LHC Morning Meeting - G. Arduini

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
LHC Status Fri Morning 3-June
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday
Wednesday 3rd October - morning
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Wednesday September 14th
Friday 18/03 07:15 Test ramp with pilot after the test of dynamic FIDEL correction. Ramp was OK, but fill was stopped due to the trip of several RQTFs.
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Monday 11/07: Recovery Plenty of accesses.
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Summary of Week 11: 14 – 21 March
Coordination: Gianluigi Arduini & Jan Uythoven
LHC Morning Meeting - G. Arduini
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Wednesday 8th August & night
LHC Morning Meeting - G. Arduini
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Friday 14th December - morning
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Chromaticity can make a difference…
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Wire almost entirely through beam before BLM triggers dump
LHC Morning Meeting - G. Arduini
Yesterday’s morning’s controls issues
Friday Morning 7:30 injection for fill 2908
LHC Morning Meeting - G. Arduini
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
LHC Morning Meeting - G. Arduini
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
LHC Morning Meeting - G. Arduini
Thursday Fill 1364 (24 bunch) dumped at 07h
Friday 25 bunch fill dumped just before (BLM in 5)
Saturday 3rd November - morning
LHC Morning Meeting - G. Arduini
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
LHC Morning Meeting - G. Arduini
LHC - Week 38 Technical stop: Katy Foraz
Wednesday 23/2 Thanks CRYO!!!.
Saturday 24 September 2011.
Wednesday h18: 228b fill lost just before start of ramp.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Saturday 6th October 05:38 STABLE BEAMS # :06 OP dump
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Wednesday 6.10 Morning: Quench test at 450 GeV
Wednesday Following the struggle with the vacuum in IR2 over the night, drop intensity to 1.2E11/bunch. Fill first B1 – pretty quiet – then B2 – quite.
Tuesday
Presentation transcript:

LHC Morning Meeting - G. Arduini Tue 13/11 – Wed 14/11 06:30 Cryogenics back – pre-cycle. 08:00 Injecting pilots, steering. 09:00 No beam from injectors, problem with Booster distributor. 11:35 Booster back. Check injection 144 bunches: OK. 12:00 Set-up of gated BBQ for B2. 12:30 Continue filling for physics: very clean. 13:00 Start ramp fill 3285. Good signal on gated BBQ for both beams without chirp. Some losses on the B2 6 bunches (lower gain – factor 2 -of the damper as compared to B1) 13:56 Stable beams, initial lumi's around 7.2 e33, ALICE 3.3e30 cm-2s-1. 24:00 End of fill 3285. OP dump.153 pb-1 in ~10 h. 03:30 Stable beams #3286, initial lumi's up 7.5 e33 cm-2s-1. 07/12/2018 LHC Morning Meeting - G. Arduini

Optimization BBQ-high sensitivity Not yet ideal for all possible bunch configurations from nominal to full machine but good settings for ramp found. Ramp without chirp. M. Gasior, R. Steinhagen 07/12/2018 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Injection For the time being running with satellite enhancement OFF in the PS and no controlled longitudinal blow-up at injection Very clean injections 07/12/2018 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Injection Beam injected No beam injected but MKI firing This indicates that the observed losses on Monday are likely due to the injected beam (satellites) and not to uncaptured beam kicked out at the moment of injection  Next step switch-on longitudinal blow-up to 1.4 ns to confirm that 07/12/2018 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Longitudinal blow-up Still unwanted longitudinal blow-up on B2 even after reset of (we thought) all parameters. But due to a bug this was not the case. Another version of the longitudinal blow-up deployed for the last ramp with initialization of gain parameters at every new injection  Fixed 07/12/2018 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Too short rise-time observed on dump at injection (programmed dump of circulating pilot after machine parameter verification). Following verification dumps requested by Jan did not show any problem. Will be followed up today 07/12/2018 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Fill #3286 Last ramp with increased gain of damper during the whole ramp (factor 2) and no chirp. Well behaved. Some losses at the end of the squeeze (instability still there) Stable beams #3286 ALICE up to 6.5x1030 cm-2s-1 with natural satellites 07/12/2018 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Plan Physics: Parameters being scanned (one at a time): Longitudinal blow-up at injection (next fill 1.4 ns) Damper gain during the ramp to try and minimize blow-up now that gated BBQ is operational Tune split during the squeeze to get rid of instability at the end of the squeeze Pending access: PM32 : CV to check / remove sand. Access system 07/12/2018 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Tue 13/11 BBQ "high sensitivity" systems are now optimised for pilots and to operate correctly with high intensity nominal bunches the frond-end settings have to be changed. In the attached plots are shown spectra for 6 nominal bunches for B1 and three values of the diode detector time constants. The first plot shows the spectra for the "standard pilot settings", that is with the largest time constant. For nominal bunches in those conditions the bunch intensity variations may cause the detectors to trigger on different bunches, resulting in the noisy spectra. When the time constant is reduced (second plot), the steady-state peak detector voltage is lower, making the detectors to trigger also on less intense bunches, resulting in cleaner beam spectra. Reducing the time constant further (third plot) lowers again the steady-state detector voltage, causing the system to detect bunches with yet lower intensity. This setting may be optimal when operating with the full machine but is not optimal for pilot beams. An optimisation of the operation of the "high sensitivity" systems in different beam conditions requires software changes. Marek and Ralph 07/12/2018 LHC Morning Meeting - G. Arduini