Saturday 7th May Sat – Sun night

Slides:



Advertisements
Similar presentations
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Advertisements

The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
MD Wed – Sat DayTimeMD Wed06:00UPS repair, ATS optics checks w/o beam 12:00Cycle, test ATS optics w/o beam 16: TeV: BPM offset determination for.
Shortened program (2 days), as decided in LMC. MD program worked very well  all MD’s on plan with ~foreseen beam time. LHC in very good shape with excellent.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Preliminary MD Report R. Assmann, G. Papotti, F. Zimmermann
Floating MD week 28 summary
Ion Commissioning: Thursday & Friday
Wednesday
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
MD Planning Fri – Sat (26. – 27.8.)
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
-9:00: Test IP transverse adjustment (CMS) and optics verification.
Saturday 24 March 2012.
Wire, flat beams and beam-beam MDs in 2017
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
MD Report 24 June 2012 Machine coordinators: Barbara Holzer, Mike Lamont MD Coordinators: Ralph Assmann, Giulia Papotti, Frank Zimmermann MD#2 News & Plan.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
MD2490: Measurement of the TMCI Threshold at Flat-Top
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Thursday morning – optics correction
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Friday March 4th 08h32: Access for beam dump system.
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Week 36 Machine coordinators R.Assmann, R.Bailey
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
Planning at 5 o’clock meeting Friday
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Friday 16/3 08:30 – 10:15 Access for QPS and EPC (BI in point 4)
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Friday 23rd March 08:00 Access
(on behalf of the LHC team)
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
MD Planning Fri – Sat (1. – 2.7.)
Summary for LPC (March 7th, Ralph Assmann)
Saturday :42 stable beams fill 3541
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Sat 18/3 - Ramp to 4 TeV Again glitch on the safe beam flag for beam 2. Cause identified: noise on BCT2B giving values above the safe beam limit (2.4×1010.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
LHC status - Week 35 G. Arduini, M. Lamont Main aims:
Wednesday 23/2 Thanks CRYO!!!.
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Tuesday – Morning and Evening
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
31/3/2010 Difficult day… but at the end stable beams.
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Saturday 7th May Sat – Sun night Machine Status: OK Sat – Sun night 2 hours lost due to linac 5 V power supply problem 03:45 Start 2. ramp for collimation 05:20 Dumped beam from collimation RF getting the beams ready in the SPS 06:00 Ready to inject for RF multi-bunch instability MD QPS OK MB.A28R4 lost – checked 06:40 RF MD going, getting the right beams in the SPS There seems to be some features with the tune as seen by the BBQ. It seems that there is an influence from an external source at 0.43 *frev 08/05/2011 LHC 8:30 meeting

Saturday 7th May MD Status: Also OK -> Summary from Ralph Day Time 04:00 0.45 TeV: Investigation on CODs 10:00 0.45 TeV: ATS (including cycle to new injection settings) 20:00 0.45 – 3.5 TeV: Nominal collimation, single bunch tune shift Ramp down, cycle Sun 06:00 0.45 TeV: RF multi-bunch instabilities 0.45  3.5 TeV: Coupled-bunch instability rise times 18:00 0.45  3.5 TeV: Quench test in the DS of IR7 Mon Technical Stop Lost 6h 3.5 TeV: Tune scan – beam-beam optimization, lifetime, losses 08/05/2011 LHC 8:30 meeting

0.45 TeV: Investigation on CODs Nuria, Matteo, et al Investigation done on the following CODS: 1 - RCBYHS5.R8B1 2 - RCBYV5.L4B2 3 - RCBYH4.R8B1 4 - RCBYHS4.L5B1 5 - RCBCV8.L1B2 Procedure: Bump with each of the correctors observing leakage to machine. Data acquired at 25Hz has to be analyzed online, but some hints suggested good results (especially the corrector 2 showed a large dynamic response). Further analysis has been done on correctors 1 and 5 sending a sinusoidal current at different frequency. Results to be analyzed. Ongoing. 08/05/2011 MD #1 2011/12

0.45 TeV: Investigation on CODs Nuria, Matteo, et al Dynamic orbit effect while ramping bump with correctors. 08/05/2011 MD #1 2011/12

New ATS Optics S. Fartoukh et al New injection optics (ATS optics) tested and ramped successfully up to 3.5 TeV crossing scheme off (TCT, TDI, TCLI opened with probe beam successfull inject and dump test damper new settings OK (with new phases of the ATS optics) no emittance blow up during the ramp new integer tunes measured at injection 62/60 (instead of 64/59) CO, tune, coupling, chromaticity measured and corrected at injection and flat top new tune, chroma and coupling knobs operational orbit and tune feed-back successfull during the ramp. beta-beat measurement 30% at injection, 10-15% at flat top w/o any specific correction H and V dispersion measured H: +/- 50 cm (compared to 2 m) for Dx at injection, +/- 20 cm at flat top. V: 15-20 cm peak at injection, about 10 cm at flat top. 08/05/2011 MD #1 2011/12

New ATS Optics Next steps: S. Fartoukh et al inject and ramp with crossing scheme (170 murad, 2 mm in all IP's kept constant during the ramp). pre-squeeze to bstar=1.2 m w/o crossing scheme. measure/correct the off-momentum beta-beating, and non-linear chromaticity. switch on the crossing scheme at bstar=1.2 m and measure/correct the spurious dispersion. 08/05/2011 MD #1 2011/12

ATS New Injection Orbit – Ramp 08/05/2011 MD #1 2011/12

ATS New Injection Orbit – Dispersion 08/05/2011 MD #1 2011/12

Nominal collimation, single bunch tune shift Initial blow-up tests with transverse damper. Injection scraping during short delay from injectors. Nominal 3.5 TeV collimation settings achieved for b1 &b2: TCP = 5.7 sigma (nom) TCSG = 6.7 sigma (nom) TCLA = 9.7 sigma (nom) TCSG-IP6 = 7.2, TCDQ-IP6 = 7.7 sigma (nom) Octupoles trimmed to 350A for beam 1. For b1 moved towards nominal 7 TeV settings. Limited by TCSG losses close to IP7. Valid setup reached: TCP = 4.0 sigma (nom) (equiv. to 7.TeV nominal 5.7sigma) TCSG = 6.0 sigma (nom) TCLA = 8.0 sigma (nom) TCSG-IP6 = 7.0, TCDQ-IP6 = 7.5 sigma (nom) 08/05/2011 MD #1 2011/12

Nominal collimation at 3.5 TeV Smallest gap: 2.2 mm Beam lifetime: > 100 hours Tune shift measured: ~3e-4 Efficiency measured: 3e-5 – 1e-4 08/05/2011 MD #1 2011/12

Blowup Test Transverse Damper 08/05/2011 MD #1 2011/12

Settings b1 first loss-maps 08/05/2011 MD #1 2011/12

Settings b2 first loss-maps 08/05/2011 MD #1 2011/12

Lifetime small collimation gaps 08/05/2011 MD #1 2011/12

Vertical tune shift – collimator movement Clearly seen in vertical plane when moving collimtors out by 4 sigma and back in, etc… Magnitude: ~0.0003 08/05/2011 MD #1 2011/12

Efficiency measured – here b1, horizontal 08/05/2011 MD #1 2011/12

Nominal collimation Tune shifts of the order of 1e-4 to 3e-4 could be observed at flat top when synchronously moving a fraction of the collimators from nominal settings by 4 sigma. The tune signals were again very noisy and drifting, and both damper gains and octupole currents should be lowered to increase the signal/noise ratio. However, the signals were clear enough during the first ramp in the vertical plane and there was no time to observe in real time during the second ramp, so that we did not try to decrease these gains that could have jeopardized the loss maps. Many thanks to the OP teams for their help and very quick reaction to the several issues that occurred during the MD! Conclusion from second ramp: Tight settings, very close to 7 TeV settings, have been qualified for B2. In B1, larger retractions between primary and secondary colliamtors are needed (2 sigma worked). 08/05/2011 LHC 8:30 meeting