ISEN 315 Spring 2011 Dr. Gary Gaukler. Hierarchy of Planning Forecast of aggregate demand over time horizon Aggregate Production Plan: determine aggregate.

Slides:



Advertisements
Similar presentations
ISEN 315 Spring 2011 Dr. Gary Gaukler. Inventory Control Deterministic inventory control Stochastic inventory control MRP / Lot sizing / JIT Supply chain.
Advertisements

Material requirement planning (MRP)
Material Requirements Planning
Material Requirements Planning (MRP) and ERP
INDEPENDENT - DEPENDENT DEMAND INVENTORY Sekolah Tinggi Manajemen PPM.
ISEN 315 Spring 2011 Dr. Gary Gaukler. 1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead.
15 – 1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. Inventory and MRP 15 For Operations Management, 9e by Krajewski/Ritzman/Malhotra.
Material Requirements Planning
Dependent Inventory: Material Requirements Planning BA 339 Mellie Pullman.
14 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 14 Material Requirements Planning (MRP) and ERP.
4. Production and Material Planning
Material Requirements Planning (MRP)
Push Vs. Pull Part Two – Focus on MRP IE 3265 POM R. R. Lindeke, Ph. D.
© The McGraw-Hill Companies, Inc., Chapter 15 Materials Requirements Planning.
21–1. 21–2 Chapter Twenty-One Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
DOM 301 : Operations Management Practice
ISEN 315 Spring 2011 Dr. Gary Gaukler. Review: Prototype LP Problem Desk manufacturer Regular and rolltop desks, made of wood Regular: 20 sqft pine, 16.
Chair Seat Legs (2) Cross bar Side Rails (2) Cross bar Back Supports (3) Leg Assembly Back Assembly Level Product Structure Tree.
1 1 Slide © 2000 South-Western College Publishing/ITP Slides Prepared by JOHN LOUCKS.
14 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 14 Material Requirements Planning (MRP) and ERP.
© 2004 by Prentice Hall, Inc. Upper Saddle River, N.J Operations Management Material Requirements Planning (MRP) & ERP Chapter 14.
Materials Requirements Planning
1-1 McGraw-Hill/Irwin ©2009 The McGraw-Hill Companies, All Rights Reserved 1 Chapter 18 Materials Requirements Planning.
Operations Management Material Requirements Planning
Material Requirements Planning (MRP)
© 2008 Prentice Hall, Inc.14 – 1 Operations Management Chapter 14 – Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer/Render.
LSM733-PRODUCTION OPERATIONS MANAGEMENT By: OSMAN BIN SAIF LECTURE 22 1.
14 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 14 Material Requirements Planning (MRP) and ERP.
1 Slides used in class may be different from slides in student pack Chapter 16 Materials Requirements Planning  Material Requirements Planning (MRP) 
Murat Kaya, Sabancı Üniversitesi 1 MS 401 Production and Service Systems Operations Spring Material Requirements Planning (MRP) Slide Set #10.
Material Requirements Planning
1 Materials Requirements Planning. 2 Material Requirements Planning Defined Materials requirements planning (MRP) is a means for determining the number.
Irwin/McGraw-Hill © The McGraw-Hill Companies, Inc., 1998 Material Requirements Planning (MRP) Chapter 15 11/7/05 Overview Position of MRP in Operation.
Lecture 9 Materials Requirements Planning Books Introduction to Materials Management, Sixth Edition, J. R. Tony Arnold, P.E., CFPIM, CIRM, Fleming College,
1 Operations Management MRP Lecture 22 (Chapter 14)
Hierarchy of Production Decisions
14 - 1© 2014 Pearson Education Material Requirements Planning (MRP) and ERP PowerPoint presentation to accompany Heizer and Render Operations Management,
4/4: Material Requirements Planning Dependent inventory model For in-house inventory planning.
© The McGraw-Hill Companies, Inc., Master scheduling Material requirements planning Order scheduling Weekly workforce and customer scheduling Daily.
14 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 14 Material Requirements Planning (MRP) and ERP.
McGraw-Hill/Irwin Copyright © 2011 The McGraw-Hill Companies, All Rights Reserved Chapter 18 Material Requirements Planning.
Introduction to Materials Management Chapter 4 – Material Requirements Planning.
Material Requirements Planning (MRP) and ERP
Production Planning and Control
Resource Planning Chapter 15.
Materials Requirements Planning
Operations Fall 2015 Bruce Duggan Providence University College.
Manufacturing Systems Engineering
© The McGraw-Hill Companies, Inc., Chapter 15 Materials Requirements Planning.
INVENTORY CONTROL OF MANUFACTURING SYSTEMS Prof. Dr. Orhan TORKUL Res. Assistant M. Raşit CESUR.
1 The MRP Heuristic  MRP stands for Materials Requirement Planning  It is a widely used approach for production planning and scheduling in industry 
© 2008 Prentice Hall, Inc.14 – 1 Material Requirements Planning (MRP)
Chapter 12: Learning Objectives Instructor Slides You should be able to: 1.Describe the conditions under which MRP is most appropriate 2.Describe the inputs,
Aggregation To combine the creation of many similar products into one relevant measure of activity for the organization. Click here for Hint heuristic.
1 © 2006 The McGraw-Hill Companies, Inc., All Rights Reserved Chapter 16 Materials Requirements Planning.
Material Requirements Planning
MRP and ERP McGraw-Hill/Irwin Copyright © 2012 by The McGraw-Hill Companies, Inc. All rights reserved.
Reid & Sanders, Operations Management © Wiley 2002 Material Requirements Planning 15 C H A P T E R.
SISTEM INFORMASI ENTERPRISE
MATERIAL Requirements planning MRP
Material Requirements Planning (MRP)
Materials Requirements Planning
Chapter 16 Materials Requirements Planning
MRP and ERP.
12 Inventory Management PowerPoint presentation to accompany
Introduction to Materials Management
CHAPTER 14 MRP and ERP.
MATERIAL Requirements planning MRP
Material Requirement Planning (MRP)
Chapter 14 Dependent Demand
Presentation transcript:

ISEN 315 Spring 2011 Dr. Gary Gaukler

Hierarchy of Planning Forecast of aggregate demand over time horizon Aggregate Production Plan: determine aggregate production and workforce levels over time horizon Master Production Schedule: Disaggregate the aggregate plan and determine per-item production levels Materials Requirements Planning: Detailed schedule for production/replenishment activities

Push and Pull Production Control The inventory control methods covered so far are useful for independent demand situations: Now, introduce methods to deal with dependent demand:

Push and Pull Production Control Push system: Determines when and how much to produce based on forecasts of future demands Pull system: Initiates production of an item only when the item is requested

1.Master production schedule 2.Bill of material (BOM) 3.Inventory availability 4.Purchase orders outstanding 5.Lead times Effective use of dependent demand inventory models requires the following Dependent Demand

Specifies what is to be made and when MPS is established in terms of specific products The MPS is a statement of what is to be produced, not a forecast of demand Master Production Schedule

MPS Example Example: How to determine MPS?

List of components, ingredients, and materials needed to make product Provides product structure Items above given level are called parents Items below given level are called children Bill of Materials

B (2) Std. 12 Speaker kit C (3) Std. 12 Speaker kit w/ amp-booster 1 E (2) F (2) Packing box and installation kit of wire, bolts, and screws Std. 12 Speaker booster assembly 2 D (2) 12 Speaker D (2) 12 Speaker G (1) Amp-booster 3 Product structure for Awesome (A) ALevel0 BOM Example

B (2) Std. 12 Speaker kit C (3) Std. 12 Speaker kit w/ amp-booster 1 E (2) F (2) Packing box and installation kit of wire, bolts, and screws Std. 12 Speaker booster assembly 2 D (2) 12 Speaker D (2) 12 Speaker G (1) Amp-booster 3 Product structure for Awesome (A) ALevel0 Part B:2 x number of As = Part C:3 x number of As = Part D:2 x number of Bs + 2 x number of Fs = Part E:2 x number of Bs + 2 x number of Cs = Part F:2 x number of Cs = Part G:1 x number of Fs = BOM Example

The time required to purchase, produce, or assemble an item For purchased items – the time between the recognition of a need and the availability of the item for production For production – the sum of the order, wait, move, setup, store, and run times Lead Times

|||||||||||||||| |||||||||||||||| Time in weeks F 2 weeks 3 weeks 1 week A 2 weeks 1 week D E 2 weeks D G 1 week 2 weeks to produce B C E Start production of D Must have D and E completed here so production can begin on B Time-phased Product Structure

Starts with a production schedule for the end item – 50 units of Item A in week 8 Using the lead time for the item, determine the week in which the order should be released – a 1 week lead time means the order for 50 units should be released in week 7 This step is often called lead time offset or time phasing Determining Gross Requirements

From the BOM, every Item A requires 2 Item Bs – 100 Item Bs are required in week 7 to satisfy the order release for Item A The lead time for the Item B is 2 weeks – release an order for 100 units of Item B in week 5 The timing and quantity for component requirements are determined by the order release of the parent(s) Determining Gross Requirements

The process continues through the entire BOM one level at a time – often called explosion By processing the BOM by level, items with multiple parents are only processed once, saving time and resources and reducing confusion Determining Gross Requirements

Gross Requirements Plan

available inventory net requirements on hand scheduled receipts +–= total requirements gross requirements allocations + The Logic of Net Requirements

Net Requirements Plan

Starts with a production schedule for the end item – 50 units of Item A in week 8 Because there are 10 Item As on hand, only 40 are actually required – (net requirement) = (gross requirement - on- hand inventory) The planned order receipt for Item A in week 8 is 40 units – 40 = Net Requirements Plan

Following the lead time offset procedure, the planned order release for Item A is now 40 units in week 7 The gross requirement for Item B is now 80 units in week 7 There are 15 units of Item B on hand, so the net requirement is 65 units in week 7 A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5 Net Requirements Plan

A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5 The on-hand inventory record for Item B is updated to reflect the use of the 15 items in inventory and shows no on-hand inventory in week 8 Net Requirements Plan

Lot Sizing For MRP Systems Given: Net requirements Determine: When and how much to produce / order

Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Simplest Lot Sizing: Lot-for-Lot

Lot Sizing For MRP Systems Assumptions: Consider only one item Demand known and deterministic Finite horizon No shortages No capacity constraints

Lot Sizing For MRP Systems Problem formulation:

Lot Sizing For MRP Systems Does this look like an EOQ problem?

Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipts Planned order releases Holding cost = $1/week; Setup cost = $100; Average weekly gross requirements = 27; EOQ = 73 units EOQ Lot Size Example

How did we obtain EOQ?

Lot Sizing: Silver-Meal Heuristic In any given period, produce to cover demand in a future period as long as the average cost per period is reduced by doing so Algorithm: 1.Start in period 1. Calculate C(t): average per-period cost if all units for next t periods produced in period 1. 2.Select lowest t such that C(t)<C(t+1): t* 3.Produce t* in period 1 4.Repeat, starting from period t*+1

Silver-Meal Example Assume net requirements are 18, 30, 42, 5, 20 Setup cost for production is $80 Holding cost $2 per unit per period