Las Delicias, El Salvador Water Supply Project Implementation Proposal Phase I Trip Dates: May 2012 Presented to TAC: March 6, 2012.

Slides:



Advertisements
Similar presentations
1 Laboratory RFP Q & A session Simon Everitt / Joy Cooper Planning and Funding 18 th August 2006.
Advertisements

Las Delicias, El Salvador Water Supply Project Current Project Status, January 2010 Richard Cairncross & David Haussler.
MBTA Groundwater Action Plan Dr. Steve J. Poulos, P.E.
Relay in the Urban Setting Making Water Supply Work for You!
County of Fairfax, Virginia Board Transportation Committee Updates on Alternatives for Improving Roadway Services in Fairfax County Discussion of Converting.
September Wood to Warmth – Heat Networks Michael Beech TV Energy.
1 Intelligent Energy Europe 2009 European Commission, EACI Market Replication Eco-Innovation and Intelligent Energy Astrid Geiger, Head of Sector Energy.
April 19, 2012 SBE Presentation on Performance Evaluations.
Antti Piirto The first EPR under Construction in Finland International Nuclear Forum 2008 ”Bulgarian Nuclear Energy – National, Regional and.
Underground Storage Tanks at Duke Duke Medical Center –8 permitted USTs located on medical campus –Range in size from 2,000 gallons to 30,000 gallons Proper.
Budget Update January 26, Our Priorities have not changed… Students Employees.
Agreement between the Village of Owego and Inflection Energy.
Irrigation Water Conveyance
Water Distribution Systems – Part 1
1 Beachcomber Bay Sewer Lift Station Homeowners believe a better solution is available for both the City and the Homeowners.
Green Building Ordinance Transportation and Environment Committee
Ultra-Low Freezer Rebate Program Report Fiscal Year
City of Olympia | Capital of Washington State Percival Landing Update Land Use Committee Meeting March 27, 2014.
Methow Valley Irrigation District Alternatives Evaluation Presented by Bob Montgomery, P.E. and David Rice, P.E. January 31, 2013.
Lindbergh Field International Airport New Terminal Bill Mahoney LSW Engineers.
1 © 2011 Regents of the University of Minnesota. All rights reserved. 11 A UNIVERSITY OF MINNESOTA EXTENSION LEECH LAKE BAND OF OJIBWE PARTNERSHIP SHIRLEY.
WASH Cluster – Groundwater Pumping GWP GWP3 1 Groundwater Pumping Session 3 Pump Selection.
Agrichemical Containment Facility. NRCS Standard Practice 702 NRCS Practice Standard 702 AGRICHEMICAL CONTAINMENT FACILITY MDA REG. 640 Commercial Pesticide.
Wastewater Collection (Sewer Alternatives). Sewer Basics Collection and transport of wastewater from each home/building to the point where treatment occurs.
 Meaning: Establishment of an industry at a particular place.  It refers to the choice of region and the selection of a particular site for setting.
COLEGIO CRISTIANO AVIVANDO EL FUEGO
Potential Pathways for Coliform Contamination. Fixing Positive Coliform Results.
Energy Savings from Supplying Drinking Water at Two Pressure Levels - a Retrofit in Las Delicias, El Salvador, EWB-MAP Presented by Adam A. Brostow November.
BOB BROZ UNIVERSITY OF MISSOURI EXTENSION (573) ISE #78 WATER MANAGEMENT STRATEGIES FOR DROUGHT MITIGATION AND SUSTAINABLE AGRICULTURAL PRODUCTION.
Nunavut Water Board Public Meeting Water Licence Amendment Rankin Inlet 3AM-GRA-1015 January
Gravity Water Supply Design
Basic Hydraulics Irrigation.
Energy Savings from Supplying Drinking Water at Two Pressure Levels - a Retrofit in Las Delicias, El Salvador, EWB-MAP.
Las Delicias, El Salvador Water Supply Project Current Project Status, January 2010 Richard Cairncross & David Haussler.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2012 Updated: 2/12/2012.
ENGINEERS WITHOUT BORDERS USA ALAMO PROFESSIONAL CHAPTER.
Hydronic Mechanical Controls
2010 Pipe Dreams Team: Ibrahim Ibrahim, Mike Johnson, Scott McCombie, Bronze Richards & Josh Schroeder.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2012 Update: 2/2/2012.
Potential Underground Wiring Meeting with Residents Wednesday, September 15, 2010 lionsbay.ca Lower Lions Bay Water Line Replacement The Village of Lions.
Las Delicias, El Salvador Water Supply Project Implementation Proposal Phase I Trip Dates: May 2012 Presented to TAC: March 7, 2012.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2011.
EWB-MAP Water Tank Project Construction Progress June 5-12, 2012.
1 CTC 450 Review Water Quality Water Quality. 2 CTC 450 Water Distribution Systems Water Distribution Systems.
Lec.16 Underground pipeline irrigation system - structures for underground pipelines.
Project Location: El Chaguite, Yoro District, Honduras Northeastern University’s Student Chapter 1Project: El Chaguite Water System.
City of Polson April 5, 2010 PUBLIC HEARING Water System Improvements PRESENTATION ON PRELIMINARY ENGINEERING REPORT.
Engineers Without Borders H&S Presentation
Imagine the result Impact Study on MSD Rate Payers of Proposed Consolidation/Merger Phase II – Towns of Biltmore Forest, Montreat and Weaverville Presentation.
Water for Life Project Apatut, La Union, Philippines
EWB-NCSU Bolivia Water Supply Project. Why Do They Need Additional Water Supplies? School Students Add to Population Rainfall – Avg. 8.5 in/yr – 0.7 in/month.
Safe Drinking Water Permit and Capacity Requirements Developer Services Summit November 16, 2010 Engineering - Asset Planning Vince Monaco.
Engineers Without Borders CCNY Chapter Project in Milla Tres, Honduras August 2012.
Engineers Without Borders-USA 2009 Midwest Workshop.
10 Frequently Asked Questions about Center Pivots Gulf Coast Irrigation Conference Sinton, November 18, 2008 Guy Fipps Professor and Extension Agricultural.
Review of the Nipissar Lake Replenishment Project, Rankin Inlet, Nunavut September 25, 2014 NWB Hearing Presentation Type A Water License Amendment Application.
LCWDBoardMtg_ pptx/1 LCWD Board Meeting January 14, Carneros Avenue, Napa Los Carneros Water District.
1 What is Precast Concrete? Precast concrete consists of a mixture of cement, water, aggregates and admixtures. This mixture is cast into a specific shape.
BASICS IN IRRIGATION ENGINEERING 2.1. Planning Irrigation systems 2.2. soil-plant-water relation – over view 2.3. Crop water requirement 2.4. Base, delta.
Chapter 37 Pipeline Construction. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Explain the.
Engineers Without Borders-USA Mid-Atlantic Professionals Chapter Water for Life Project Apatut, La Union, Philippines Amanda Jacobs Project Lead.
1 HVACR316 - Piping Copper Tubing and Fittings. 2 2 Safety Refrigerant cylinders should be stored and transported in the upright position to keep the.
Las Delicias, El Salvador Water Supply Project Implementation Proposal Phase I Trip Dates: May 2012 Presented to TAC: March 7, 2012.
Variable Speed Applied to Pumps. Life Cycle Costs - Courtesy of Hydraulic Institute and Europump Initial cost is not the only cost associated with a pump.
Existing System The system originally operated with everyone having 24-hour availability. The village then created a 3-day rotation which improved the.
Pressure and Flow Analysis Through EPANET Open source software package for hydraulic simulation of water distribution networks Used to determine impact.
WATER SYSTEM WORKSHOP February 27, 2012
DORSET Water System Information Meeting
City of Roundup, Montana
Detailed Design Review Solar Thermal Water Heater
Presentation transcript:

Las Delicias, El Salvador Water Supply Project Implementation Proposal Phase I Trip Dates: May 2012 Presented to TAC: March 6, 2012

Presentation Outline Overview of Las Delicias Community Current Water Supply System and Challenges Proposed Improvement to Water System – Summary of alternative analysis – Phase I (May 2012) New Water Tank at Intermediate Elevation New Supply pipeline and distribution pipeline – Phase II (Fall 2012) New pump (or VFD) Improvements to distribution system Control system improvements and pumping at night Logistics and Implementation

Las Delicias, El Salvador Las Delicias

Las Delicias, El Salvador Community Facts – ~600 homes, 2700 residents – 15 miles NW of San Salvador – On Western Slopes of Volcan San Salvador – Homes Spread Out, but Las Delicias is Bordered by Several Similar Communities – Water Storage & Piping System installed 20 years ago With Water Delivery by Truck – Well and Pump Installed < 5 years ago – Residents are Poor (<$10/week income) – Community Well-Organized through Adesco and NGOs (FIAT & FIMRC) – Able to spend about $5 per household on water each month Project History Project FIAT and FIMRC have been active in Las Delicias for > 5 years Initial Contact with Project FIAT (Dave H.) January 2009 Application to EWB-USA March 2009 Project Approved May 2009 Preliminary Assessment Visit July 2009 First Assessment Trip July 2010 Second Assessment Trip November 2011

Map of Las Delicias Water System DOWNHILL

Current Las Delicias Water Supply & Storage System Pump Runs 6 Hours a day 4 days/week ~ 26 hr/wk. Pump flow rate: GPM.

260 Homes Served by Tanque 3 33 Homes Served by Tanque Homes Served by Tanque 1 DOWNHILL Map of current Las Delicias Water System from ADESCO with approx house locations indicated

Summary of Existing Water System

Challenges to Las Delicias Water Supply System High electric cost – Typical ADESCO revenue from water fee ~$2300/mo – Typical monthly cost for water system ~$2000/mo (mostly electicity ~$1500/mo) – Pumps run about 26 hr/wk – Not taking advantage of nightime off-peak rates – Power factor on pumps leads to monthly fine of $50/month. Inequitable water distribution – Some homes report receiving water <1x/week and low flowrates – Valvulero controls distribution via valves to zones (Tramo) throughout community – Large number of new homes at low elevation Culture of scarcity where residents hoard water when it is flowing Water Quality: – Effectiveness of in-line chlorination is not clear

Electric Bill Monthly Income for Las Delicias ADESCO Water System Expenses

Alternatives Analysis Summary Drilling another well ($3500 for hydrogeological study) We spoke with a hydrologist in country and drilling a new well at higher elevation is considered to have low probability for success. Solar power for pump (eliminated due to high cost >$50K) Additional tank locations (three considered – current location on public land and co-located with current tank) Other locations require land purchase which could be costly and time consuming. VFD (variable frequency drive – possibility but must consider approx. 10% loss in pump efficiency at lower head) New pump for better efficiency at lower head.

Proposed Updates to Las Delicias Water System Objectives – Utilize existing and new tank at intermediate elevation to supply water to lower half of Las Delicias with lower pumping head required. – With new pump (or VFD on existing) and supply line reduced electricity costs due to lower head will result in more water for the community. – Improved distribution system more equitable water supply to all homes (especially at lower elevations) Phase I (May 2012) – New Water Tank at Intermediate Elevation – New Supply pipeline and distribution pipeline Phase II (Fall 2012) – New pump (or VFD added to existing) – Improvements to distribution piping system – Improving power factor for pump via capacitors to eliminate penalty. – Enabling pumping during nighttime to take advantage of lower rates by adding a timer circuit to the pump controller. (approx. 20% savings)

117 Homes Served by Tanque 3 33 Homes Served by Tanque Homes Served by Tanque 1 Proposed Water Distribution System 280 Homes Served by New Tank DOWNHILL

Modified water system

Summary of potential changes in water distribution system CURRENT SYSTEM Storage – Tanque 1: 35,000 gal – Tanque 2: 11,000 gal – Tanque 3: 25,000 gal Pump supplies water to Tanques 1 & 3 at 175 gpm, ~4 days per week Spring supplies water to Tanque 2 (and other tanques) Homes serviced by Tanques PROPOSED MODIFICATION Storage – Tanque 1: 35,000 gal – Tanque 2: 11,000 gal – Tanque 3: 25,000 gal – New Tank (combination): 28,600 gal Current 65 HP Pump supplies water to Tanques 1 & 3 at 175 gpm New 20 HP pump will supplywater to new tank at 175 gpm with much lower head and energy savings. Homes serviced by Tanques New: 280 New tank reduces demand of water from Tanques 1&2 (which require high head) by roughly 50%

Map of Current Water System (section relevant for EWB-MAP modifications) RED lines – supply lines to tank (uphill by pump) BLUE lines – distributions lines by gravity DOWNHILL Exisiting 11,000 gallon tank

Proposed update to Water System (section relevant for EWB-MAP modifications) RED lines – supply lines to tank (uphill by pump) BLUE lines – distributions lines by gravity NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2c NEW DISTRIBUTION LINE 2a NEW DISTRIBUTION LINE 2b NEW TANK A B C D E F DOWNHILL

New Tank Design – Location and Coupling with Old Tank

Design of New Tank – 3D view of Block/Rebar construction

Tank Design response to J. Knight concerns Concrete block vs poured concrete. Block recommended by local Structural Engineer (Daniel Rivera). Assumed strength of concrete ( psi acceptable – steel strength controls) Local Engineer accepted 3000 psi concrete although 2000 psi concrete will work as well. Tank seal at base of wall – We will look into this in further detail and will add it if necessary. We will contact seal manufacturer and seek advice of a water engineer before making a decision. Supply pipes will be connected to both tanks with shutoff valve to each.

Proposed update to Water System (section relevant for EWB-MAP modifications) RED lines – supply lines to tank (uphill by pump) BLUE lines – distributions lines by gravity NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2c NEW DISTRIBUTION LINE 2a NEW DISTRIBUTION LINE 2b NEW TANK A B C D E F DOWNHILL Design of Additional Pipelines for - supplying water to tank - distributing water

A B C 105 m 240 m D 638 m 640 m 643 m 651 m Elevation: 640 m 655 m Supply Pipe 1 Pipe Profile NEW TANK Tee connect to 6 pipe Gate Valve 45° Elbow 90° Elbow with anchor Gate Valve 90° Elbow Pipe Exit PIPE FITTINGS Tee with Manual Air release valve Tee with Manual drain valve Road Crossing

Estimate of head losses in supply pipe 1 (smooth PVC) 4 PVC sufficient to keep major and minor losses to <10% of the elevation change

Supply Pipe 1 Trenching Based on recommendations from EWB Water Resource Guidelines and advice from Tony Sauder: – 70 cm trench depth (45 cm depth acceptable except in road crossing) with pipe buried below 50 cm – 10 cm bedding (2-12 mm soil) if stones/rocks present in trench – Back-fill with soil that is free of lumps, from stones (>3 cm), and from organic matter – PVC pipe joined in trench and cure for >10 hr prior to pressurizing. Keep joints exposed to check for leaks. Expansion joints not necessary – For road crossing, may bury PVC pipe inside steel or concrete pipe (ID > diameter of PVC joints); final decision to be made in the field after evaluating potential for erosion 70 cm trench depth 10 cm bedding 10 cm 50 cm

Valve Boxes Design options – Obtain pre-cast valve boxes with lockable lids locally – Build from bricks and mortar with metal lids Specifications – 4 Pipe centered about 55 cm below ground level – Box should extend 10 cm above ground level – Internal dimensions roughly 45cmx45cm – Place support under valve Photos of current valve boxes installed in Las Delicias

Valve Box Design Drawing of valve boxes to be constructed at Las Delicias

Thrust Anchors for Elbows &Tees From Russ Turner, Tetratech

Summary of May 2012 Implementation Keys to Success: Success assured by working closely with: – Local community providing excavating equipment, funds, land and labor. – Local Rotary Club and Structural Engineer Daniel Rivera providing funds, logistics and expertise. – NGO – Project FIAT helping with funds, logistics and volunteers as well as arranging for a cement mixer. FIAT has vast experience doing these types of projects in El Salvador. – The Honorary Consul of El Salvador in Philadelphia is working with one of our members (Paolo) to help coordinate the project with the local Mayors office. She has also informed us that she will arrange to allow us to ship components (such as pumps) to the country tax and duty free. – NGO - FIMRC providing local health related services to the community and EWB by helping us define objectives and measure results.

Summary of Finances for Implementation Local community provides excavation equipment, land, material transportation and field labor (assume avg. 4 people, 8 hrs/day for duration of project) Chapter currently has about $28,500 available for this project including. – $15,000 Rotary Grant (must be used by September – specifically ear- marked for tank) – $8,000 from Project FIAT – $5,500 in chapter funds Costs are estimated at about $27,000 including: – Tank estimate - $12,500 – Piping estimate - $10,500 – Transportation estimate $4,000 – We plan to raise additional funds to cover gap costs between now and May. We will delay piping if funds prohibit completion until the Fall.

Logistics and Implementation Plan Engineer – Daniel Rivera of Local Rotary in San Salvador will coordinate with local government, obtain building permit, help organize material delivery and oversee installation through periodic visits. Project FIAT volunteers will coordinate with local community, organize material deliveries, hire an albañil, provide secure space for materials, provide cement mixer, supply working volunteers and provide lodging and transportation for EWB volunteers. Local community will provide land, excavating equipment and labor as well as help in transporting materials to site. EWB volunteers will provide supervision, project management and labor. EWB volunteers will cover entire 5 week installation.

Schedule for Implementation

Contingency Plans (worst case scenarios) for Implementation Project can proceed even if EWB members are not present every day. Control runoff and use tarps if heavy rains become problematic.

Material Procurement Project Fiat has executed many similar projects. They know exactly where the type of materials used on this project can be obtained locally. Project FIAT will provide a locked building close to the tank site where materials can be securely stored. All material will be sourced locally. All materials are common everyday building materials. Daniel Rivera has reviewed the material list and did not have any issues with our selections. (He did recommend using grade 40 rebar instead of 60 and we followed his recommendation) The area near the village includes heavy industry and business enterprise and the community is only 15 miles from a major city. We foresee no major issues sourcing materials.

Plans for Phase II Implementation (Fall 2012) Install new pump (or VFD) Install Power Factor Correction Capacitors Install Timer Circuit to allow Night time Operation Install additional distribution pipes.

Metrics Increase water supply by ~40% without increasing operating cost Increase in % of homes receiving sufficient water (at least 2x per week)

Concluding Remarks Project is sustainable through community involvement and use of: – Locally available materials – Standard construction techniques typical to the area. – Adding to existing water system infrastructure using identical technologies. O&M will be the same as they are doing now. – The community already has people in place to operate and maintain the water system. Community will benefit through better distribution and more abundant supply with no increase in operating cost.