PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Advertisements

Thursday 21/4 07:30: End of fill #1727. Beam dumped. ALICE compensator magnet fault. Delivered ~6.7 pb -1 in 7.5 h. 11:30 Stable beam # bunches/beam.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
07:30 – 10:30 Asynchronous dump test with Beam 2. No issue found. FIDEL update. Now chromaticity decay corrected. 12:13 Beam dump due to problem in the.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Last 24 hours RQ4.L1 Lost going into collision Test ramp Storm
Machine Coordinators: G. Arduini, J. Wenninger
Luminosity lifetime – fill 2932
Wed :55 Fill 2653 stable beams 1.40e11 ppb, cm-2s-1peak lumi, 11.6 pb-1 total lumi delivered. 09:31 Dumped by collimator interlock:
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
MD25 ns - 14/12/2012 G. Arduini, H. Bartosik, G. Iadarola, G. Rumolo
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Coordination: G. Arduini, E.B. Holzer
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
LHC Morning Meeting - G. Arduini
Monday 6th August & night
Summary of week 22 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Summary of Week 16 G. Arduini, J. Wenninger
Note: squeeze in Atlas, CMS, LHCb and Alice on going
LHC Morning Meeting - G. Arduini
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Mike Lamont, Jorg Wenninger
Wednesday 8th August & night
LHC Morning Meeting - G. Arduini
Sunday morning Recovering from 400 kV disturbance.
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Friday morning 10:30 Optics measurements and corrections.
Saturday – Morning 7:36 beams dumped
LHC Morning Meeting - G. Arduini
Friday Morning 7:30 injection for fill 2908
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Tuesday morning 09:30 Beam dump, SIS dump due to lost connections with FCG FECs. Coincides with starting a development SIS server to test new interlocks.
Wednesday 10/5 Cryo recovery until 18:30
Tuesday Access for RF & QPS (others in the shadow) until ~18:00.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Monday – Morning Fill 3265 stable beams since 1:31
LHC Morning Meeting - G. Arduini
Monday 14:00 beam dump Access:
LHC Morning Meeting - G. Arduini
Saturday 3rd November - morning
Tue/Wed 12/ :00 Probe beam back again
LHC Morning Meeting - G. Arduini
Thursday 26th July 13:21 Fill 2880 beam dumped
Thursday – Morning Energy matching at injection with H CODs
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Monday 11th June 08:10 Beam dumped in the ramp by OP. OFB did not start its function and kept the injection orbit. 08:50 Switch LHCb polarity to negative.
Friday morning 08:00 Stable beams with 840b.
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
Thursday
Saturday 24 September 2011.
Coordination: Eva Barbara Holzer, Mike Lamont
Wednesday h18: 228b fill lost just before start of ramp.
LHC Morning Meeting - G. Arduini
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Another Immortal Fill….
Wednesday morning / afternoon
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Tuesday
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Presentation transcript:

Chromaticity can make a difference… 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Sat 4/8 After the losses observed during the ramp increased chromaticity by 5 units in the second half of the ramp and throughout the rest of the cycle as proposed by Elias and Alexey in case of instabilities until we do not manage to reduce significantly the transverse damper gain In the mean time PSB working on beam quality: improvement of the transverse emittance by 10 % measured at PSB output 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini 12:43 Injectors ready  decided to dump and refill with fresh beams and new settings in the LHC. End of fill #2911 (61 pb-1 in 4.8 h). Filling slowed down by frequent losses at injection in the SPS (under investigation) 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Beam quality B2H B2V On average some improvement although with some differences inside the trains. No difference between PS trains (still running with dummy LHC cycle in PSB PS) 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Very clean ramp and squeeze. Lifetime dip when going in collision 15:28 STABLE BEAMS #2912. Initial luminosity 6.4x1033 cm-2 s-1 Ramp Squeeze Adjust 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini LHCb exceeding 4x1032 cm-2s-1 when optimizing in the crossing plane. Incorporated additional separation in the levelling plane to avoid that next time 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Delivered 10 fb-1 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini 23:12 FMCM trigger (RD1 in 5). Electrical perturbation because of the thunderstorms 23:44 trip of RQF.A45 during pre-cycle (QPS) followed by trips in 5 other sectors. 120 pb-1 in 7.6 hours 01:34 ready for powering after intervention of the power piquet (remote resets) In the mean time the SPS is also down because of the thunderstorms 03:47 SPS ready – filling. Emittances as in previous filling Good ramp and squeeze (we had reduced gain of the damper) 05:17 cold compressor lost. Before ramping down go through the adjust process  Beam dump due to BLM in point 7 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Fast beam instability B2H on some of the bunches in the first step of the reduction of the separation in point 1 and 5. Signature of loss of Landau damping due to relative sign of octupoles 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Plans Recovery expected by the end of the afternoon Fill for physics 01/01/2019 LHC Morning Meeting - G. Arduini

LHC Morning Meeting - G. Arduini Pending Change CTRV cards on TSU FECs for LBDS  N. Magnin (2 h) Moving of the spare MKD generator from gallery to the surface 01/01/2019 LHC Morning Meeting - G. Arduini