ISPA Measure 2002 BG 16 P PE 009 WWTP Bourgas – Meden Rudnik
Works Contract Commencement Date: 15th May 2007 Completion Date: 31st Dec. 2009 Physical Execution: 100 % Financial Execution: 100 % WWTP became operational on 21st Dec. 2009 1 year DNP expired on 27th Dec. 2010 Performance Certificate was issued on 27th Dec. 2010 Final Payment was made on 27th Dec. 2010
WWTP Meden Rudnik - Completed
WWTP Meden Rudnik (during DNP and operation)
WWTP Meden Rudnik (during DNP and operation)
Reconstruction of the Main Collector (implemented by Final Beneficiary)
Reconstruction of effluent channel (implemented by ViK Bourgas)
Site visit by reporters of TV France 3
WWTP Meden Rudnik Publicity
Supervision Contract Commencement Date: 24th April 2007 Completion Date: 31st March 2011 Time elapsed: 100 % Financial Execution: 100 %
Compliance with Article 8 of the Financing Memorandum All other conditions under Article 8 of the FM are considered fulfilled.