PLANNING ENGINEERING AND PROJECT MANAGEMENT

Slides:



Advertisements
Similar presentations
CP Chapter 4 Schedule Planning.
Advertisements

PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Chapter 10: Project Schedule Planning
Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George.
Project Time Management
Project Management Techniques.
Project Time Management
Project Planning Basics Project: set of activities which ends with specific accomplishment (the goal) –Non-routine tasks –Distinct start/finish dates –Resource.
LSU 10/09/2007Project Schedule1 The Project Schedule Project Management Unit #4.
Managing Project Scheduling. What is Project Scheduling? The process of: – defining project activities – determining their sequence – estimating their.
Chapter 6 Introduction to Microsoft Project
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
BSBPMG402A Apply Time Management Techniques 1 Apply Time Management Techniques Week 6 Project Time Processes – Part 2 C ertificate IV in Project Management.
EGNR 300 Project Management Planning & Scheduling ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport,
~ pertemuan 6 ~ Oleh: Ir. Abdul Hayat, MTI 03-Apr-2009 [Abdul Hayat, Project Time Management, Semester Genap 2008/2009] 1 PROJECT TIME MANAGEMENT.
Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.
Lecture 3 Scheduling CSCI – 3350 Software Engineering II Fall 2014 Bill Pine.
Gantt Chart Heba Iqbal. What is a Gantt chart? Developed by Henry Gantt Were considered revolutionary when first introduced Type of bar chart Illustrates.
Work Systems and the Methods, Measurement, and Management of Work by Mikell P. Groover, ISBN ©2007 Pearson Education, Inc., Upper Saddle.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects… Project Planning and Control Project Life Cycle Gantt Chart PERT/CPM.
PROJECT MANAGEMENT Approaches
12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.
PROJECT MANAGEMENT Outline What is project mean? Examples of projects…
Chapter 7 – PERT, CPM and Critical Chain Operations Management by R. Dan Reid & Nada R. Sanders 4th Edition © Wiley 2010.
(M) Chapter 12 MANGT 662 (A): Procurement, Logistics and Supply Chain Design Purchasing and Supply Chain Analysis (1/2)
Project Scheduling. Why Are Projects Late? an unrealistic deadline established by someone outside the software development group changing customer requirements.
Project Planning & Scheduling What is a “project”? Objectives and tradeoffs Planning and Control in Projects Scheduling Methods Constant-Time Networks.
WEEK 3 Project Planning.
BSBPMG503A Manage Project Time Manage Project Time Project Time Processes Part 2 Diploma of Project Management Qualification Code BSB51507 Unit Code.
Project Management Planning and Scheduling. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling Planning: “what” is.
MANAGEMENT of INFORMATION SECURITY, Fifth Edition.
© 2008 Prentice Hall6-1 Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and.
Chapter 16 – Project Management
Project Management.
Project Management – PTM721S
PROJECT MANAGEMENT.
Project Management MGT 30725
Project Management Systems
By Wilmer Arellano Spring 2010
Gantt Chart Presentation Name Course Name
Project Planning & Scheduling
Project Scheduling
Project Controls: As-Built S-Curves
Most commonly used methods for project management.
PART SIX PROJECT MANAGEMENT Chapter Eighteen Project Management.
Project Planning & Scheduling
2nd Task of Your Project „All you have to decide, is what to do with the time that is given to you.“ J.R.R. Tollkin Prof. Dr. Christian Bleis 1 Interaktionskompetenz.
17 Project Management.
Chapter 6: Project Time Management
Chapter 6: Project Time Management
CHAPTER 6 PROJECT TIME MANAGEMENT
ENGINEERING MANAGEMENT (GE 404)
Project Time Management
17 Project Management.
ENGINEERING MANAGEMENT (GE 404)
PLANNING ENGINEERING AND PROJECT MANAGEMENT
Stevenson 17 Project Management.
Prepared by Lee Revere and John Large
Critical Path Method Farrokh Alemi, Ph.D.
Gantt Chart.
P ROJECT M ANAGEMENT Skills.
Information System Analysis
Project Management CPM/PERT Professor Ahmadi.
Modern Systems Analysis and Design Third Edition
Importance of Project Schedules
CHAPTER 6 PROJECT TIME MANAGEMENT
Modern Systems Analysis and Design Third Edition
Scheduling.
Presentation transcript:

PLANNING ENGINEERING AND PROJECT MANAGEMENT Lecture#06 PLANNING ENGINEERING AND PROJECT MANAGEMENT By Lec. Junaid Arshad DEPARTMENT OF ENGINEERING MANAGEMENT

Topics Covered Dependent and Independent Activities Dependency and Precedence Relationship Project Scheduling Guidelines for Estimating Duration Probability Considerations in Project Scheduling Gantt Chart

Dependent and Independent Activities An essential concept behind project planning is that some activities are dependent on other activities being completed first. As an example, you cannot start building a bridge before you have finished designing it. These dependent activities need to be completed in a sequence, with each activity being completed before the next activity can begin. We can call dependent activities sequential or linear.  Independent activities are not dependent on completion of any other activity. These are nondependent or parallel activities.

Dependency and Precedence Relationship Dependency is the timing relationship that exists between two activities. The earlier activity in a dependency relationship is referred to as the predecessor and the later is known as successor. The precedence relationship is given by defining the immediate preceding activities.

Precedence Relationship Immediately preceding Activity Description

Precedence Relationship Predecessors (Dependencies)   Activity Predecessors (Dependencies) A - B C D E F G H I J G - H

Project Scheduling Project scheduling involves sequencing and allotting time to all project activities. At this stage, managers decide how long each activity will take and compute how many people and materials will be needed at each stage.

Accurate Project Scheduling requires an understanding of : The interdependencies among project activities and events (network diagramming) The duration of various activities that comprise the network (duration estimating) The availability of resources (resource leveling) Mathematical models for analyzing these interdependencies and availabilities (Pert and CPM)

of starting and completion (dates) of the Project Schedule: Project Schedule shows the time frame of starting and completion (dates) of the activities constituting the project. PMI defines the Project Schedule as The planned dates for performing project activities and meeting project milestones.

Activity In the definition of schedule, activities refer to the lowest level elements of WBS. An activity consume resources and takes time to complete. Event The start point or the finish point of one or more activities. An event occurs at a particular point in time without duration. Event does not consume resources. Milestone Milestones refer to key events in a project. Milestones are important checkpoints for a project. Milestones can be used to catch scheduling problems early.

Guidelines for Estimating Duration Duration estimating involves assessing the number of work periods (hours, days, weeks) required to complete each individual activity. Guidelines for Estimating Duration The following guidelines are offered to assist in the duration estimating process and to improve estimating accuracy.

Note: These guidelines have been developed assuming that resources are being considered conceptually, but not actually assigned at this time. Obviously, the labour resources assigned to a task can affect its overall duration. It is common to estimate task duration first by thinking conceptually about the level of resource assignments. Once resources are actually assigned, the activity durations can be further refined and adjusted as necessary.

Whenever possible, make use of in-house experience Whenever possible, make use of in-house experience. Seek out individuals who may have performed activities in the past. Have the people who will be responsible for performing a given task provide duration estimates. This does not mean talking only to task managers, but also to technicians, field engineers etc. These individuals have a tremendous amount of knowledge that should not be overlooked. Make all time estimates realistic, without an optimistic or pessimistic view.

Assume that the work will be performed with a normal level of labour and equipment. Although completion of tasks can often be accelerated by adding more people and/or equipment it is best not to assume an exaggerated level of effort. An exception would be where an analysis of the network indicates that the customer’s required finish date can not be met with a normal level of effort. Assume a normal workweek and a normal workday. Use consistent time units for all activity durations.

7.Be willing to break activities into smaller units (work packages) if there seems to be great difficulty in estimating a particular activity. (If this is done the work breakdown structure and network diagram will require updating) 8.Do not assume that a worker will have eight hours of uninterrupted time to work on a task e.g. office workers are constantly interrupted by phone calls, other office personnel, meetings. 9.Because reports require revisions, be sure to include editing time (beyond your original estimate) for making the necessary changes.

Probability Considerations in Project Scheduling Two types of time estimates are used for activity duration. Deterministic times or definite times, where the activity duration can be calculated from the quantity of work, rate of work done with a specific resource allocation. Probabilistic time estimates are used when past data or knowledge is insufficient or where uncontrollable environmental factors exist.

TE=(a + b + 4m)/6 Expected Time: Probability considerations are incorporated in project scheduling by assuming that the time estimate for each activity is based on three different values a = optimistic time (which will be required if execution goes extremely well) b = pessimistic time (which will be required if execution goes badly) m = most likely time (which will be required if execution is normal) TE=(a + b + 4m)/6 Expected Time:

mid point=(a + b)/2 most likely time=m The most likely time is given double weightage than the mid point for calculating the arithmetic means Arithmetic means of (a + b)/2 and 2m = (a + b)/2 + m + m 3 = (a + b + 4m)/6 Expected Time

Note: Activity Optimistic time a Most likely time m Pessimistic time b Expected time (TE) x 4 10 16 y 2 12 11 z 6 38 18 Note: The most likely estimate ‘m’ need not to coincide with the midpoint (a + b)/2

Gantt Chart One popular project scheduling approach is the Gantt chart. Gantt charts are low cost means of helping managers to make sure that All activities are planned for Their order of performance is accounted for The activity time estimates are recorded The overall project time is developed

In a Gantt chart, each activity takes up one row In a Gantt chart, each activity takes up one row. Activities may run sequentially or in parallel. Dates run along the top in increments of days, weeks or months, depending on the total length of the project. Decide what resolution to use in the timeline. For projects of three months or less, use days, for longer projects use weeks or months, and for very short project use hours. The expected time for each activity is represented by a horizontal bar whose left end marks the expected beginning of the activity and whose right end marks the expected completion date.

Gantt Chart Task Duration Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 1 2 mo.   2 3 4 5 6

Monitoring When a project is under way, Gantt Charts are useful for monitoring its progress. You can immediately see what should have been achieved at a point in time, and can therefore take remedial action to bring the project back on course. As the project progresses, the chart is updated by filling in the bars to a length proportional to the fraction of work that has been accomplished on the activity.

This way, one can get a quick reading of project progress by drawing a vertical line through the chart at the current date. Completed activities lie to the left of the line and are completely filled in. Current activities cross the line and are behind schedule if their filled-in section is to the left of the line and ahead of schedule if the filled-in section stops to the right of the line. Future activities lie completely to the right of the line.

In constructing a Gantt Chart, keep the activities to a manageable number (no more than 15 or 20) so that the chart fits on a single page. More complex projects may require subordinate charts which detail the timing of all the subtasks which make up one of the main tasks. For team projects, it often helps to have an additional column containing numbers or initials which identify who on the team is responsible for the task.

Gantt Chart

Gantt Chart

Gantt Chart

Q&A