Yesterday Power back around lunchtime Access until 12:30

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Ion Commissioning: Thursday & Friday
DRY RUNS 2015 Status and program of the Dry Runs in 2015
LHC Status Tue Morning 22-Aug
Wednesday 8.9 External crossing angles:
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Day :00-11:30: Optics at 3.5 TeV Optics re-measured with AC-dipole. Excellent reproducibility. Small emittance increase from AC-dipole. Collapsed.
Wednesday September 14th
Summary of week 7 Hardware Commissioning:
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
A/N 26 16:00 Access finished problem with the BLM test. one crate is failing the beam permit test. Fixed. Access required in sector 78 for QPS to fix a.
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Tue :25 Beams dumped due to RF vacuum interlock
Thursday morning – optics correction
Barbara Holzer, Jorg Wenninger
LHC Morning Meeting - G. Arduini
Yesterday Issue of injection kicker not pulsing:
Wednesday 31 October: Morning
Bernhard Holzer, Joerg Wenninger
Scrubbing progress - 09/12/2012
Friday 31st August & night
Week 36 plan Todo’s: And also: 12+b injection.
LHC Status Sun Morning 20-Mai
Friday March 4th 08h32: Access for beam dump system.
Week 35 – Technical Stop and Restart
Planning at 5 o’clock meeting Friday
Thursday :00: Physics fill from the night shift
LHC Morning Meeting - G. Arduini
Monday 08:30 – 11:00 Access for: LBDS beam 2 problems: TSU unit changed RQTD.A67B1: controller for the current lead heater changed RQS.A67B1 power converter.
Friday Morning 7:30 injection for fill 2908
Wednesday 09 March …:09:00: beta* measurement (1.5 m) by K-modulation and with AC-dipole excitation. 1/17/2019 LHC 8:30 meeting.
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Planning for the week MO M P
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday Physics fill 1250 (with 13b) dumped at 10.30
Monday 14:00 beam dump Access:
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Monday 3rd September - morning
Tuesday morning 08:30-09:00 Squeeze with probe.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Can operation put the MPS in a unsafe state?
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Thursday – Morning Energy matching at injection with H CODs
Cold compressor speed S45
Friday morning 08:00 Stable beams with 840b.
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Tuesday In the morning test cycle with probe for Q’ measurement.
Wednesday 23/2 Thanks CRYO!!!.
LHC Status Fro Morning 9-Sep
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Saturday 24 September 2011.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
RAMP FOR COLLIMATOR SETUP
Another Immortal Fill….
Monday 10th December - morning
15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.
Saturday 10:00: Cryo Pt8 back, starting the pre-cycle.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Saturday Morning used to complete the loss maps and asynch dumps (with RPs). All loss maps OK (B. Salvachua), but the off-p cleaning for B1 (Lead) was.
Monday 5 July Morning: Continued with the Physics fill, 7b x 7b, 1e11/bunch Stable beams from 2:30 am to 13:30 : 11 hours.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Yesterday Power back around lunchtime Access until 12:30 Totem winkled out last QPS tests on sector 12 Pre-cycling interruptus by re-energization of SVCs around the ring Access (6 & 4) again for beam dump in the shadow 20:15 Pre-cycle again 22:15 Beam circulating again 02-12-09 LHC status

Overnight Aperture checks in IR8 Loss cyro instrumentation ROFA45.B2 temperature monitoring – masked, to be superlocked force cryo start cryo maintain Beating team started, finished at 8:15 Collimators in coarse, BLMs in 3 & 7 unmasked Number of problems with LBDS sync problem with BETS XPOC failure IPOC – retriggering LBDS be woken up all night similar problems this morning 02-12-09 LHC status

aperture IR8 02-12-09 LHC status

Example 02-12-09 LHC status

Beating Beta-beating experiment finished for now... 1. Beam 1 has a positive effect from the corrections applied. 2. Need to understand IR7 results more carefully for Beam 2. All trims and tunes reset to initial settings. Off line analysis to follow Capture not used 02-12-09 LHC status