1 Dennis Daughters, P.E. City Engineer / Director of Engineering, City of Sarasota Lido Key Beach Renourishment Program & New Pass Dredging.

Slides:



Advertisements
Similar presentations
Numbers Treasure Hunt Following each question, click on the answer. If correct, the next page will load with a graphic first – these can be used to check.
Advertisements

Scott's Winter Forecast ! How do I make a forecast?
Accredited Supplier Communications Plan FY09-10 Q1 to Q4 May 2009, v2.0 Home Access Marketing & Stakeholder Engagement Team.
AP STUDY SESSION 2.
1
Feichter_DPG-SYKL03_Bild-01. Feichter_DPG-SYKL03_Bild-02.
Flexible Budgets, Variances, and Management Control: II
© 2008 Pearson Addison Wesley. All rights reserved Chapter Seven Costs.
Copyright © 2003 Pearson Education, Inc. Slide 1 Computer Systems Organization & Architecture Chapters 8-12 John D. Carpinelli.
Copyright © 2011, Elsevier Inc. All rights reserved. Chapter 6 Author: Julia Richards and R. Scott Hawley.
Author: Julia Richards and R. Scott Hawley
1 Copyright © 2013 Elsevier Inc. All rights reserved. Appendix 01.
UNITED NATIONS Shipment Details Report – January 2006.
David Burdett May 11, 2004 Package Binding for WS CDL.
Performance of Hedges & Long Futures Positions in CBOT Corn Goodland, Kansas March 2, 2009 Daniel OBrien, Extension Ag Economist K-State Research and Extension.
1 RA I Sub-Regional Training Seminar on CLIMAT&CLIMAT TEMP Reporting Casablanca, Morocco, 20 – 22 December 2005 Status of observing programmes in RA I.
Tennessee Higher Education Commission Higher Education Recommendations & Finance Overview November 15, 2012.
FACTORING ax2 + bx + c Think “unfoil” Work down, Show all steps.
Year 6 mental test 15 second questions Calculation Addition.
Grants 3.0 Departmental Administrator Review January 22, 2014.
REVIEW: Arthropod ID. 1. Name the subphylum. 2. Name the subphylum. 3. Name the order.
Break Time Remaining 10:00.
PP Test Review Sections 6-1 to 6-6
EU Market Situation for Eggs and Poultry Management Committee 21 June 2012.
Funding, Regulatory, and Private Property Right Issues Encountered by a Small Coastal Community 1.
2 |SharePoint Saturday New York City
Exarte Bezoek aan de Mediacampus Bachelor in de grafische en digitale media April 2014.
VOORBLAD.
15. Oktober Oktober Oktober 2012.
Copyright © 2012, Elsevier Inc. All rights Reserved. 1 Chapter 7 Modeling Structure with Blocks.
1 RA III - Regional Training Seminar on CLIMAT&CLIMAT TEMP Reporting Buenos Aires, Argentina, 25 – 27 October 2006 Status of observing programmes in RA.
Factor P 16 8(8-5ab) 4(d² + 4) 3rs(2r – s) 15cd(1 + 2cd) 8(4a² + 3b²)
Basel-ICU-Journal Challenge18/20/ Basel-ICU-Journal Challenge8/20/2014.
Time Series for Oil Facility on East Timbalier Island Aerial Video Survey Program Pontchartrain Institute of Environmental Sciences University.
Time Series for Central West Grand Terre Island of the Lafourche Shoreline Aerial Video Survey Program Pontchartrain Institute of Environmental.
1..
CONTROL VISION Set-up. Step 1 Step 2 Step 3 Step 5 Step 4.
© 2012 National Heart Foundation of Australia. Slide 2.
Adding Up In Chunks.
Understanding Generalist Practice, 5e, Kirst-Ashman/Hull
The Church is… 1. God’s people 2 Our Facility is… 3.
Benjamin Banneker Charter Academy of Technology Making AYP Benjamin Banneker Charter Academy of Technology Making AYP.
Model and Relationships 6 M 1 M M M M M M M M M M M M M M M M
Subtraction: Adding UP
: 3 00.
5 minutes.
Januar MDMDFSSMDMDFSSS
Analyzing Genes and Genomes
©Brooks/Cole, 2001 Chapter 12 Derived Types-- Enumerated, Structure and Union.
Essential Cell Biology
Converting a Fraction to %
Clock will move after 1 minute
PSSA Preparation.
Reporting and Interpreting Owners’ Equity
Essential Cell Biology
Weekly Attendance by Class w/e 6 th September 2013.
Immunobiology: The Immune System in Health & Disease Sixth Edition
Physics for Scientists & Engineers, 3rd Edition
Energy Generation in Mitochondria and Chlorplasts
1 Fundamental Stock Analysis The Market is NOT Efficient Fundamental analysis can uncover individual companies selling in the public market at significant.
Select a time to count down from the clock above
Murach’s OS/390 and z/OS JCLChapter 16, Slide 1 © 2002, Mike Murach & Associates, Inc.
1 Ocean View Shoreline Project Update Overview for Norfolk City Council January 7, 2014.
TOPSAIL BEACH 30 Yr Beach Management Plan June 8, 2011.
Presentation transcript:

1 Dennis Daughters, P.E. City Engineer / Director of Engineering, City of Sarasota Lido Key Beach Renourishment Program & New Pass Dredging

2 Location, Location, Location Lido Key New Pass Big Sarasota Pass

3 Presentation Content Lido Key Beach Erosion Control Projects Presentation Content History of Island Long Range Master Plan Projects 1997 New Pass Dredging 1998 Restoration 2001 Interim Restoration 2002 New Pass Dredging 2004 Federal Nourishment

4 History of Island New Pass formed in 1848 by hurricane. New Pass formed in 1848 by hurricane. Initial dredging of New Pass in Initial dredging of New Pass in Group of small detached mangrove islands, Cerol Isles. Group of small detached mangrove islands, Cerol Isles. filled by John Ringling in the 1920s. filled by John Ringling in the 1920s. City purchased 16.2 acres at mid-section in City purchased 16.2 acres at mid-section in built a public spa and casino. built a public spa and casino. County purchased 153 acres at South Lido area in County purchased 153 acres at South Lido area in dedicated South Lido Park to be preserved in a natural state. dedicated South Lido Park to be preserved in a natural state. City purchased 60.9 acres at north section in City purchased 60.9 acres at north section in dedicated North Lido Park to be preserved in a natural state. dedicated North Lido Park to be preserved in a natural state.

5 Long Range Master Plan City obtained services of Coastal Planning & Engineering (CPE) in January 1990 to develop long-range beach management and erosion control plan. City obtained services of Coastal Planning & Engineering (CPE) in January 1990 to develop long-range beach management and erosion control plan. CPE completed Long Range Master Plan in January CPE completed Long Range Master Plan in January Plan examined 7 erosion control alternatives, a buy-out/ retreat approach, 4 renourishment options and an offshore breakwater. Plan examined 7 erosion control alternatives, a buy-out/ retreat approach, 4 renourishment options and an offshore breakwater. Plan recommended renourishment of 9,000 feet of beach (from R-35 to R-44) at minimum width of 75 feet. Plan recommended renourishment of 9,000 feet of beach (from R-35 to R-44) at minimum width of 75 feet.

6 Inlet Management Plans FDEP required City to develop Inlet Management Plan for both, New Pass and Big Sarasota Pass. FDEP required City to develop Inlet Management Plan for both, New Pass and Big Sarasota Pass. City obtained services of CPE in June 1992 to develop both Inlet Management Plans. City obtained services of CPE in June 1992 to develop both Inlet Management Plans. CPE completed New Pass Inlet Management Plan in June 1993 and Big Sarasota Pass in September CPE completed New Pass Inlet Management Plan in June 1993 and Big Sarasota Pass in September Both Plans included Sand Sediment Budget. Both Plans included Sand Sediment Budget. New Pass IMP recommended continual periodic dredging of New Pass channel. Big Pass IMP did not. New Pass IMP recommended continual periodic dredging of New Pass channel. Big Pass IMP did not. Town of Longboat Key disagreed with Sand Budget. Town of Longboat Key disagreed with Sand Budget. Neither Plan approved by FDEP. Neither Plan approved by FDEP.

7 Federal maintenance began in Federal maintenance began in Eight Projects done. Eight Projects done. Dredging has occurred about every 4-5 years. Dredging has occurred about every 4-5 years. 2 ¼ million cubic yards dredged in last 35 years (8 projects). 2 ¼ million cubic yards dredged in last 35 years (8 projects). Average 280,000 c.y. per dredging. Average 280,000 c.y. per dredging. Year Quantity (c.y) , , , , , , , ,000 New Pass Dredging Project

8 Cubic Yards Dredged

9 LONGBOAT KEY LIDO KEY 1982, 1985, 1991, 1997 CHANNEL ALIGNMENT 1964, 1970, 1974, 1977 CHANNEL ALIGNMENT

New Pass Dredging New Pass Dredging Project - USACE New Pass Dredging Project - USACE Hendry Dredging began June 15, 1997 Hendry Dredging began June 15, 1997 Placed 163,000 cubic yards (50% of total) on north part of Lido Beach Placed 163,000 cubic yards (50% of total) on north part of Lido Beach Completed work in September 1997 Completed work in September 1997 No local funds involved No local funds involved

Restoration Project City/State Funded Project City/State Funded Project Applied for grants for many years Applied for grants for many years Received 25% State grant in May 1997 Received 25% State grant in May 1997 Placed 285,000 cubic yards in May 1998 Placed 285,000 cubic yards in May 1998 Total cost = $3.41 million. ($12.00/Cubic Yard) Total cost = $3.41 million. ($12.00/Cubic Yard) Protection from Earl, Georges & Harvey Protection from Earl, Georges & Harvey

12 Hopper-type Dredge Weeks Marines operation during 1998 Lido Beach Restoration Project

Interim Lido Restoration Severe erosion incurred in last few years ELegance condominium lost almost all of their newly constructed dune

14 Southern Lido Key Serious erosion South end of 1998 Restoration Project

15 Buildings were in jeopardy 2001 Interim Lido Restoration

Interim Lido Restoration Benefits Benefits Storm protection - private & public Storm protection - private & public Recreational - longitudinal beach access Recreational - longitudinal beach access Economic - increased tourist tax dollars Economic - increased tourist tax dollars Environmental - increased areas for vegetation, sea turtle nesting, etc. Environmental - increased areas for vegetation, sea turtle nesting, etc.

Interim Lido Restoration Ebb shoal extends south Severe erosion and exposure of Lido Harbor and Lido Harbor South North Note gray sand from 1998 Project Big Sarasota Pass

18 Beach Fill Comparison Beach fill for Feeder Beach concept Beach fill for Groin concept St. Armands Key Lido Key

Interim Lido Restoration Before After Pool

Interim Lido Restoration During

21 Limits of Projects 1997 Project limits

New Pass Dredging Sarasota County is Local Sponsor. Sarasota County is Local Sponsor. City/County worked together to obtain funding for USACE. City/County worked together to obtain funding for USACE. Congressman Dan Miller was of great assistance in getting approval. Congressman Dan Miller was of great assistance in getting approval. City of Sarasota and Town of Longboat Key will share the sand on 50/50 basis. City of Sarasota and Town of Longboat Key will share the sand on 50/50 basis.

23 USACE wanted to dredge in this location. USACE is now going to dredge in this location, as they did the last 4 times. Normal shoreline when dredging is straight out.

New Pass Dredging USACE awarded contract on 30 September 2002 to Goodloe Marine, Inc. USACE awarded contract on 30 September 2002 to Goodloe Marine, Inc. Bid amount for New Pass project is $2,231,050. Gordon Pass will be extra $$. Bid amount for New Pass project is $2,231,050. Gordon Pass will be extra $$. Pre-construction meeting was held on November 1, Pre-construction meeting was held on November 1, Construction to began 15 December Construction to began 15 December Completed Lido portion on 1 Febr Completed Lido portion on 1 Febr

New Pass Dredging Water Surface Existing Bottom 10 foot Required Depth With 2-foot allowable overdepth 100 feet inside Pass 150 feet outside Pass Material to be removed Existing Waterway Typical Cross-section

26 White Sand Issue Gray sand compared to natural beach color Some people dont like gray sand.

27 White Sand - Status Sand dredged from New Pass is white sand. USACE included two options in their contract for New Pass Dredging with City to pay difference. Stock pile 123,000 cy at R-35.5 to R-38.5 or, Spread 123,000 cy from R-35.5 to R-44. Citys actual share will be $98,050 plus 7.5% Admin. costs. White sand was spread from north of Holiday Inn to Big Sarasota Pass, if there is sufficient sand.

White Sand Project Beach Cross-section Lido Resort Or Condo Existing Gray Sand Beach Move 2 of gray sand to waters edge Place 2 layer of white sand Move 2 of gray sand to waters edge White sand layer Water surface Elevation +5.0

29 Federal Nourishment Project Initially authorized by Congress - December 31, Initially authorized by Congress - December 31, De-authorized by USACE - January 1, De-authorized by USACE - January 1, Approval for Reconnaissance Study Approval for Reconnaissance Study Reconnaissance Study completed - January Reconnaissance Study completed - January Feasibility Cost Sharing Agreement Feasibility Cost Sharing Agreement Signed by City - July 20, Signed by City - July 20, Signed by USACE - July 20, Signed by USACE - July 20, Re-authorized by Congress - August 7, 1999 Re-authorized by Congress - August 7, /35 of initial project and 50 year commitment. 65/35 of initial project and 50 year commitment.

30 Federal Nourishment Project Feasibility Study began - November Feasibility Study began - November $700,000 shared 50/50. $700,000 shared 50/50. Now 95% complete. Now 95% complete. Submit to Congress January Submit to Congress January Selected Plan – 1,075,000 cy and 3 groins. Selected Plan – 1,075,000 cy and 3 groins. Design / Construction Phase - Year 2004 Design / Construction Phase - Year 2004 $12.95 million with Citys share about 37.3%. $12.95 million with Citys share about 37.3%. State grant program may fund 50% of Citys share. State grant program may fund 50% of Citys share. Renourishment Phase - Year 2008, 2012, Renourishment Phase - Year 2008, 2012, $5.3 million to be shared 50/50. $5.3 million to be shared 50/50.

31 Federal Nourishment Project New Pass Big Sarasota Pass St. Armands Circle Sand Placement 3 Groins

32 TDT Funding Commitments Original 2% levy: $300,000/year (more or less) Additional 1% levy: $1.1 million in FY 97/98 $304,000 in FY 98/99 $146,000 for 6 years FY98/99 to FY 03/04 $1.1 million in FY 01/02

33 Funding Grants The City of Sarasota, with great assistance from Lido Key residents/owners, has pro-actively obtained additional state and federal grants. The 1998 project required 75% local funds. The 2001 & 2002 projects required 53% local funds. The 2004 project will require 19% local funds.

34 Revenue $7.1 million from County TDT $3.4 million from State DEP $0.4 million from Federal

35 City of Sarasota Thanks You Enjoy your Lido Beach ! Lido Key Beach Maintenance Program & New Pass Dredging