCDQM Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

Dump at 1.2 TeV Vertical dump position low at 1.2 TeV for both beams After orbit correction to golden orbit Maybe 7-8 mm vertical error at the TDE for both beams Can be an MSD calibration issue? About 11 µrad too weak Beam2 bucket 1 from golden orbit B1 B2

Abort Gap Cleaning Tests First functionality tests performed on December 15-16, 2009 Used vertical dampers on beam 2 BSRA data show gap partially cleaned Cleaning on: BCTDC signal shows losses = cleaning BSRA signal decreases from previous equilibrium to new equilibrium Beam Dumped: BCTDC to 0 BSRA to 0 RF-Off: BCTFR signal to 0 BCTDC signal flat BSRA signal pops up and reduces when beam disperses Losses at BLMs at TCDQ / TCDS, at moment of dump, are reduced to about 10 – 12 % relative to no cleaning! Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

Conclusions on Abort Gap Cleaning Undulator and synchrotron light monitor successfully commissioned for beam 2 Beam 1 remains to be commissioned Abort Gap Cleaning “works” already during first tests! But needs to be further optimised to clean over the full 3 µs while limiting the losses outside the abort gap About 10 % of the beam was left in the gap Concerning Machine Protection we will need to commission the Abort Gap Monitoring Interlock Interlock values to be found and tested with beam Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

Conclusions / Are we Ready for Higher Intensities and Higher Energies? The beam dumping systems worked very well and the XPOC and IPOC systems caught all failures Only real failures were the Synchronous-Asynchronous dumps: solved after TSU firmware upgrade Opening up of XPOC1 window and one MKD generator which drifted Other XPOC/IPOC ‘false’ were software issues, sorted out during the 2009 run Many tests with beam outstanding Dump at intermediate energies, already some energies ‘missing’ up to 1.2 TeV Follow commissioning procedures for increasing energy and intensity: edms 896392 Sort out vertical dumped beam position on TDE (MSD calibration?) Should not pulse with unsafe beam above 5 TeV without redundancy on resistors for erratic trigger protection (new ones ordered) Further BI-XPOC modules to be commissioned With the present ‘habits’ and possibilities to skip sequencer tasks, the SIS latching is mandatory At some point the SIS interlock of the XPOC will have to become unmaskable We will need to converge to a more standard way of running sequences and clear instructions which tasks are mandatory to be run before each injection or each fill and under which conditions tasks can be skipped: PROCEDURES – Master Sequence BSRA – Abort Gap Monitoring Interlock to be commissioned and tested with beam Abort Gap cleaning also needs further commissioning, but should not be a machine safety issue Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010

Acknowledgements Many thanks to the LBDS and Abort Gap Teams: B.Goddard, E.Carlier, N.Magnin, N.Voumard,T.Kramer, W.Bartmann, V.Kain, R.Allemany Fernandez,V.Mertens, M.Meddahi, L.Ducimetière, A.Antoine, F.Castronuovo, F.Olivieri, D.Khasbulatov, V.Baggiolini, J.Axensalva, S.B.Pedersen, A.Boccardi,A.Butterworth, A.S.Fisher, E.Gianfelice-Wendt, G.H.Hemelsoet, W.Höfle, D.Jacquet, M.Jaussi, T.Lefevre, E.Shaposhnikova, D.Valuch and many others. Jan Uythoven, TE/ABT Evian, 18 - 19 January 2010