Tuesday 22 November 2011.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

PROFIBUS controller problem (SEU) on cryo valve on DFBMH (600 A circuit RQ6.L7B1/2). Loss of cryo maintain ==> Beam dump. End of fill #1975 after ~2.5.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
LHC 8:30 meetingEBH 11 Thursday 24 November 2011.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Machine Coordinators: G. Arduini, J. Wenninger
Summary Week 47 + Start Week 48
Thursday 25/11/10 & Night Work on: 16:15 Inject fill #1520
Monday fill with 1092 bunches (6 h stable beams)
Thursday 09:30 VdM scan for CMS, standard ADT gain.
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
Summary of ion week 48 Last beam OP summary of 2010 Week 48
LHC Morning Meeting - G. Arduini
Overview LHC Operation Week 47
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Tuesday 22nd January - morning
LHC Morning Meeting - G. Arduini
Monday 6th August & night
Summary of Week 11: 14 – 21 March
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Tuesday 08:30 Fill 2700 dumped by QPS on RCBXH2.L1
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
Summary of Week 16 G. Arduini, J. Wenninger
Friday 31st August & night
Thursday 10th May - morning
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
LHC Operations overview Week 28 – Getting back
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
LHC Morning Meeting - G. Arduini
Friday Morning 7:30 injection for fill 2908
Sunday
LHC Morning Meeting - G. Arduini
Tuesday Access for RF & QPS (others in the shadow) until ~18:00.
Sunday/Monday & :30 Stable beams. Fill #1851.
Monday – Morning Fill 3265 stable beams since 1:31
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
Monday 14:00 beam dump Access:
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
07/08/2010 Fill #1264 dump at 02:14:38.
Thursday 22 September 2011.
Polarity inversion 07:00 ALICE solenoid and dipole polarity switched to positive External Crossing angle polarity unchanged at injection/ramp & squeeze.
LHC - Week 38 Technical stop: Katy Foraz
Sat 15/10 New record bunch population profiting of the scrubbing period on Friday. Nb~1.42x1011p/bunch  110 MJ at 3.5 TeV. Filling slowed down by ZS sparking.
Tuesday 20 September 2011.
Thursday
Saturday 24 September 2011.
Coordination: Eva Barbara Holzer, Mike Lamont
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Monday 27th August & night
Wednesday 26 October 2011.
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Saturday Luminosity production 1380 bunches
Wed 12/10 09:30 – 10:30 Ramp down of ALICE solenoid to 50% nominal field on request of ALICE. Increase of the vacuum (e-cloud in this area that has not.
Saturday 26 November 2011.
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Sunday 12th 00:29 Stable beam fill #1864. Initial lumi 1.1e33
Friday 1st October : Van der Meer scans
Tuesday
Presentation transcript:

Tuesday 22 November 2011

Fill 2315 Fill # 2315 Stable beams: 4:33 – 11:54 (programmed dump) Integrated Luminosities: ATLAS: 5.8 ub-1 ALICE: 4.9 ub-1 CMS: 5.2 ub-1

BLM problem with tests (settings changed due to pending installation of new monitors) (19’) 13:12 injecting probe beam 13:19 – 16:40 (3:20) no beam from PS: problem with POPS (PS magnet powering system) Missing BLM data in XPOC (1h)

Fill 2316 Fill # 2316 Intensity: 3.6e12 charges injected Stable beams: 19:35 – 22:25 (trip of the RF module 1 of B2) Peak Luminosity ATLAS / ALICE / CMS: 470 / 373 / 392 (b s)-1 Integrated Luminosities: ATLAS: 3.3 ub-1 ALICE: 2.9 ub-1 CMS: 2.9 ub-1 Feedback from RF (Pierre and Philippe): At 22:24 there was a Helium tank pressure alarm, which probably corresponded to a local overheating which then caused the RF interlock and tripped the sector. This was most likely a quench. Such a trip has occurred in this module (M1B2) before and is suspected to be related to the cavity 3B2 which is weaker than the others. The recommendation was to reset and restart. Note that Beam 2 RF had been reduced to 13MV prior to this fill.

Fill 2316 – 11R5 57% of BLM threshold

Fill 2316 in stable beams

Injection Kicker MKI8 23:39 During kicker preparation sequence (‘softstart’): vacuum spike that caused the softstart to fail. Maybe electrical breakdown  extended softstart to recondition kicker (1:45)

pressure in the MKI8 during the failed soft start and the following extended soft start

‘a little bit of history repeating’ 1:35 injecting probe beams 1:42 No beam from PS, problem with POPS: two cells are down (EMD 303*6 and EMD 304*6 have over-current alarms and interlocks) The power supply fault is a short circuit in an AC/DC converter, and is not immediately fixable. To recover we have to exchange one component in the converter ( ~1 day duration) or switch back to the old Siemens rotating power supply. 7:00 decision to switch to the old power converter  estimated duration of work: 2 hours till 9:00 http://en.wikipedia.org/wiki/Shirley_Bassey

Others When putting the dp/p modulation back to the standard value of 2E-4 (was 4E-4 before) chromaticity measurements doubled

Outlook Physics for the rest of the week (VdM scan beginning of next week) Source refill (between 6 and 30 hours) – Friday ALICE polarity change – next Monday Requires some preparation work this week