Assumption for a given sector

Slides:



Advertisements
Similar presentations
1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Advertisements

Commissioning the access system M. Gruwé Machine checkout workshop November 8 th 2007.
1 Powering Tests and Safety Electrical Safety Hugues Thiesen Power Converter Group.
O. Beltramello ATLAS experimental cavern Patrol Procedure LAAWG – October 07 O. Beltramello.
SPS Secondary Beam Experimental Areas Access System 7 September 2012.
Tomasz Ladzinski GS/ASE. LASS Annual Maintenance & Tests General Principles Each winter shutdown preventive maintenance of EIS takes place. It is followed.
How to improve operational efficiency ? [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] Beam Commissioning Workshop, Evian Jan 2010.
CRYOGENICS AND POWERING
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
CLIC CES Webex 12 Nov Summary: – Set of fire safety measures defined in CERN Safety Report – Proposed Structure for CLIC/ILC Fire Safety Report Fabio.
Consolidation of access systems for the injector Complex ATOP days 4-6 March 2009 P. Ninin & R, Nunes in behalf of the PS and SPS access project teams…
Helium Spill Test in LHC tunnel to define length of restricted working areas  Actual situation  Evolution  How to continue  Set-up of the spilling.
LHC ACCESS SYSTEM 1Authors: P, Ninin, S. Grau & LHC access team EDMS: Access System during the LHC Injection tests P. Ninin, S. Grau - TS/CSE Workshop.
How to achieve satisfactory performance of the access system: stability, efficiency, operation, fluidity Timo Hakulinen (GS/ASE) Thanks: LHC access team.
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
LHC ACCESS SYSTEM 1 Authors: P. Ninin, L. Scibile, T. LadzinskiEDMS: Access Control and Safety System for the LHC Experiments P. Ninin L. Scibile.
Wojciech Sliwinski BE/CO for the RBAC team 25/04/2013.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
Access system M. Gruwé (AB/OP) Thanks to TS/ASE group Extended LTC meeting March 3 rd 2008.
Task Force on Safety of Personnel in LHC underground areas following the sector 34 accident of 19-Sep-2008 Status report LPC 07/05/2009 B. Delille, S.
For more info:
Experimental Areas Studies Lessons learnt at CMS M Gastal & CMS Technical Coordination (A Ball, W Zeuner)
Access System – LASS/LACS L. Ponce On behalf of the OP team.
ADO-PO Section Meeting Safety Group LS1 Shutdown Safety Organization.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Call Us When Ordinary Security Is Simply Not Enough. OMEGA PROTECTIVE SERVICES and INVESTGATIONS LLC.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
LHC ACCESS SYSTEM 1 EDMS: January 2008 Global Tests of the LHC Access system Outcome P. Ninin, T. Petterson, S Grau, T. Ladzinski 18 th January.
Final Report – Injector Re- Commissioning Working Group (IRWG) Working group to find strategy for more efficient start-up of injectors and associated facilities.
Access system global tests M. Gruwé LHCCWG January 15 th 2007.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
A. Herlert, CERN PH-IS ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008 ISOLDE scientific coordinator’s report INTC meeting, May 19, 2008.
External Data and DIP Oliver Holme 18 th January 2008.
An invitation to an open discussion We are team reviewing its performance globally We want to help each other to reach the objectives We know the other.
WIR SCHAFFEN WISSEN – HEUTE FÜR MORGEN Transition to user operation Didier Voulot :: Paul Scherrer Institut SwissFEL Commissioning Workshop, 22 March2016.
Access system LHC-SPS M. Gruwé and J. Ridewood OP days March 18 th 2008.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
LHC intervention scheduling with the Work Acceptance Tool
(Access system for HWC)
SPS Personnel Protection System Renovation Project
ALICE 5 o’clock meeting Wk 51.
Machine operation and daily maintenance management in SOLEIL
Landpower Project Zero Harm Learning Series Module:. #7a Module Title:
Cross-site problem resolution Focus on reliable file transfer service
CENF – Personnel Protection System Preliminary Study
Accelerator Operations Department Readiness (Part 2)
CENF – Personnel Protection System Preliminary Study
Energy Day Strawman Proposal
Evolution and future of the Access safety and control systems
FCC Civil Engineering update
Helium spill in LHC tunnel
LAAWG Status Report – 15th May 2007
Update on HW commissioning
LHC-TS3 Coordination meeting #3
Access to the experiment
SPS CC: Final plan for interlocking of crab cavities in SPS
A very first look at siting issues
EYETS 2016/2017 Activities SPS Access system Maintenance and Evolutions Access system EYETS 2016/2017 EDMS:
Cryogenic Risk Assessment in LHC
Landpower Project Zero Harm Learning Series Module:. #7a Module Title:
Monday 11/07: Recovery Plenty of accesses.
Setting the scene: Why use PM?
Loyola’s Performance Management Process For Employees
Technical Stop #4 29th August - 2nd September 2011
1v1.
Loyola’s Performance Management Process For Employees
Medical Office Management
LOCK AND TAG PROGRAM FOR THE CONTROL OF HAZARDOUS ENERGY
Powering and Safety day Underground access during powering tests
Review of hardware commissioning
Presentation transcript:

Assumption for a given sector Shutdown: general mode Powering tests: Access restrictions when powering: No one underground when tests above 1 kA (rule to be discussed elsewhere) Tunnel Adjacent tunnel areas ? To be discussed elsewhere… Service areas ? To be discussed elsewhere… Experiments ? To be discussed elsewhere… Restricted/closed (coordination of access by point owners and Rudiger) Cold checkout: restricted/closed (coordination of access by point owners and Gianluigi) Beam (coordination of access by machine coordinator + EiC) January 20th 2009

Access during powering tests (I) Proposal: ADI when possible (scheduled interventions) (approved by point owners) EIC on shift decision on the spot for any other access request? But, of course: Get input from point owners Inform point owners January 20th 2009

Access during powering tests (II) If long (few days) interruption of powering tests: ADI compulsory General mode with restricted list at PAD level (LHC-TNL34 like) Restricted list automatically filled from ADI (when signed)… feasibility to be checked January 20th 2009

Access during powering tests (III) Grouping accesses? What about one day with most accesses? Rest of the week: powering tests and NO access (except if required for fixing up for continuing test) Compatibility with schedule of accesses in experimental caverns? Feedback from last year: access during working hours and tests after 5pm was not efficient January 20th 2009

Interlocks? Starting tests: Feasible in the short term ? Start test above 1kA only when patrol SAFE no keys out closed mode ? Drawback: if in restricted mode, people might think there is no test ongoing: false feeling of safety Start test below 1kA only when Patrol SAFE? OR envelop doors are all closed and emergency handles armed? During powering: Interrupt test? How? Under which conditions? January 20th 2009

Other organizational issues How to get enough patrollers? Real patrol (procedure to be followed) requires MANPOWER and TIME! Last year, unfortunately, simply “green boxes”, in which case equivalent to have no patrol at all. Who will rearm doors (external envelop/powering test envelop)? Possible candidates: CSA, gérants de site, OP, people on shift, coordination team. Mandate and priorities? Flow of information between person who authorizes the access and person who gives the access? January 20th 2009

How to enforce the rules? Who has got authority to refuse an access request? Who has got authority and appropriate means to empty a zone such as Service area? Experiment? Non interlocked underground areas? Real patrol (procedure to be followed)! Last year, unfortunately, simply “green boxes”, in which case equivalent to have no patrol at all. January 20th 2009