8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC Status Mo Morning 20-June Bernhard Holzer, Gianluigi Arduini et al 7 runs The Week.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
LHC Status Sat Morning 9-June Bernhard Holzer, Joerg Wenninger Status Friday Morning: 09:00h end of fill “studies” rf coupler fine tuning ADT gain reduced.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
LHC Status Fri Morning 3-June
LHC Status Tue Morning 22-Aug
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Luminosity lifetime – fill 2932
Summary of week 7 Hardware Commissioning:
Summary week 23 Luminosity production
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
LHC Morning Meeting - G. Arduini
Overview LHC Operation Week 47
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
Barbara Holzer, Jorg Wenninger
Tuesday 22nd January - morning
Monday 6th August & night
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Thursday 10th May - morning
Wednesday 8th August & night
LHC Status Sun Morning 20-Mai
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Week 35 – Technical Stop and Restart
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Thursday :00: Physics fill from the night shift
Friday Morning 7:30 injection for fill 2908
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Friday 25 bunch fill dumped just before (BLM in 5)
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Thursday – Morning Energy matching at injection with H CODs
Programme for Friday 9 July
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
LHC Status Tue Morning 22-Aug
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Summary for LPC (March 7th, Ralph Assmann)
Saturday :42 stable beams fill 3541
LHC Morning Meeting - G. Arduini
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Wednesday 23/2 Thanks CRYO!!!.
LHC Status Fro Morning 9-Sep
Saturday 24 September 2011.
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Wednesday h18: 228b fill lost just before start of ramp.
Friday 15th February - morning
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Wednesday morning Waiting for PS – problem on RF cavity.
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Saturday 10:00: Cryo Pt8 back, starting the pre-cycle.
Saturday 26 November 2011.
Tuesday
HI2011 Commissioning Status
Presentation transcript:

Bernhard Holzer, Joerg Wenninger Thursday Morning 31-Jan 2013 Bernhard Holzer, Joerg Wenninger Wednesday Morning ... LHC in access for temperature alarm (“RF faraday cage”, ventilation problem) ... after a lengthy discussion ... decide to refill the source Plan for LHC: ADT set up for the future quench tests 10:00h injection delayed ... POPS 11:30h injection for ADT tests (protons in beam2)

LHC STATUS Wednesday Late ≈ 16:00h source ready, Pb available BUT 16:30h Water fault on demineralised water in S23 / S34 loosing 100 m3 / day ... which will run into trouble during the weekend 19:00h Water leak found on pipe connected to RB in S34. 20:10h Expert working on Beam Imminent Warning system ... which is still not operational in Pt 7/8 ... to be fixed today !! 04:30h ... 21:00h ... in parallel: since early morning intermittent problem at RF: (problem disappeared at 05:30) faulty VME modules in the Tuner Controller for cavities 5,6,7 and 8 B1. 22:00h Precycle 22:30h Collimator error network problem ? 29/06/2012 LHC 8:30 meeting

LHC Status Wednesday Night 00:00h injection probe beam 00:30h injection physics beam some optimisation needed ... TL steering, RF phase 00:50h beam dump: false trigger from BLM in point 1 (no losses observed) ->MKD beam 2 in error after the beam dump “fault on LBDS kicker was "retrigger box1 compensator B" on generator” 01:15h ... 02:00h injection & TL optimisation 02:10h machine full, prepare ramp 60o inj phase 29/06/2012 LHC 8:30 meeting

LHC Status Wednesday Night 02:55h adjust & lumi optimisation 03:00h stable beams 03:04h separating IP1 and 5 by 130 um in separation plane 5 % 9 % 29/06/2012 LHC 8:30 meeting

LHC Status Wednesday Night 03:10h ... optimisation of lumi & lifetime for beam 2 trim Total voltage to 14MV for B2 orbit correction h & v tune optimisation τ ≈ 8.5h 29/06/2012 LHC 8:30 meeting

LHC Status tune optimisation 29/06/2012 LHC 8:30 meeting