Agenda Provide a recap of primary northern route alternatives for the MPRP Describe basis for selected route N5 Overview of analyses performed Description.

Slides:



Advertisements
Similar presentations
Demand Resource Operable Capacity Analysis – Assumptions for FCA 5.
Advertisements

Al McBride MANAGER, AREA TRANSMISSION PLANNING Existing Import Interfaces: Transmission Transfer Capabilities and The Calculation of Tie Benefits DECEMBER.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Navarro to Houston Presentation to ERCOT RPG August 27, 2013.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
BOSTON DENVER LONDON LOS ANGELES MENLO PARK MONTREAL NEW YORK SAN FRANCISCO WASHINGTON Effective Load Carrying Capability of Wind Generation: Initial Results.
NOVEMBER 11, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
AUGUST 19, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
National Renewable Energy Laboratory Innovation for Our Energy Future * NREL July 5, 2011 Tradeoffs and Synergies between CSP and PV at High Grid Penetration.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Subtransmission Reliability Criteria
ISO Exhibit 13 Federal Energy Regulatory Commission Technical Conference on Connecticut Infrastructure Reliability and Operability Committee Update Hartford,
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting December 16, 2009.
Lyndonville Electric Department Feasibility Analysis Review December 2,
North Island Grid Upgrade Proposal Presentation to the Electricity Commission Conference 22 May 2007.
Options to Manage Electricity Demand and Increase Capacity in Santa Delano County Jon Cook Jeff Kessler Gabriel Lade Geoff Morrison Lin’s Lackeys.
Proposed Generation Expansion Process For Review and Discussion March 1, 2011.
Local Area Study Local Area Study Mitigation Plan Update and Uncertainty Scenarios
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
© ABB Group August 23,2010 | Slide 1 MBPC Study – 1 st Load Pocket Preliminary Results for Discussion only Entergy Regional State Committee (ERSC) Southwest.
LAREDO RMR EXIT STRATEGY Presentation to Technical Advisory Committee March 4, 2004 Transmission Services Operations.
1 1 1 Central Maine Power Local System Plan Presentation Planning Advisory Committee Meeting November 19, 2008.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
OCTOBER 2, 2013 Maine 2013 Outage Coordination Redacted Copy.
Demand Forecast Deviations Working Group Presented to: Stakeholder Advisory Committee Presented by: Pat Doran January 24, 2007.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting June 20 th, 2008 Austin, TX.
ESI Alternate Economic Study Process E-RSC Meeting October 21, 2010.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
1 Entergy Mississippi, Inc. Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
June 26, 2008 Technical Advisory Committee American Electric Power Service Corporation Presidio Area Reliability Improvements Project James Teixeira Manager,
UM 1751 Energy Storage Workshop #3 May 9, UM 1751 Workshop #3 Topics Most viable and beneficial applications (HB 2193 time frame: ) Emerging.
PJM© Market Efficiency RTEP Proposal Window PJM TEAC 1/9/2014 – Market Efficiency Presentation.
ERCOT – LP&L Study Status Update For Regional Planning Group Ben Richardson March 22, 2016.
GRID INTEGRATION COST OF PHOTOVOLTAIC POWER GENERATION G. Strbac, D. Pudjianto, P. Djapic, J. Dragovic Energy Futures Lab.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Houston Import Study Update
Pan-Canadian Wind Integration Study (PCWIS) Prepared by: GE Energy Consulting, Vaisala , EnerNex, Electranix, Knight Piésold Olga Kucherenko.
Target Reserve Margin (TRM) and Effective Load Carrying Capability (ELCC) of Wind Plants Evaluation - Input and Methodology ERCOT Planning 03/25/2010.
Minnesota Renewable Energy Integration and Transmission
Barrilla Junction Area Transmission Improvements Project
Columbia Grid Wind Integration Study Team Dynamic Transfer Capability Studies Update 9/10/09.
Mike Jaske California Energy Commission
Allegheny Power Residential Demand Response Program
Modifications to Planning Charter
Restructuring Roundtable March 24, 2017 Boston, MA
ISO New England System R&D Needs
Local Area Planning Update to TRANSAC – March 15, 2017
Transmission Planning in a Modern Market Environment
DEC System Voltage Planning - June 2018
New England Resource Adequacy
RE Grid Integration Study with India
New England Electricity Restructuring Roundtable September 18, 2009
Bringing Power from the North
Study Results Drought Scenario Study
Bringing Power from the North
Presentation transcript:

MPRP Northern Route Alternatives N5 versus N1 NEPOOL Reliability Committee March 17, 2009

Agenda Provide a recap of primary northern route alternatives for the MPRP Describe basis for selected route N5 Overview of analyses performed Description of process followed Respond to questions from recent RC and TCA Stakeholders Meetings, including a Present Value analysis comparing N1 and N5

MPRP Northern Routes Alternatives Assessment Developed 5 Northern Solutions (N1 thru N5) Dropped N4 - Weakest Electrical Performance; Highest Cost Analyzed 4 Solutions (N1, N2, N3, N5) in detail Performance Evaluation Compliance with reliability criteria for N-1 and N-1-1 Year 2017 Summer 90/10 peak load 18 base cases (6 dispatches, with 3 transfer conditions) Electrical performance evaluation based on: Longevity 115-kV Operability Loss Savings Transfer Capability

Assessment Criteria (Cost & Performance) Electrical Performance Ranking based on: Longevity Evaluation Reliability assessment analyzed 15- and 20-year N-1 analysis for each alternative and compared both voltage and thermal reliability criteria violations 115 kV Operability Evaluation Evaluated N1 & N5 alternatives with a limited number of single 115 kV line outages Loss Savings Evaluation Average of the loss savings for the 18 cases for each alternative Transfer Capability Evaluation Analyzed steady-state thermal transfer capability of Orrington-south interface in north-to-south direction Other considerations: Renewable integration Design factors to mitigate the risk of Extreme Contingencies & Conditions

MPRP Transmission Alternatives Assessment Longevity Analysis – Thermal Results N-1 (First Contingency)

MPRP Transmission Alternatives Assessment Longevity Analysis – Voltage Results N-1 (First Contingency)

Western Area – Post-Contingent Thermal Loading MPRP Transmission Alternatives Assessment Longevity Analysis (N-1) – Local Area Review Western Area – Post-Contingent Thermal Loading N1, N2 and N3 show overloads for line and / or autotransformer contingencies N5 shows overload for autotransformer contingency only Location of autotransformer at Gulf Island (N5) is preferred over Kimball Rd (N1 and N2) or Livermore Falls (N3) to reduce loading concerns on Section 62 and to eliminate need for new 115 kV line into the Lewiston area Central Area – Post-Contingent Thermal Loading Alternative N1 shows overload for Section 67 contingencies before the 15-year time frame Alternative N1 shows overload on Section 84 for several contingencies before the 20-year time frame Alternative N5 displayed reliable thermal performance at the 20-year time frame due to the Albion Rd. 345/115 kV autotransformer Autotransformer Longevity All Alternatives provide 12 to 16 years beyond 2017 before the outage of the Western autotransformer caused overload on Surowiec autotransformer Alternatives N1 and N5 provide the best longevity overall

MPRP Transmission Alternatives Assessment Longevity Analysis Summary Voltage Performance (N-1) Fifteen Year # of Violations 23 13 11 Twenty Year # of Violations 79 65 74 34 Voltage Ranking 4 2 3 1 Thermal Performance (N-1) Western Area Auto Contingency Ranking Western Area Line Contingency Ranking Central Area Contingency Ranking Southern/Central Line Contingency Ranking Thermal Ranking Auto Transformer Loading Overloads on Existing Autotransformers

MPRP Transmission Alternatives Assessment Longevity N-1 Analysis Conclusions Alternative N5 Provides the best longevity solution Only option with no violations in 2022 (15 yrs) Option with the fewest violations in 2027 (20 yrs) Alternative N5 requires only limited upgrades for 20-Year Solution N5 Alternative only requires 2nd autotransformer at new Larrabee Road Substation N1 Alternative likely requires addition of new 115 kV lines in both Central and Western Maine, along with other reinforcements Overall, Alternative N5 moves the next Year of Need out about 5 years While not studied, it was clear that there would be significant added costs to expand Alternative N1 to provide comparable longevity to Alternative N5

In Central region, several 115 kV outages were analyzed MPRP Transmission Alternatives Assessment N1 vs. N5 Operability Analysis Scope Operability is defined as the ability to operate the system under various scenarios Operability comparison conducted on N1 vs. N5 in Central and Western Maine regions N1 Autos are at Maxcys (Coopers Mills) and Kimball Road N5 Autos are at Benton (Albion Rd) and Gulf Island (Larrabee Rd) In Central region, several 115 kV outages were analyzed Section 67, Section 83, and Section 84 In Western region, several 115 kV outages were analyzed Section 62, Section 64, and Section 87

MPRP Transmission Alternatives Assessment N1 vs MPRP Transmission Alternatives Assessment N1 vs. N5 Operability Analysis Results Central Area - N5 provides more support with Benton (Albion Rd) autotransformer for both N-1 and N-1-1 Section 67, Section 83, and Section 84 Under N-1-1 conditions, voltage collapse and severe overloads for Alternative N1. Under N-1-1 conditions, no violations of reliability criteria for Alternative N5 Recommend new 115 kV transmission line (26 miles) from Maxcys to Winslow for equivalent Operability Western Area - N5 provides more support to load pocket with Gulf Island (Larrabee Rd) autotransformer for both N-1 and N-1-1 Section 62, Section 64, and Section 87 Recommend eliminating 345 kV line from Gulf Island to Kimball Road and moving autotransformer to Gulf Island for equivalent Operability

MPRP Transmission Alternatives Assessment N1 vs MPRP Transmission Alternatives Assessment N1 vs. N5 Operability Analysis Conclusion Both N1 and N5 meet reliability standards per MPRP scope. However, there is a major difference in how these alternatives perform under N-1 and N-1-1 conditions. In many cases, local area voltage collapse in N1 following the second contingency reinforces the conclusion that N5 is more robust electrically and will serve the load in the Western and Central Maine areas the longest during both normal and emergency conditions. The effect of moving the N1 autotransformer location and additional 115 kV reinforcement is an additional $27M.

Reduction in losses due solely to changes in Maine MPRP Transmission Alternatives Assessment N1 vs. N5 System Loss Savings All dispatch scenarios and transmission alternatives were compared against the base system without upgrades in 2017 Reduction in losses due solely to changes in Maine N5 had the highest average loss savings of 21.8 MW The average loss savings of N1 is 20.6 MW N5 average loss savings are 1.2 MW greater than N1 14

N5 (and N2) had the highest thermal transfer capability at 1975 MW MPRP Transmission Alternatives Assessment N1 vs. N5 Transfer Capability Analysis Summer Peak load assessment of first contingency thermal transfer limit on Orrington-South interface Existing limit is 1200 MW due to loss-of-source limit for single contingency N5 (and N2) had the highest thermal transfer capability at 1975 MW N1 was the next highest at 1925 MW. 50 MW incremental transfer limit for N5 over N1 15

MPRP Transmission Alternatives Assessment Comparison Summary ROUTE ALTERNATIVES N1 N2 N3 N5 Electrical Performance 3 2 4 1 Longevity Loss Savings 20.6 MW 21.3 MW 19.8 MW 21.8 MW Thermal Transfer Capability 1925 MW 1975 MW 1725 MW Total Estimated Cost $905M $1,037M $979M $1,001M Estimate to Achieve Similar Operability $27 M Estimated Cost for Similar Operability $932 M $1,001 M

MPRP Transmission Alternatives Assessment Selected Alternative: N5 MPRP Northern Alternative N5 Best Electrical Performance Best Longevity Best Operability Best Loss Savings Highest Thermal Transfer Capability Additional 345 kV Transmission Corridors Fewer 345 kV lines in common Rights-of-Way and more 345 kV substation reinforcements at different locations Stronger Reinforcement of Central Maine – 345 kV transformation closer to major generation & load centers Relies on fewest static capacitors to achieve reliable performance Better integration of wind and/or Canadian resources to the north Concurrence from ISO-NE The above advantages of N5 over N1 were not quantified in a Net Present Value (“NPV”) analysis as part of CMP’s selection process

Process for Alternatives Assessment & Choice N1 vs. N5 Evaluation CMP MPRP project team met several times in fall 2007 with ISO-NE technical staff & senior management to review alternative analysis and basis for decision CMP & ISO reached consensus on N5 vs. N1 performance difference and N5 as the best choice for MPRP ISO-TO System Planning Group reviewed the N5 vs. N1 analysis & decision and accepted it subject to TCA review N5 was presented as CMP’s choice to PAC in January 2008 N5 was studied and reviewed with the NEPOOL Reliability Committee task forces through the PPA process The selection of northern route N5 has been thoroughly vetted with ISO-NE and stakeholder groups No opposition to the selection from any stakeholders

Questions from Recent Meetings After the January 29th TCA Stakeholders Meeting, ISO-NE asked CMP for an “NPV analysis of N5 versus N1” CMP’s Approach Express the Costs of N1 and N5 in NPV Revenue Requirements Longevity – The entire scope of added projects & costs of N1 are unknown Operability – Estimate the Added Costs to Provide Comparable Operability Losses – Estimate the impact on regional LMP cost to load Transfer Capability – LMP effects included in the estimate on Losses CMP and ISO original decision making process Recognized these benefits qualitatively Only Operability costs were estimated at that time

MPRP N1 vs. N5 NPV Analysis Costs of N5 versus N1 Base N5 costs $96 million more than N1 (in 2012$) That difference decreases to $69 million with equivalent operability Multiply by annual carrying charge factor and add O&M costs to estimate incremental revenue requirements NPV in 2008$ of incremental revenue requirements for N5 is $52 million

Energy market simulations performed assuming N1 instead of N5 MPRP N1 vs. N5 NPV Analysis Evaluated Benefits of Losses and Transfer Capability N5 has 50 MW higher transfer capability for Orrington-South interface, compared to N1, based upon thermal analysis N5 has higher loss savings (21.8 MW) than N1 (20.6 MW) at the peak hour, based upon an average of all dispatch and transfer scenarios. Energy market simulations performed assuming N1 instead of N5 NPV of Benefits in 2008$ With N5, NPV of regional energy costs are $11 million to $63 million lower than with N1 Above NPV savings exclude benefits from N5’s greater longevity and superior operability

MPRP N1 vs. N5 NPV Analysis La Capra Northeast Market Model Based upon the PROSYM simulation software NE system representation based upon latest CELT and RSP databases Benchmarked against latest year of historical LMP data Renewable energy build-outs assumed to comply with RPS Convention build-outs when necessary to achieve resource adequacy Maine modeled as three energy zones BHE, central Maine, southern Maine

MPRP N1 vs. N5 NPV Analysis NPV Summary ROUTE ALTERNATIVES N1 N5 N5 – N1 Total Estimated Capital Cost, 2012 $905M $1,001M $96M Estimate to Achieve Similar Operability, 2012 $27M ($27 M) Total NPV of Revenue Requirements, 2008$ $698M $750M $52M Estimate of Energy Cost difference due to Losses & Thermal Transfer Capability, 2008$ $11 - $60M ($11 - $60M) Total Estimated Net Cost NPV, 2008$ $709 - 758M $41M - ($8M)