LERF Cryomodule Testing Facility – Accelerator Systems Deliverable Jose Chan August 3-4, 2017
Request 1.3 GHz SSAs L-Band Isolators LLRF control racks Requested 16 units SLAC has over 120 in storage L-Band Isolators SLAC just placed production order with Ferrite Delivery starts in January 2018 LLRF control racks Requested 4 units Order racks in August, load racks at SLAC in January LCLS-II LERF Test Facility Review
Request from Cryogenic Systems All requested items (SSAs, Isolators & LLRF Racks) will be available to LERF testing facility by March 2018 All requested items will have to be returned for LCLS II installation Will need to BCR resources, packing and shipping and linking activities in P6 LCLS-II LERF Test Facility Review