D-Cal production preparations in Japan Dec. 16, 2009, D-Cal meeting at CERN Tatsuya Chujo (Univ. of Tsukuba) for the D-Cal Project 1.

Slides:



Advertisements
Similar presentations
P. Checchia Como 8th ICATPP1 LCcal * : a Calorimeter prototype for future Linear Colliders Design principles Prototype description Construction.
Advertisements

PREX main detector Piotr Decowski Aimee Shore Smith College Piotr Decowski Aimee Shore Smith College Kumar Krishna Jon Wexler Patrick Rogan Vireak Yim.
Mechanical Modernization Project Creating the Best Choice in Urban Education St. Louis Public Schools Department of Operations June 26, 2008 Roger L. CayCe.
$100 $200 $300 $400 $500 $100 $200 $300 $400 $500 $100 $200 $300 $400 $500 $100 $200 $300 $400 $500 $100 $200 $300 $400 $500 $100 $200 $300.
Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
LHCb VELO Production Visit November 9 th 2005 Introduction to staff Status Schedule.
Welcome to Who Wants to be a Millionaire
LHC CMS Detector Upgrade Project US CMS Trigger Upgrade Introduction to Cost & Schedule Wesley Smith, U. Wisconsin Fermilab Directors Review 16 July 2013.
Prototype sPHENIX Calorimeters
LINAC 4 Emittance Meter.
Chapter 4 Estimating and Reducing Labor Costs
CHAPTER 10: REPORTING AND ANALYZING LIABILITIES
CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE EE crystals.
Apprenticeship Grant for Employers of 16 to 24 year olds (AGE 16 to 24) Employer Update Presented by DMT Business Services.
Equal or Not. Equal or Not
1 - $ $ $ $1, $2, $4, $8, $16, $32, $64, $125, $250, $500,000.
SNS Spallation Neutrino Source 1 SNS layout GeV proton linear accelerator Accumulator ring Main target Stripping foil.
Fundamentals of Cost Analysis for Decision Making
Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
HCAL-J Status Hadron Calorimeter HCAL-J SBS Collaboration Meeting July, 2014 G. B. Franklin Carnegie Mellon University 7/8/2014 Carnegie Mellon INFN, Catania.
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
MINER A Director’s CD-3b Review 11 June 2007 Kevin McFarland University of Rochester 1MINERvA WBS 1,2,4: Scintillator and Fiber Fiber Milestones: WLS Fiber.
EMCAL: project update - Italy - LNF - Frascati Fixture production Module assembly (proto) WLS fibers processing Lead procurement (proto) CT- Catania APD.
DCal Meeting
EMCal Meeting CERN – July 2 nd 2007 LPSC Status 1 J-F Muraz LPSC Status LPSC Status.  Assembly Hall. - Removal starts and is in progress. - Main infrastructure.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
HCAL-J Update (G.B. Franklin, CMU, Mar. 2015) 40 Ton Detector 288 modules Arranged in 4 sub-assemblies 24 Modules (360 cm) 12 Modules (180 cm) 1 Absorbers.
PCB issues requirements & procurement MMM Würzburg, 30/01/2014J. Wotschack1.
1 HBD Construction status Itzhak Tserruya DC meeting, BNL, February, 2006 Plans for Run-6 Box construction GEM assembly and testing Status of urgent items.
Status of the PSD (Jan. 2009) F.Guber, INR, Moscow.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
0 The LHCb Hadron Calorimeter Rustem Dzhelyadin, (IHEP, Protvino) INSTR02 Conference, BNPI, Novosibirsk, Russia Contents: Œ Design overview  Trigger with.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
ALICE high p T workshop, LBNL, April 7, 2009 (T. Chujo) J-Cal Construction Plan Tatsuya Chujo University of Tsukuba (for the ALICE J-Cal Project) 1.
Toward the FNAL Beam Test S. Uozumi (Kobe) May Japan-Korea meeting.
ECAL LED monitoring system upgrade Pavel Shatalov ITEP, Moscow, Russia Yuri Guz IHEP Protvino, Russia.
Status of the development of Mini-Camera for the 1 st LST camera. Toko Konan Univ. Japan A test module for the 1 st LST camera, which is called.
 YE+4 disks = 2 Nos. (12 Sectors each)  Support Structures = 2Nos.  AISI 1045 steel bar = 1 No. for checking dimension of 680 mm (0/-0.5)  Fasteners.
Status Report for KEK-PS E391a KEK IPNS G.Y.Lim 14 April 2003.
15/07/2008 EMCAL Meeting Nantes A. Palmeri - F. Noto I.N.F.N. Catania1 EMCAL CATANIA A. Palmeri - F. Noto.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
EMCal Status ALICE Technical Board November 20, 2008 News Schedule.
VVS Prototype Construction at Fermilab Erik Ramberg 26 February,2002 Design issues for VVS Details of VVS prototype design Schedule and Budget Testing.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
Progress with DDIA-30 Mark Rivers Yanbin Wang Clayton Pullins.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
P. Checchia ECFA-DESY Prague1 Status report of the tile-Si Lccal * project Prototype description Production Beam test results Future plans *
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
SCT week: 14th - 16th Dec 04 Spine progress R. Bates University of Glasgow.
26-Feb-16S.Movchan Straw manufacturing and QC1 Dubna NA62 straw tracker assembly area (milestone) halls plans conclusion Presented by S.Movchan.
EMCal Meeting Nantes – July J-F Muraz  Grenoble Status  Assembly and test Hall.
EMCAL Calibration & Assembly at Yale University Mark Heinz, Project Mgr EMCAL Meeting Nantes July 15, 2008.
Modules components procurement EU Lead US Lead EU Scintillators US Scintillators EU Bond Paper US Bond Paper EU Straps US Straps EU BackPlate US BackPlate.
July 20, 2007Anita Topkar, BARC PSD Production: Present Status Dr Anita Topkar BARC.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
【New Draft】 France -Japan International Co-funding Joint call Schedule (revised version) APR. 11, 2017 Bpifrance / NEDO final meeting (week of 18/9) Announcement.
SPF MAG Quarterly Report – Feb 2015
Experimental Method: 2 independent detectors on both sides of IP
T1 status (a selection from EDR presentations)
MLC Schedule Plan Proven in-house expertise and infrastructure for fabrication, assembly, and testing cryomodules Confident in our technical expertise.
SCHEDULE Nov 1st - Assembly Table Complete
Support Structure Fabrication
Design of the He and HB ODU
EMCal – France Status report, July 2008 Manpower Technical activities
Beam Wire Scanners (PS prototype and LIU series)
Status of the PANDA Solenoid Magnet Production in BINP
PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100%
Experimental Method: 2 independent detectors on both sides of IP
Presentation transcript:

D-Cal production preparations in Japan Dec. 16, 2009, D-Cal meeting at CERN Tatsuya Chujo (Univ. of Tsukuba) for the D-Cal Project 1

Overview: We have finished the order for all major parts to build 288 EMCal modules. Some of the smaller parts have been already delivered. Bigger ones, like lead tiles, scintillator, aluminum parts, will be delivered by the end of March 2010 in Japan. Our Plan: Setting up the module assembly station in Tsukuba, on March or April with a help from WSU tech. At the same time, we are preparing the load cells (3 sets) in order to have the own pressure control & monitoring system in Tsukuba. They will be ready by March (by M. Inaba). Start the mass production in Apr. 2010, and continue until July-Aug (to be discussed at this meeting). Ship the modules to Nantes or Grenoble, for the strip, SM assembly and calibration around Aug-Sep. 2010, depending on the installation schedule. 2

Parts status (1) Lead tiles [order completed] Source: Vulcan (import agent: Yatoro Elec. co.) Status: Order has been completed for 288 modules (= 21,888 tiles) (Sep. 4, 2009) Time estimate: Production line in November. 9 weeks after the production start, delivery in Feb (TBC) Notes: perform own cleaning. Unit price: 3.19 USD. Scintillator tiles [order completed] Source: UNIPLAST (Russia) Status: Order completed for 95,000 tiles and made a contract (Dec. 2009) Time estimate: (1) 50,000 tiles in Feb., (2) 45,000 tiles in Apr. & May. Notes: perform own cutting (by Japanese workshop) and painting (by students) after delivery. 3

Parts status (2) Aluminum parts (front, back, compression plates). [order completed] Source: Meccanotecnica RIESI S.R.I. (Italy) (import agent: Yatoro Elec. co.) Status: order completed, Quantity: 300 each. Time estimate: Mar (TBC) Notes: Machining components immediately after the last slot for WSU. Eng. Francesco Noto (INFN) will perform dimensional control (Nov.19, Rosy Trovato). Plunger pins will be ordered (Japanese workshop or MECCANOTECNICA) 4

Parts status (3) Inter-layer paper sheets [order completed] Source: KRICK Kunststoff (Germany) Status: 55,000 in total (4 different kinds of sheets) Time: delivered by Jan Fabrication of sheets ready (Dec. 11, 2009). Stainless Steel Straps [order completed] Source: IPSC, Grenoble (France) Status: 1,200 straps ordered. Raw materials have been purchased, and start cutting. Time: 400 foils will be ready (wire cut) by end of Dec Producing the 1,200 straps by end of Jan Need to discuss the payment method, and cost shearing. 5

Parts status (4) WLS Fibers [order completed] Source: Kuraray trading Status: Ordered 43,200 (40 cm length, pre cut). Time: will be delivered on Jan. 25, 2010 Note: Aluminized & polishing by Japanese workshop. Will perform the test for aluminized and polishing in Feb. Unit price: 119 JPY Bellvilles washers [delivered] Source: Schnorr Corp, via Hohsen Corporation (Japanese representative) Status: 23,000 washers delivered. Time: - Light Guide [delivered] Source: I & G tool (USA). Status: 1,200 pc delivered. Time: - 6

Parts status (5) Black tape [delivered] Source: Sony Chemical & Information Device Co. (bender: Yasuda sangyo KK). Status: 1 roll (500 x 200 M), Delivered. Time: - Note: will be cut by Japanese workshop (already ordered). Optical cement [delivered] Source: Saint Gobain. Status: BC-600 (2 sets, 250 ml) delivered. Time: - Reflector paint [delivered] Source: Saint Gobain. Status: BC-620, 2 PC (1L each) delivered. Time: - 7

Module Assembly Station Source: from WSU Status: Completed the shipping arrangement for first station. Time: One station will be delivered in Dec. 2009, another station in Mar Note: 192 modules x 2 SM = 384 modules 6 months for 2 stations 4 months for 3 stations 8

Items to be done in Japan 1. Black tape cutting 2. Scintillator cutting & polishing & painting 3. WLS fiber aluminized & polishing 4. WLS bundle assembly 5. WLS fiber holder & receiver 6. Load cell aluminum frame 9

Open issue (1) Module production schedule in Tsukuba. - 2 stations enough? - Need a detail schedule for assemble of module, strip, SM, & shipping, work sharing modules --> 384 modules?? ~100 additional. - If there is a delay of scintillator delivery, can expect the contributions from WSU?. (2) Integration issue. - strong back & strip, SM integration, which are not included in the current budget projection in Tsukuba. (3) APD, preamp, FEM (purchase plan, work share?). FEE: components have been purchased for 50 FEE boards. (4) Jig for fiber bundle (can be borrowed from Wayne State?). (6) Aluminized Y11 fiber check by experts needed (thickness)? (7) Y11 fiber bundle, holder, O-ring. check the drawings. (8) How to perform the cosmic ray test for EMCal Grenoble. (9) Payment for straps (via CERN account?), and share of strap cost. (10) Check plunger pin drawings (new version). (11) Clack on Light Guide OK? (12) Plan to visit WSU in Feb. or Mar. to learn the module production. 10

Summary: Ordering the parts and tools for 288 modules have been completed. Need to discuss the schedule, work sharing, coordination etc. at this meeting (e.g. making additional ~100 modules in Tsukuba). 11