Prototype Fabrication, Economic, & Test Plan QDR AAE451: Team 2 Matt Negilski Mike Palumbo Chris Selby Tara Trafton Ashley Brawner Neelam Datta Xing Huang Jesse Jones Presents: The TFM-2
Outline Cost Analysis Build Schedule Flight Test Plans Material cost Team hours Build Schedule Flight Test Plans
Fabrication Cost Analysis Estimated Team Cost: $301.09 Over Budget: $51.09 Exempt Item Cost: $205.95 TOTAL COST: $507.04
Team Hours (Week 8) Total team hours: 1260 Total projected team hours: 2205
Overall Schedule Legend Green = Team Work Blue = Aero Work Red = Propulsion Work Black = Structures Work Purple = D&C Work ♦ = Milestones
Overall Schedule Continued… Legend Green = Team Work Blue = Aero Work Red = Propulsion Work Black = Structures Work Purple = D&C Work ♦ = Milestones
Flight Test Plan Flight regimes Take-off Landing Moderate-slow cruise and loiter Stall/Flapped operation High speed dash
Flight Checks Control surface sizing Control surface operation Electrical connections Structural fasteners Control surface actuators Engine/throttle control Lateral/longitudinal CG check
Tests Test 1 Test 4 Test 2 Test 5 Test 3 Test 6 Static thrust test Low level flight cruise Landing tall grass, no flaps Test 3 Clean stall Flapped stall Landing short grass, with flaps Test 4 High speed Maneuvering Landing short grass, with flaps Test 5 High speed short mission Test 6 Endurance mission