4Laser RF Diagram
4Laser LO System
Laser RF Front-End
Cost/Labor Estimate
Tasks, Assignment, Completion Dates Injector LO/MO System documentation and modification - Manuel Diaz ( assigned by supervisor/ in progress) System documentation completed COTS FPGA Board, ADC Board, DAC Board purchasing ( in progress) – completion 04-30-2016 Digital Platform Bench testing ( Tomasz, Rama) completion 05-15-2016 LO system modification – completion 05-30-2016 RF Board - (Will Brinton assigned by supervisor /in progress, possible leave !) completion 05-15-2016 RF Board ready 06-15-2016 LO chassis - ( Larry Farrish) completion 06-15-2016 4Laser LLRF Chassis ready ( Dave Seidman, Dave Williams) - 06-30-2016 FPGA Firmware - (Rama, supervisor approval needed ) 07-15-2016 EPICS Software/ IOC - (Control Group) if IOC-PC104 then 07-31-2016, if IOC-FPGA 09-31-2016 Alternative Clock Board, design, pcb, installation - completion 09-31-2016