VELO-meeting January 25, 2007 Sub-projects: SX & SX

Slides:



Advertisements
Similar presentations
VELO Module PRR preparation meeting28-feb-2006 LiverpoolMassimiliano Ferro-Luzzi 1 Introduction VELO overview Overall planning A bit of (recent) history.
Advertisements

Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
14 June 2007VELOEddy Jans 0 Recent VELO-installation++ activities June 14, 2007 Potmeter calibration Bake-out Cabling & Commissioning.
7 September 2006VELOEddy Jans 0 VELO-installation September 7, 2006 installation of exit window + part I of the beam pipe logging of vacuum data what’s.
VELO RF box status at Nikhef Report at the Meeting for new VELO RF foil development Tjeerd Ketel, Erno Roeland a.o., Nikhef Tjeerd Ketel, Nikhef.
14 February 2008VELO NikhefEddy Jans 0 Cooling and warm-up of the VELO under neon atmosphere conditions results (Jan 28  30) implications.
Walls crates cables gas chambers electronics CERN adb.
EA meeting, Wednesday 6 Dec 2006 TT installation, Jeroen van Tilburg 1 TT installation Installation of the TT station.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
Warm magnets and the remote handling system in the J-PARCν beam line E. Hirose, K. H. Tanaka, Beam Channel Group.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
Dec. 4, 2001 CERN-1 Hans de Vries VELO Mechanics  RF/vacuum foil  Rectangular bellow  Wake field suppressors  Cabling Summary & Outlook VELO mechanical.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
Electrical and Optical Cables Installation at P5 What When How H. Breuker
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT) Gennaro Ruggiero (PH/TOT) LHCC minireview – 06 May 2009.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
D. Gasser ST/CV 1 Fluid distribution from UW85 Fully available now.
1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.
LumiCal mechanical & sensors design Wojciech Wierba J.Błocki, E.Kielar, J.Kotuła, K.Oliwa, L.Zawiejski FCAL Workshop, IFJ PAN Cracow,
Power Up of the First VELO Module at IP8 Eddy & Olaf on behalf of the VELO group.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Integration with LDC & Push-pull impact on LumiCal Wojciech Wierba Institute of Nuclear Physics PAN Cracow, Poland FCAL Workshop, LAL Orsay,
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Expt. Area meeting – December V. Bobillier1 Cabling installation status.
Vrije Universiteit amsterdam Milan, September 25, 2000 VELO System J.F.J. van den Brand LHCb Vertex Detector System: Status Report J.F.J. van den Brand.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
25 January 2007VELO sub-projectsEddy Jans 0 VELO-meeting January 25, 2007 Sub-projects: SX & SX connectorize cooling cables alignment procedure.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Dec
6 September 2007VELOEddy Jans 0 VELO-installation++ activities September 6, 2007 General items Detector installation plans.
Lab Activities: Chamber Baking & Mixing Station Flushing Claudio Curtis Dan PPS meeting 22 June, 2011.
VELO Integr - Jan06Jean-Christophe GAYDE TS/SU EDMS n° SURVEY FOR VELO INSTALLATION 1.SURVEY AT GROUND FLOOR - FIDUCIALISATION 2.SURVEY FOR INSTALLATION.
1/20 LHCb upgrade, Jeroen van Tilburg Nikhef Jamboree, 14 Dec 2015 Preparing for the LHCb upgrade.
DCal-ALICE integration and installation plan and status A. Tauro.
Upgrade activities DT-LHCb coordination meeting 14 March 2016.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
VELO Replacement Girish Patel University of Liverpool.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
Laser Control Status A. Masi, T. Feniet, K. Szczurek Awake Technical Board November 12 th 2015 Thanks for inputs from: M. Donze`, V. Fedosseev, C. Hessler.
ELENA installation progress F. Butin / ELENA collaboration.
BM&N STS ladders assembly in VLHEP
PIXEL CAEN Installation Status
DT-LHCb coordination meeting 18 April 2016
Status of the ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS AFP group 25FEB2016.
Cabling for LHCb Upgrade
VELO-installation meeting CERN, January 17, 2006
Introduction Status before the 2009 run Results from the 2009 run
Totem Gas Systems ( T1 , T2 ) S. Haider PH / DT1.
Gas System Commissioning
VELO Thermal Control System
RICH Status from last RICH meeting
LHC Experimental Vacuum Systems Status October ‘07
LumiCal mechanical design, integration with LDC and laser alignment
(Business Professional)
LHCb & EYETS
Initial BIS installation
LHCb comprehensive review, Paula Collins
RPC HV&LV status Introduction HV power supply tender
Cryomodule Assembly Plan
Polarized 3He target installation
CSC Electronics Installation and Commissioning CSCE I&C
Presentation transcript:

VELO-meeting January 25, 2007 Sub-projects: SX8-2.003 & SX8-2.004 connectorize cooling cables alignment procedure motion test bake out procedure turn over project DP-project VELO vacuum commissioning LHCb installation planning summary + timelines 25 January 2007 VELO sub-projects

clean up SX8-2.003&4 Spaces 2.003 and 2.004 are future storage, repair and working places for the whole VELO + PU communities. With other people and parts/equipment approaching soon, our stuff needs to be reorganized/cleaned up. Estimated time: 0.5 manweek. 25 January 2007 VELO sub-projects

Cabling 22 Jan  16 Feb: - pull long-distance (RB84  D3) analog cables by INEO - “simultaneously” connectorize D3-side 19 Feb  23 Feb: - pull control cables (RB84  balcony) 26 Feb  2 Mar: - pull HV cables (RB84  D3) Cooling cables still need to be connectorized at both ends, i.e. RB84 and C3. Estimated time: 2*1 manweek. 25 January 2007 VELO sub-projects

Alignment Alignment procedure uses 5 fiducial Centre Frame Fiducial Marks Alignment procedure uses 5 fiducial points on each side of center frame. However, these are soon not visible anymore due to the repeater crates, mounted on the detector hood. 25 January 2007 VELO sub-projects

Install new alignment points above and below the existing ones. Solution: Install new alignment points above and below the existing ones. Watch out that the analog cable supporting frame is not in the way also. Estimated time: design: 1.5 mw construction: 1.5 mw implementation: 2*0.5 mw 25 January 2007 VELO sub-projects

Motion Estimated time: thinking: 2 mw implementation: 2 mw Increasing expertise with the system has revealed the necessity to take a few additional safety measures. Partly to be implemented in the PLC, partly in the PVSS application. moving both XL and XR in the same direction from a position in which XL=-XR, needs special precautions. implement the possibility to stop the stepper motor when really necessary (moving wrong way based on pot. meters, one side not moving at all, etc.) Estimated time: thinking: 2 mw implementation: 2 mw testing: 2*1 mw 25 January 2007 VELO sub-projects

Test bake-out procedure Bake-out procedure of rf-boxes has to be commissioned: regulation of lamps, temperature interlock, etc. Estimated time: preparation: 1 mw implementation: 2*1 mw 25 January 2007 VELO sub-projects

Turn over project Rotation of the detector half is a delicate, not yet well-established activity. Likely solution: Use 2 small cranes. Either powered by hand or electricity. Estimated time: preparation: 0.5 mw production of test tool: 0.5 mw ? testing: 2*0.2 mw 25 January 2007 VELO sub-projects

DP project (elastic) deflection: 0.3 mm @ 4 mbar 0.4 mm @ 5 mbar Dx Dp [mbar] (elastic) deflection: 0.3 mm @ 4 mbar 0.4 mm @ 5 mbar 25 January 2007 VELO sub-projects

Dp=pbeam-pdet [mbar] evacuation foil hits sensors side 25 January 2007 VELO sub-projects

Dp=pbeam-pdet [mbar] venting foil hits sensors side 25 January 2007 VELO sub-projects

change Dp-range and/or central Dp-value. Estimated time: Possible remedy: change Dp-range and/or central Dp-value. Estimated time: preparation: 2*1 mw testing: 2*0.5 mw 25 January 2007 VELO sub-projects

VELO vacuum commissioning Unacceptable leak rate (10-5 mbar.l/s) of rf-boxes necessitates additional tests + attempts to (temporary) fix the problem. Present plan with VELO + part I of the beam pipe: evacuate bake rf-boxes @ 160 oC vent ?? evacuate ?? determine leak rate vent seal “holes” with Varnish Estimated time of NIKHEF-involvement: 2*2 mw 25 January 2007 VELO sub-projects

LHCb installation schedule Coming months lots of activities from RICH1, TT, VELO (HV, LV, ECS, etc.) in the vicinity of the VELO. Need for coordination, flexibility and mutual cooperation. Jan 22  Mar 2: Cabling (analog + control) around the VELO. March + April: installation LV-distribution boxes, HV-patch panels April 5: Start bake out + commissioning of the complete LHCb beam pipe. 25 January 2007 VELO sub-projects

Summary what where time [mw] start at the latest on ready before who 2.003&4 cleanup IP8 0.5 1 Mar 15 Mar FM/MD/MK cooling cables connectorize 2*1 1 Apr JS+?? alignment design NL 1.5 1 Feb 15 Feb JvdB+FM production 20 Feb 5 Mar VU align 2*0.5 23 Mar motion 2 15 Apr 1 May PdG+MvB coding 15 May 1 June testing 15 Jun 1 July bake out 1 10 Mar PdG+?? turn over prep MK/MD prod. of test tool NIKHEF/CERN? ?? 2*0.2 MK+MD+RD Dp MD+LJ vacuum comm. leak rate++ 2*2 1 April LJ/MD/BM/FM 25 January 2007 VELO sub-projects