Lost at 12:05 to power converter (RTQX2.R1) problem

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Wednesday 8.9 External crossing angles:
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Operation Week 41 Coordination G.Arduini, M. Lamont
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
LHC operation in week 42 Coordination:, Malika Meddahi, Joerg Wenninger Thanks to OP crews, HW and SW teams + experiments Aims for the week Cure aperture.
Saturday 1.3 e32 Overnight Morning
Summary of Week 11: 14 – 21 March
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
LHC Morning Meeting - G. Arduini
Friday 31st August & night
Mike Lamont, Jorg Wenninger
Saturday 2/4/ :00-09:00 Problems with SPS:
Tuesday 20 March 2012.
Week 35 – Technical Stop and Restart
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Wire almost entirely through beam before BLM triggers dump
Sunday
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Monday 24 October hours of 25ns MD
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Saturday Nov Stop proton operation. Switch back to ions
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Monday :15 fill 3523 dumped by BPMs IP6
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
Wednesday 23/2 Thanks CRYO!!!.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
RAMP FOR COLLIMATOR SETUP
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Another Immortal Fill….
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Tuesday
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
HI2011 Commissioning Status
Monday 152 bunch operation summary
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Lost at 12:05 to power converter (RTQX2.R1) problem Fill 1418 Peak luminosity ~1.03e32 Beam current 2.62/2.61 e13 Average initial bunch current 1.04e11 Initial emittance (reconstructed from lumi) 2.4 micron Integrated luminosity > 2 pb-1 Approx beam-beam tune shift at start 0.016 Initial stored beam energy 14.9 MJ Pots in at 8:45 Lost at 12:05 to power converter (RTQX2.R1) problem 12/3/2018 LHC status

12/3/2018 LHC status

Yesterday afternoon Philippe B. has trimmed the injection values of the cavities Q and adjusted the first point of the ramp accordingly for some lines. Q5 aperture measurement Aim: check aperture at MQY5 for injected beam after implementation of bump for losses at MSIA Measured emittance in SPS: emittance varied from one shot to the other by 0.5um (1.7-2.2) and big tails were observed Scan with vertical trajectory oscillations (60 and 180 degree phase advance (candidate for maximum amplitude at Q5)) up to -8.5 sigma--> no losses at MQY (bottleneck observed at the upstream MSI) A full scan for all the different phases is needed for a better understanding BGI commissioining 17:52 dumped B2 – valves in 12/3/2018 LHC status

BGI 12/3/2018 LHC status

Evening/Overnight Aim of evening: qualify 312 b and go for physics From 21:00 Problems with injection – beam 2 – LHCb triggering Unfortunately, every trial fill was dumped by LHCb BCM. optimizing the orbit, disregarding RF injection errors; optimizing RF inj errors (phase~=0, synchro~=10 pkpk), accepting the orbit to be off center; tried injecting a previous pattern (248b); tried removing the cavity Q trims done in the morning (they should be put back before the 312b fill!); tried leaving 8+8 bunches in to observe de-bunching, nothing special seen; tried kicking with MKI while SPS MKE disabled; removed transverse and longitudinal blow up at the injectors; corrected chromaticity at the SPS by 0.2 in H and 0.1 in V; 12/3/2018 LHC status

Continued… tried injecting both rings, or b2 only; reduced the intensity by 10% (to 0.95e11 ppb) and tried to improve the PS splitting; tried logging all possible parameters per shot (inj oscillation, ring BLMs, IQC data, MKI, SPS V wires, SPS BCT, SPS FBCT, SPS inj oscillations) Losses on the TCTVB.4R8 were often present, LHCb dumped when we got to 60/70% of ring BLM dump thresholds. Note that similar losses on TCTVB.4L2 were present. LHCb's feedback: for the shots that dumped, the signal on the BCM is 3/4 times higher than previous shots (often signal from 8-b injection worse than i.e. for 24). This seems to indicate a variation shot to shot from the injectors, which we could not track though. The signal on LHCb's BLS is not connected to our interlocks, but they saw a particular signature in all cases of dump: a much stronger signal on the C-side (inside of the ring) than on the A-side. This same signature was seen also when our kickers kicked, but no beam was extracted from the SPS. 12/3/2018 LHC status

12/3/2018 LHC status

Morning shift this morning 07:00:12 Wide spread electrical glitch S81 down Pre-cycling at the moment UPS to PIC – redundancy missing, OK to run but can’t re-start – masked in PIC at the moment 12/3/2018 LHC status

Weekend Friday 07:00 – 19:00 vdM Friday evening Check injection Friday overnight Physics 312b 12 hour fill Saturday Saturday overnight Sunday TL BL calibration 3-4 hours Quench test? 8 hours Sunday overnight 12/3/2018 LHC status

To-do list

OP Periodic loss maps Orbit shift versus TCT check: Betatron loss map done week 40. Orbit shift versus TCT check: collide 1 bunch and check the TCT center change as compared to predicted orbit change. All in one ramp, squeeze, collide - 1 shift Plus test of 'dynamic' references for the OFB (varying Xing.separation bump): injection, then test of ramp + first part of squeeze IR aperture at 3.5 TeV 50 ns – pilot runs After 3-4 fills with ~400 bunches Push beam-beam tune shift with 150 ns one test already performed with #1410 12/3/2018 LHC status

BI studies – list to be updated Check the linearity of the fast BCT’s in the new configuration for nominal bunches Tune the High BW/Low Gain fast BCT calibration for the coming ion run Measure the High BW/Low Gain fast BCT sensitivity limit and linearity for low intensity bunches (ion run) Re-check BPM sensitivity limit Calibrate the abort gap over the whole ramp Check the abort gap acquisition gate timing resolution and stability Commission BGI in preparation to ions – started! Check BSRT/BGI/BWS cross-calibration including corresponding emittance logging Test and compare bunch/bunch profile measurement via BWS and/or BSRT PLL studies during ramp continued JJG: for all this, we would need the 2 rings for a few hours at 450 GeV then a ramp and again a few hours at 3.5 TeV. This would be really difficult to fit in a 4 hour slot. 8 would be perfect but we could try with 6. 12/3/2018 LHC status

Other Abort Gap Cleaning – on at injection for physics continue testing Injection studies 32 Bunches when required (344 bunches) Injection studies with 50 ns Setting-up of the SPS with tighter batch spacing (225 ns) to be checked Transfer line collimator cross-talk calibration Quench test at 3.5 TeV – pilot beam Bernd & co 12/3/2018 LHC status

Experiments 50 pb-1 total (20 delivered so far) 10 fills@3 pb-1 ~ 10 good days Alice – fill without dipole Totem – dedicated fill Totem – 90 m optics LHCb – switch polarity – plus test ramp (combine with BI plus map) vdM continued – count 1 – 2 shifts 12/3/2018 LHC status