M. Zerlauth, I. Romera 0v1.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

6 th April 2010 MP3 weekly summary – issues and follow-up 0v1 M. Zerlauth for the MP3-CCC shift crew.
LHC UPS Systems and Configurations: Changes during the LS1 V. Chareyre / EN-EL LHC Beam Operation Committee 11 February 2014 EDMS No /02/2014.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
TE-MPE-TM 09/08/2012, TE-MPE-MS section WIC: Overview of on-going projects + Outlook to LS1 activities: - Short introduction to WIC systems - Booster renovation.
January 2006Beam dump and injection inhibits / J.Wenninger1 Beam Dump and Injection Inhibits J. Wenninger AB-OP & D. Macina TS-LEA LHC experiments signals.
Status of Data Exchange Implementation in ALICE David Evans LEADE 26 th March 2007.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
Weaknesses of the LHC Machine Protection System Bernhard Holzer, CERN BE-ABP... what a MPS should do: 2 major tasks * protect the machine in case of hardware.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
The LBDS trigger and re-trigger schemes Technical Review on UPS power distribution of the LHC Beam Dumping System (LBDS) A. Antoine.
BP & RS: BIS & SLP for AB/CO Review, 23 h Sept Realisation of the interlocking between SPS, LHC and CNGS and open issues Beam Interlock Systems.
Interlocks for Magnet Protection System Iván Romera Ramírez, Markus Zerlauth - CERN.
‘Review’ of the machine protection system in the SPS 1 J. Wenninger BE-OP SPS MPS - ATOP 09.
Beam Interlock System MPP Internal ReviewB. Puccio17-18 th June 2010.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
MP3 List of main Issues during March 2010 MP3 - Team.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
TE/MPE/MI MPE-TM30 th June 2011 FMCM sensitivity to mains perturbations 0v1 M. Zerlauth.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
MPP Workshop Status of Powering Interlocks I. Romera on behalf of MPE-MS MPP Workshop, 12 June 2015, I. Romera (TE-MPE)1.
LBOCM. ZerlauthMarch 06 th 2012 Acknowledgements : B.Todd, C.Martin, I.Romera, E.Carlier, J.Wenninger, C.Zamantzas, S.Redaelli et al. 1v0 MPS Commissioning.
Interfacing the FMCM for additional protection in the LHC and the SPS- LHC/CNGS Transfer Lines to the CERN controls system Cristina Gabriel Casado, Interlock.
TE-MPE-CP, RD, 28-Sep Problems with QPS DAQ Systems During LHC Operation, 1 st Results from 2010 CNRAD Tests R. Denz TE-MPE-CP.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Session 8: What we will do for beam preparation in 2009 G. Arduini, R. Giachino 1Session 8 – Summary - GA24/02/2009.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
MICE Spectrometer Solenoids Step IV running
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
LHC Beam Commissioning Meeting V. Kain & R. Alemany
DRY RUNS 2015 Status and program of the Dry Runs in 2015
R. Denz, A. Gomez Alonso, AT-MEL-PM
Injectors BLM system: PS Ring installation at EYETS
Transfer line test: Beam stability measurements
Potential failure scenarios that can lead to very fast orbit changes and machine protection requirements for HL-LHC operation Daniel Wollmann with input.
M.Jonker CTC MPO-WG status
J. Uythoven for the MPE-MI & MS Teams
352MHz Klystron Control for the 3MeV Linac test stand
Commissioning and Testing the LHC Beam Interlock System
MPS Commissioning and Status
V.Chareyre/H.Thiesen/I.Romera/M.Zerlauth
TEST PLANS for HL LHC IT STRING
MPSC Procedures An update
Saturday 12:00 Fill 1992 in stable beams.
Machine Protection Xu Hongliang.
Electrical Glitch 06:02 Electrical glitch is seen on all circuits connected to the 18kV (RD1.LR1, RD1.LR5, RD34.LR3, RD34.LR7)
Bernhard Holzer, Joerg Wenninger
Week 35 – Technical Stop and Restart
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Beam Dump and Injection Inhibits
Planning at 5 o’clock meeting Friday
Friday Morning 7:30 injection for fill 2908
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
Machine Protection System Commissioning plans
Monday 14:00 beam dump Access:
1v1.
RF Local Protection System
LHC FMCM Project 1.
Beam Interlocks for Detectors and Movable Devices
The LHC Beam Interlock System
Thursday
Monday 27th August & night
31/3/2010 Difficult day… but at the end stable beams.
Wednesday 6.10 Morning: Quench test at 450 GeV
Review of hardware commissioning
SPS Injection BIS - Draft requirements
Presentation transcript:

M. Zerlauth, I. Romera 0v1

FMCM @ LHC 14 Fast Magnet Current Change Monitors already successfully commissioned and in operation for some 2 years in TI2, TI8/CNGS 12 additional FMCMs installed on nc circuits of LHC Separation dipoles RD1.LR1, RD1.LR5 RQ4.LR3/7, RQ5.LR7, RD34.LR3/7 Dump septas RMSD.LR6B1/2 ALICE compensators RBXWTV.R2/L2 Functionality slightly different from TL no fast cycling magnets continuous Beam Permit instead of Permit window Interlock only active > 5% of Unom Need to detect ΔI/I of 3.5*10-4 in <1ms Installed in BIC racks, cables >> Ethernet VME Crate CPU + CTRP VIPC626 RS422 link Measurement of PC or circuit voltage Beam Dump to BIS Voltage Divider & Isolation Amplifier Machine Interlock Systems

Protection of nc circuits Power Converter Beam Dump to BIS Status info WIC Power Permit Thermo-switches @ 60°C + Water Flow Thermo-switches @ 60°C + Water Flow RQ4.LR3/7 RQ5.LR3/7 RD34.LR3/7 Machine Interlock Systems 3 of 5 RD1.LR1/5 RMSD.LR6B1/2 RBXWTV.R2/L2 Beam Dump to BIS

FMCM Supervision Courtesy of N.Hoibian Machine Interlock Systems

1st MPS dry-runs in IR2 Gather first experience for MPS checkout of FMCMs in LHC to Establish conditions for the tests Setting up and tuning of devices Test procedures and duration Documentation of results Profit from HCC powering phase 1 in S12, prepared nc circuits of IR2 for test on 1st of September + Dry-runs for automated procedures to test Beam Permit exchange of main clients with BIS (FMCM, WIC, BLM, BTV,…) Successfully validated first version of sequences in operational environment See future presentation of I.Romera Machine Interlock Systems

Results I_INJECTION Test at I_INJ (Ramp to I_INJ and provoke FGC_STATE Fault) A&B WIC trigger @ 10:23:01. 238264 A&B FMCM trigger @ 243489 Δt [FMCM-WIC] 5.225 ms I @ trigger of WIC 40 A I @ trigger of FMCM 39.999 ΔI/I [WIC] 1.E-04 ΔI/I [FMCM] 0.25 <3.5 Machine Interlock Systems

Results I_NOM Test at I_INJ (Ramp to I_NOM and provoke FGC_STATE Fault) A&B WIC trigger @ 10:40:28. 658266 A&B FMCM trigger @ 662021 Δt [FMCM-WIC] 3.755 ms I @ trigger of WIC 600 A I @ trigger of FMCM 599.9998 ΔI/I [WIC] 1.E-04 ΔI/I [FMCM] 0.0033 <3.5 Machine Interlock Systems

Conclusions Tests were executed as specified in document, <30 min / device FMCM performed (better) than expected, due to slow ramps and more stable supplies Requirements met without difficulties, still > margin in detection threshold For operation thresholds probably to be relaxed in favor of stability (determined not by noise but mainly by di/dt & acc = change of voltage at start / end of PLEP) Add additional test for failure case of V_max applied by converter when at I_INJ in procedure (see studies of A. Gomes Alonso) For FMCM and WIC, MPS tests could be scheduled at early stage – what is an early (but still safe) date to start (still >> interventions ongoing) Nice surprise: Due to new FM352 module, the WIC reacts for this failure case well before the FMCM (internal fault signaled by PC before the output stage is switched off) Machine Interlock Systems

Documentation MPS share-point site: https://espace.cern.ch/LHC-Machine-Protection Machine Interlock Systems

FIN Machine Interlock Systems