Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Beam expected in the afternoon PM: – Establish first-turn – Establish closed orbit – Rough correction of machine parameters Evening: – RF capture Night:
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
LHC progress Report LHCC Wednesday 23 rd March 2011.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Saturday 24 March 2012.
Wednesday 21 March 2012.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Summary of week 7 Hardware Commissioning:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
Monday 11/07: Recovery Plenty of accesses.
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
Summary week 31 Week 31 G. Arduini & O. Brüning
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Monday 6th August & night
LHC Morning Meeting - G. Arduini
Summary of Week 16 G. Arduini, J. Wenninger
Lost at 12:05 to power converter (RTQX2.R1) problem
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Friday March 4th 08h32: Access for beam dump system.
Tuesday 20 March 2012.
Friday 14th December - morning
Monday Morning – recovery from cryo.
Monday February 28th 8h00: Injection
Tuesday 28th September Fill 1375 ongoing 09:00 Move in Roman Pots
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Planning at 5 o’clock meeting Friday
Wednesday 03/11 – The Plan Finish electron-cloud program:
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Friday 8/10/10 - Morning Planned to keep fill until the afternoon
07/08/2010 Fill #1264 dump at 02:14:38.
Summary for LPC (March 7th, Ralph Assmann)
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
Friday 28 October 2011.
Summary Tuesday h23: Machine closed. Precycle started.
Wednesday 23/2 Thanks CRYO!!!.
Thursday 30th September De-bunching test
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Monday 10th December - morning
31/3/2010 Difficult day… but at the end stable beams.
15/12/2009 Vacuum interlock in sector 78 understood  out-gassing of a Penning gauge ignited as a result of ionization or dust arcing In conclusion: NO.
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4) No problem found for dump resistor for RB.A81. Some more measurements will be taken. RCBYV4.L1B2 power converter replaced IMPACT delaying access start (new requests were not propagated to the access point fast enough)  Requested to deactivate the check of the IMPACT for access to the LHC machine for the time being.  Possible solution of being studied Update for FGC during access  RT input now take into account

Friday 16/3 11:30 Gateway at point 1 crashed. Lost communication for several power converters. Problem with sub-converter of RQX.L2 required another access at ~ 12:00. 13:30-15:30 No beam from PS. PS Main power supply problem. 13:45 trip of ATLAS solenoid and toroid while ramping up.

Loss map by controlled transverse blow-up 16:00 – 21:30: Setting-up of tune and orbit feedbacks and of radial modulation for chromaticity measurement Setting-up of the damper for controlled transverse emittance blow-up for Beam 1 for aperture measurements and loss maps

Loss map by controlled transverse blow-up

While preparing for the ramp While preparing for the ramp. Vacuum spike due to gauge outgassing (between Q5 and Q6.L5)  piquet opened vacuum valve.

4 TeV!!! Beam 2 dumped at flat top: glitch in the safe beam flag combined with a intermittent interlock on BMPSA.4R6.B2.

Ramp to 4 TeV Tune, chromaticity, orbit, coupling measured  feedforward to be done

Status and Plan Preliminary global aperture measurements overnight and validation transverse blow-up for aperture and loss maps  to be analyzed Day Shift Time (h) Activity Breakpoint System/topic Beam SAT M 8 Squeeze to 0.6 m First squeeze Squeeze Probe A Optics measurements - test dump at 4 TeV   Optics N Damper setup for controlled blow-up (B2) and for nominal bunch RF Nominal SUN Dump checkout Dump 4 Orbit at injection with nominal bunch and bumps OP Experimental magnets ON Orbit feedback with dynamic reference in the ramp Feedback Pre-cycle or ramp (no beam) - decay measurement at 450 GeV Magnets

Pending issues BPMSA.B4R6.B2. Noisy and giving spurious interlocks Vacuum gauge outgassing between Q6 and Q5.L5 There is no fill number data stored in the logging DB since the beginning of this year  fixed Logged chromaticity data not correct yet Issue with generation of the functions for trim quadrupoles Suspected electrical problem on a fire detection unit in UX85