FMS Repair Work: Summary

Slides:



Advertisements
Similar presentations
n-DVCS/E status report
Advertisements

Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Polarized 3 He Target System Overview Design Vertical Polarization Spin-Flip Oven/Ladder/Enclosure/Access Laser/Optics/Cells Polarimetry Safety/Documents.
Update on FMS Repair Stephen Trentalange STAR Management Meeting October 31,
Muon Campus Controls Update Brian Drendel 8/6/13.
Preparation of SPD Cabling Calo comissioning meeting – 19th July 2006 – CERN I.Status of cables II.Cable reels III.Labelling IV.Cabling inside a VFE box.
Endcap Integration Workshop: June 11-14, CSC Commissioning Andrey Korytov.
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
Summary of FMS/Jet Meetings July FMS Meeting: 7/21/14 Discussion of progress refurbishing the FMS – First delivery of ~40-50 finished bases from.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
1 Booster Corrector BPM Status AD/ Instrumentation Jim Fitzgerald.
DVCS-2 Assembly & Installation Charles Hyde DVCS Collaboration Meeting 18 December 2009 Clermont-Ferrand.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
DOE Rev of Run IIb Sep 24-26, Detector Production WBS James Fast Fermilab.
PMG, Aug 03, 2000 Slide 1 Schedule In preparation Done Started Done Started Half done.
MuTr Shutdown Work Rusty Towell for And JUNE 22, 2004 at the Muon Physics and Forward Upgrades Workshop.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Ronald Lipton Layer 0 Status PMG Sep Status of the Layer 0 Project – emphasis on hardware status, preproduction, and preparations for shutdown work.
1 HBD update Itzhak Tserruya DC Upgrades meeting, January 14, 2005 NIM paper II: Generic R&D ~ completed Full scale prototype construction Pending issues.
Refurbished Booster RF John Reid October 24, 2012.
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
LAV construction status – M. Moulson (Frascati) – Photon Veto WG – CERN – 12 Jul 2011 LAV construction status: a snapshot 2 A1 Arrived at CERN 29 Jun.
Update on FMS Repair STAR Management Meeting: Oct Stephen Trentalange.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
1 PHENIX WEEKLY PLANNING January 21, 2016 Carter Biggs.
CLAS12 Drift Chamber Prototyping
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
Activities of 2008) Jinsook Kim, Yongwook Baek 1.
Preparations for Run 6 Don Lynch February 13, 2006.
DON LYNCH OCTOBER 28, October 28, 2014 sPHENIX Detector Integration & Assembly Concept.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
SPHENIX MECHANICAL D. Lynch, R. Ruggiero June 12, /12/2014sPHENIX Mechanical Design.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
CDMS II Shielding To Installation To Construction From Design.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Next chance for Service test. In the next B2GM Use of old VXD KEK The screw connection may not work. -> double scotch tape for PXD PP mock 1/4.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
Bill Christie For the STAR Collaboration June 15,
Operations meeting on FY07 Shutdown Date: June 27, W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.
ELENA installation progress F. Butin / ELENA collaboration.
2007 Physics Run Status STAR Collaboration mtg June 12, 2007, Berkeley California Bill Christie Outline Overview of BUR/Goals for Fy07 Run Collider Performance.
מהפכות באנגליה.
Assembly of steering.
SPF MAG Quarterly Report – Feb 2015
FMS Update Refurbishment for Run15
The SABRE Crystals Frank Calaprice.
MICE Project in the US: Completion of Efforts
TripleSpec 4 Status and Coming Steps
Renovation of the 45-year old PS magnets
Technical Support Activities in PH-ADO-PO
Stephen Trentalange STAR Upgrade Workshop June 11, 2012
Installation plans from mid 2005
FMS Readiness for Run 11 Stephen Trentalange.
FMS Repair Work: Summary
Status of FMS Refurbishment
JUNE 2010 CALENDAR PROJECT PLANNING 1 Month MONDAY TUESDAY WEDNESDAY
3 Week A: May 1 – 19 3 Week B: May 22 – June 9
Polarized 3He target installation
Presentation transcript:

FMS Repair Work: Summary Extra Month for repair work compared to original plan Jan 15- June 15 -> Jan 15-July 15 (6 months) Must install scaffolding on mezzanine (1 month delay?) Stacking to begin in August: Restacking Plan Written Finish at end of October Mismatch of manpower with stacking Originally plan to stack in June PSU students gone by early August Student labor available for preparation work Tasks at BNL/PSU well in hand and on schedule Starting to get problems/rework necessary.

Jul Completed

Recovery of expansion rings, signal and HV cables, inner and outer magnetic shields PSU: Alteration of FNAL Bases Annealing lead glass, cleaning and wrapping of lead glass in 0.001”mylar Casting plastic fixtures for gluing magnetic shields to lead glass

Personnel working at BNL Main Tasks to Finish: Gluing/Wrapping Large Cells 300 left 15/day = 1 month. PMT Bases work at PSU ~50% completed. Can be mounted after stacking. Order for 700 optical pads: 10 delivered; next week-100 units/week. Stacking plan written and submitted to Bill Christie: Main points are front platform and delivery thru RHIC tunnel/Door 6ED1. Some reworking: ~10% large cells reglued/recast plastics holders for magnetic shields Tolerances on PMT bases-do not fit inside shields Personnel working at BNL David Hamilton Joseph Newton Dmtry Kalinkin Stephen Trentalange Mriganka Mondal Personnel working at PSU Tyler Boone Dan Marshall Sam Heppelmann Steve Hepplemann Yaokun Sity Branden Summa Christopher Dilks