Investigation of pipeline failure

Slides:



Advertisements
Similar presentations
Surge Pressure Computations
Advertisements

Mitigation of AC Induced Voltage On Buried Metallic Pipelines
AUTOMOTIVE COOLING SYSTEMS
Fluid Mechanics.
Study on Wave calculation of an air cushion surge chamber
Manual Set-Up for Density by Hydrometer Method ASTM D1298, D287, D6822 and IP160 Feb
Test to Failure of 3/8-Inch Tube Ferrule Connections in an Effort to Determine the Shear Strength of a Varying Number of Threads Engaged P.O. Box
Investigation of Consolidation Promoting Effect by Field and Model Test for Vacuum Consolidation Method Nagasaki University H.Mihara Y.Tanabasi Y.Jiang.
GROUNDWATER CONTROL.
Lesson 25 TWO-PHASE FLUID FLOW
Student Book © 2004 Propane Education & Research CouncilPage Performing Pressure Tests on Gas Distribution Lines Gas personnel must understand.
CVFD Training – Water Supply SFFMA Training Objectives: –
Lab IV: Internal Combustion Engine 14:650:431:03 Max Tenorio.
TransCanada Corporation (TSX/NYSE: TRP)
Gas Transmission Pipelines
Pipe Supports and Restraints
Unit 205: Cold water systems
Monroe L. Weber-Shirk S chool of Civil and Environmental Engineering AguaRed.
1402 Hybrid Firefighter I 6 th Edition Chapter 14 Water Supply.
WILLBROS A Good Job On Time Hydrostatic Testing Practices Establishing Verifiable, Traceable, and Accurate Documentation August 20, 2013 Hal Ozanne Willbros.
Intermediate SFFMA Objectives: – Hrs received.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2012 Updated: 2/12/2012.
2013 Section Engineer’s Meeting.  Correct Type, Gauge, and Coating (Standard Drawings)  Based on Pipe Diameter, Fill Height & Soil pH  Obtain copy.
Fuel Oil Systems Fuel Oil Systems consist of: Storage Tanks Pumps
Hydronic Mechanical Controls
Mechanical for Oil Heat
Hydraulics For The Long Term
Learning Objective 1 Explain the ways water supply system components are used by firefighters.
Las Delicias Water Project: Piping System Design EWB-MAP Compiled by: Richard Cairncross Date 1/12/2011.
You Should Know Bulletin No. 135 © ACPA All Rights Reserved.
TECHNICAL ASSOCIATION OF THE EUROPEAN NATURAL GAS INDUSTRY Development of a Eurogas-Marcogaz Methodology for Estimation of Methane Emissions Angelo Riva.
Hydraulic Engineering
Other Construction Projects
Unit 2 Terms & Definitions.  Legal requirements designed to protect the public by providing guidelines for structural, electrical, plumbing, and mechanical.
Safety in the numbers Working Safely Around Pipelines Dig Safe BC! Workshop: March 2010.
Chapter 37 Pipeline Construction. Objectives After reading the chapter and reviewing the materials presented the students will be able to: Explain the.
DEVELOPING FIRE TESTS FOR FCV AND HYDROGEN VEHICLES Glenn Scheffler Consultant for the US Department of Energy August 2010 DEVELOPING FIRE TESTS FOR FCV.
TRENTON Casing Filler Presentation
Vacuum Fundamentals High-Vacuum Technology Course Week 7 Paul Nash HE Subject Leader (Engineering)
Firefighter III Module B Water Supply (4-19) (4-19)
Experimental and numerical studies on the bonfire test of high- pressure hydrogen storage vessels Prof. Jinyang Zheng Institute of Process Equipment, Zhejiang.
Manual Density Business Today
1 ME444 ENGINEERING PIPING SYSTEM DESIGN CHAPTER 6 : PUMPS.
Sanitary Engineering Lecture 13
PILOT PROJECT ON NRW IN SHEETAL PARK AREA OF RAJKOT CITY IN GUJARAT Danish Water Forum AND Rajkot Municipal Corporation.
Fluid Mechanics for Chemical Engineers Arif Hussain (Lecturer)
VALVES IN PIPE LINES.
Irrigation Pumping Plants
Plumbing system fundamental and design course
AUTOMOTIVE COOLING SYSTEMS
Fluid Statics/Dynamics
CTC 450 Review WW Characteristics.
EXERCISES Two water reservoirs are connected by a pipe 610m of 0.3m diameter, f’=0.038 and the flow produced by the difference in water surface elevations.
Introduction: Excavations and other engineering constructions in the ground are central to many civil and mining projects. Ground reinforcement includes.
Aquifer Test Analysis Carter Lake, Iowa
14 Refrigerant Recovery, Recycling, and Recharging.
TRENCHLESS TECHNOLOGY
Leakage control in transmission pipelines
Parul Institute of Technology
Coursework guidelines
Private Septic Systems
Taum Sauk Dam Failure Missouri, 2005
Private Septic Systems
Excavation.
Flexible pavement design
TRENTON Casing Filler Presentation
Investigation of vibrations at two Pilbara mines
GENERALPIPINGREQUIREMENTS:. Designing and erecting an efficient piping system requires certain aspects/ requirements which could be found in our PME handbook…
An Investigation into the Failure of Belly Dump Trailers
Gas Transmission Pipelines
Presentation transcript:

Investigation of pipeline failure Mr Peter Airey BE GradDipAdmin FIEAust CPEng RPEQ Managing Director - Airey Taylor Consulting Engineers & Scientists Chairman – Advanced Substructures Ltd

Burst HDPE pipeline 25 km long, large (650 to 800mm) diameter buried High Density Polyethylene (HDPE) irrigation pipeline, installed parallel to Gasgoyne River in Western Australia The pipeline is a transmission main for collecting and conveying groundwater from a bore field to irrigation properties adjacent to the Gascoyne River During final filling operations on December 19 2016, 800mm diameter section failed (burst)

Pipeline profile Designed for direct delivery of variable flow rates. The estimated maximum pressure at the lower (west) end was forecast to be 40 m. The test pressure was specified to be 60 m (600 kPa). Sited in generally well drained sand (with about 15 % fines). Bedding and backfill was compacted excavated material. Minimum cover for the 800mm nominal diameter piping was specified to be 850 mm.

Pipeline failure A length of 800mm nominal diameter PN6.3 pipe (inside diameter approx. 736 mm) yielded along the crown of the pipe and subsequently fractured during final flling operations. The failure was near the lowest point of the pipeline (invert approx. 16.5 m AHD).

Soils investigation Backfilling and compaction procedures were initially thought to be responsible. Detailed investigation of soil types and compaction techniques was conducted. It was concluded that “the rupture of the pipe was not related to the level of compaction in the trench.” Consequently a separate investigation was conducted after the failed pipe length had been transported to Perth. Following removal of the pipe and being transported to Perth, the failed section of pipeline is seen on the left.

Yield characteristics of HDPE Inspection of failed pipe indicated pipe wall had yielded from average thickness of 31.8 mm to 5.2 mm – equivalent of 612% Published test data indicates elongation prior to rupture usually 636% Ground temperature estimate was 30 – 35°C, reducing capacity by 10% (from 630kPa to approximate 580 kPa) Based on inspection and measurement, clear that pipeline had failed due to excessive internal pressure

Filling process Pipeline volume 9.6 million litres; av. pumping rate of 25L/s; needs 106 hours to fill - was filled + checked over 10 day period, contractor : “a number of leaks identified and rectified” Filled at bore pump near upper end (east) of the pipeline. Temp. connection between pump and pipeline had pressure gauge, visual flow meter + throttling valve – no means of limiting pressure or recording

Throttled head at burst location Curve A = Head capacity of the bore pump – as rated by manufacturer adjusted for bore drawdown and actual static lift Curve B = available head that could be transferred after passing through throttling valve. On day of filling, pressure adjusted to initially limit inflow to 22 L/s. Applicable pressure gradually applied as pipeline pressurised. No record of pipeline pressure at time of failure exists.

Air Valves + Test Pressure 37 air valves successfully vented trapped air during filling – no air was observed venting on 19 December 2016. Review of ASCON drawings confirmed no location where measurable amount of air could be trapped. Appropriate test pressure for HDPE (rated PN 6.3 or 630kPa) = 60m. Nominal rating includes a 2 to 1 safety factor based on ambient temperature of 20° – this safety factor judicious

Pressure Relief Valve (PRV) PRV on completed pipeline on branch at chainage 1424, near lower (east) end of conduit – it was necessary to isolate PRV prior to pressure test Following failure, PRV suggested to be adjusted to 450kPa under normal conditions In addition to PRV, pipeline has 9 scour valves at low points – these were used to discharge dirty water during initial fill but were closed on 19 December 2016

Conclusions All evidence suggests that the pipe was subject to a pressure higher than 500 kPa. Failure occurred near the lowest point in pipeline under very low flow (almost static) conditions. Filling and pressurisation had located the most vulnerable situation. It was suggested that the damaged section of pipe be replaced and that the pipeline be refilled and pressure tested at 450 kPa (at the lowest point of the conduit)

Conclusions All air had been effectively displaced from the conduit and did not contribute to the failure. HDPE material has similar yield characteristics to steel and actual fracture is preceded by gradual elongation. Failure was not instantaneous but occurred over a time span of about 5 seconds, as the volume of the pipe increased due to increasing pressure.

Conclusions The assumption of flexibility does not apply to large diameter HDPE pipe lines Piping with SDR ratings greater than about SDR 15 are rigid - miscellaneous stresses can be locked into installed pipelines. For relatively thin wall pipes - curved alignments, bedding variations and other factors lock in non pressure induced stresses. South Australia Water Corporation, for instance, requires that PN 12.5 = SDR 13.6. For large diameter HDPE pipelines, applicable in situ test pressure should include a safety factor of at least 2