Coffee & Construction Developer Meeting Details on Segment 1, 29th -40th Construction Tuesday, September 27th, 2016
Brighton Corridor Packages Map
During Construction… Approximately 18 months of construction Start in October Access to businesses will be maintained One lane of traffic in each direction during construction Pedestrians and bicyclists will be accommodated at all times Limited closures of some intersections 3 construction phases
Brighton Boulevard, Segment 1, 29th to 40th Street
Construction Phase 1 Construction Area Phase 1 – Build temporary paving: Motorists, Bicyclists and pedestrians will be one lane in each direction on the west side
Construction Phase 1 – Cont’d.
Construction Phase 2 Construction Area Phase 2 – Build new sidewalk, bike path, curb/gutter, planters, roadway, etc.: Motorists, bicyclists and pedestrians on east side; One lane in each direction
Construction Phase 2 – Cont’d.
Construction Phase 3 Construction Area Phase 3 – Build new sidewalk, bike path, curb/gutter, planters, roadway, etc.: Motorists, bicyclists and pedestrians on west side; One lane in each direction
Construction Phase 3 – Cont’d.
Summary Construction Phase 1 Construction Phase 2 Construction Phase 3 Begin fall 2016 (2 month duration) Construction Phase 2 Begin winter 2016 (6 month duration) Construction Phase 3 Begin spring 2017 (6 month duration) Landscaping Begin spring 2018 (2 month duration)
Status of Other IC Contracts Globeville Landing Outfall Phase 1A Brighton Phase 2 and GLO Phase 2 Festival and 33rd streets Globeville Landing Outfall Phase 3
Please Join Us… Brighton Corridor Redevelopment Project Ground-Breaking Event Thursday, October 13, 2016 Great Divide Brewery: 1812 35th St., Denver, CO 80216 11 a.m. – 1 p.m.
How to Get Information Continue attending Coffee & Construction Meetings Be on the look-out for weekly construction updates via the following outlets: Construction update emails Social Media – text Construction information hotline 303 265-0211 Email brightonconstruction@Kiewit.com NDCC Website