Utilizing IED Capability to Reduce Wiring Terrence Smith, GE Digital Energy Multilin Richard Hunt, GE Digital Energy Multilin Jakov Vico, GE Digital Energy Multilin
Introduction Reducing Wiring is not a new concept
Introduction Review of the Design/Installation Process A case study of a medium voltage breaker A case study of a transmission breaker A case study of a control IED as a transformer alarm aggregator
Introduction A case study of a high voltage circuit breaker using process bus. A look at the direction the industry will likely head. Rules we can develop from the case studies.
Introduction-How the design is communicated Typical Schematic Diagram
Introduction-How the design is communicated Typical Wiring Diagram
Introduction-How the design is communicated The design process
Introduction-How the design is communicated The design process
Case Study One- Medium Voltage Switchgear
Replace with IED Pushbutton
Case Study One- Medium Voltage Switchgear Replace with Latching Elements and IED Communications
Case Study One- Medium Voltage Switchgear Replace IED to SCADA communications
Case Study One- Medium Voltage Switchgear
Replaces Control Switch
Case Study One- Medium Voltage Switchgear Replaces SCADA Trip Contact
Case Study One- Medium Voltage Switchgear Replaces Lockout Relays
Case Study One- Medium Voltage Switchgear The new circuit is much simpler
Case Study One- Medium Voltage Switchgear The real value of internal lockout relays is seen in the close circuit
Case Study One- Medium Voltage Switchgear
Close Operands
Case Study One- Medium Voltage Switchgear Close Operands Block Close Logic
Case Study One- Medium Voltage Switchgear Optimization Benefits 1. Simpler Circuits meaning reduced design time, reduced wiring time, and reduced commissioning time. 2. Bench tested logic replaces wiring which reduces commissioning time. 3. Logic is repeatable and consistent.
Case Study One- Medium Voltage Switchgear Optimization Challenges 1. Cost of communications equipment, design, and installation 2. Operational challenges associated with process change.
Case Study Two – Breaker and a Half Scheme
62 wires and 124 terminations for one breaker of this scheme.
Case Study Two – Breaker and a Half Scheme
Case Study Three – Transformer Alarm Aggregator
Case Study Three – High Voltage Breaker with Process Bus
Future Directions – A station IED
Conclusions Rule #1: Wire a Process Value once and only once. Rule #2: If a function does not have to be wired, then dont.
35