Upgraded Injector Test Facility

Slides:



Advertisements
Similar presentations
INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.
Advertisements

FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Approved Labyrinth Fresh air pulled through “chicken wire” gate.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New.
’ tall Empty space below this metal sheet 66’ 14’ 4’ 10’ Ceiling tiles = 24 Concrete blocks 14’ long There are two “styles” of Ceiling tile,
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 31, 2015.
January 25, 2002David Finley to FARDOG using Harry Carter’s Slides Slide 1 Update to FARDOG: Technical Division Xband Activities Fermilab NLC Activities.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker October 21, 2015.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Re-scoping UITF Matt Poelker November 14, 2015.
Global Design Effort - CFS Oct IWLC ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Operated by JSA for the U.S. Department of Energy Thomas Jefferson National Accelerator Facility 1 Alex Bogacz UITF Beam-line Modeling (2) UITF Mtg. JLAB,
CEBAF Source and Injector Status PREx-II Collaboration Mtg Feb. 26, 2016 Matt Poelker and Joe Grames Center for Injectors and Sources.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker April 12, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker February 23, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Internal Personnel Safety Review UITF Overview and Introduction Matt Poelker.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
AIP and Large Projects Arne Freyberger OPS 2015 StayTreat.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 12, 2016.
Report Technical Director Storage-Ring-Installation Completed
LCLS-II Technical Requirements
RF Systems and Controls for the LERF CM Tests
CBETA Technical Review
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
Bubble Chamber Schedule – 2017
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
UITF – Upgrade Injector Test Facility
CEBAF Injector Update PREX/CREX March 3-4, 2017
XFEL Vacuum System Commissioning
Status of the cryogenic system for B180
UITF Project Status Meeting
UITF Project Status Meeting
CEBAF Injector Overview
Bubble Chamber Planning Meeting
Operation experience of cryogenic system and cryomodules for the superconducting linear accelerator at IUAC, New Delhi. T S Datta ( On behalf of Cryogenics.
Upgraded Injector Test Facility
Upgraded Injector Test Facility - UITF
UITF MPS system requirements
Performance Degradation cERL Injector Cryomodule
Center for Injectors and Sources
Riad Suleiman February 2, 2017
LERF Readiness Review: Charge
J. Seeman Assistant Director for PPA/LCLS
A. Freyberg Aug 2016 ECT’16 =>
Electron Beam Systems ETC and Methodology
Uses of UITF 10 MeV spin-polarized electron accelerator, beam current up to 100 uA M. Poelker December 12, 2018.
Test of Booster at UITF Reza Kazimi (12/12/18)
Polarized Source: Recent Activities
CTF Users’ Perspective
Upgraded Injector Test Facility
LCLS Personnel Protection System and Beam Containment System
Installation Status & Operational Readiness Process
UITF Conduct of Operations Review
UITF Conduct of Operations Review
LCLS e- Beams System Overview
LCLS e- Beams Systems Manager
QCM and C50-12 Status Update
Presentation transcript:

Upgraded Injector Test Facility

Upgraded Injector Test Facility Most groups stopped working on UITF during CEBAF SAD, including CIS (expected) Recall we made 200 keV beam and cooled QCM to 2K More recently, Adderley started to work on the beamline, Shaun recently ordered all the 80/20 beamline support structure Identified most of the hardware needed for elevated beamline at LERF, will borrow it Team HDIce now meeting regularly with Shaun to finish design IBC to be installed ~ end of August (W. Akers coordinating? LCLSII CMs must be moved, Kellner and company deployed)

UITF Meeting with Patrizia R., June 15, 2018 Tasks before running beam to HDIce for target commissioning Mechanical design, full time for next ~ 2 months, then intermittently (i.e., Shaun Gregory and company) Installation group to help secure HDIce target support structure Suggest we use the Vacuum Group to build the MeV beamline (my group can help) Cryo: install the helium return line, or be content to vent the helium to the test lab SRF, need a point of contact for all things related to QCM operation Electrical engineering and SSG: design and build the PSS BCM, our "credited control" to limit beam current/loss and prevent accidental exposure to x-rays Electrical engineering: stripline BPMs, get them to work Magnet group: build a third trim-card rack Cable-up the MeV beamline: valves, viewers, magnets, BPMs, harps, water flow meters, current monitors, …. RF group: commission the buncher with solid state amp, finish klystrons and high power amplifier, water skids SSG needs to incorporate high power RF interlocks into PSS, recertify. Add PSS BCM to circuitry Vashek: finish specifying the shielding requirements, then we start moving lead and sand (open CATS item) RCG to install all CARMs and electronics R&D related to low current BPMs, suggest Andy take this on, with help from Engineering Operations Group should augment Joe's modeling, using a particle tracking code (to support commissioning of QCM) Safety and Approvals: OSP for buncher, OSP for MeV beam, PSS BCM credited control documentation, UITF Accelerator Operations Directive, Conduct of Operations, Accelerator Readiness review (i.e., lots of documents, lots of reviews) Gun group needs to build a new photogun, improve the Wien filter, test polarimeters Need to operate the UITF on a daily basis.....students, Operators, Staff Scientist1 (critical hire list) Need access to liquid helium for weeks-long periods of time (i.e., competition with LCLS)

Upgraded Injector Test Facility (UITF) FY18

Upgraded Injector Test Facility (UITF) (slide from June) Deliverables/Milestones 200 keV beam, new gun, new beamline (gun getting moved to CEBAF now) Test the new QCM, cold with RF, but no beam acceleration MeV beam delivered to dump at waist height by end of FY18 MeV beam to HDIce FY19 Install new QCM at CEBAF, install old QCM at UITF (2020 SAD?) Staffing issues related to QCM: Cryo completed the work to connect the QCM to the CTF, Cool down to 2K was successful, 80K LN2 shield seemed to work fine albeit without RF applied to QCM, VTA used LHe while QCM was cold. Many thanks to Cryo! Work on high power RF has stalled When needed: now Staffing related to MeV beam EES/SSG, provide the credited control we call “PSS BCM” Bi-weekly meetings have started, we expect progress When needed: ~ August (seems unlikely) Issues/Concerns that will affect on time delivery Source Group will be busy at CEBAF injector through July but will try to find time to build second 200 kV gun, complete the waist-height beamline and push the safety documentation forward toward ultimate ARR conclusion Recommended Mitigation Be content with “best effort” basis, convert postdoc to full time employee