October 11, 2018
Updates Phase 1.1 Phase 1.2 Partner coordination Remaining items Santa Rosa pedestrian crossing Phase 1.2 Design status Construction activities Commerce Street closure Partner coordination
Phase 1.1 Update Remaining Items Santa Rosa Pedestrian Crossing Additional railing at Travis Gatehouse Inlet lighting Temporary lighting has been installed Trash screen at inlet pump station Santa Rosa Pedestrian Crossing Final design submitted for construction
Increased Pedestrian Safety Constant flashing advanced crosswalk warning sign Rumble strips prior to crossing Pedestrian-activated RRFBs at crossing Mirror to allow pedestrians to see around curve
Phase 1.2 Construction Update Early Work Package (EWP) 11: Demolition and Utility relocation Utility relocation work ongoing Archeological mitigation in Calder Alley has been completed
Phase 1.2 Construction Update EWP 12: Heavy Civil Construction Drilled pier construction Former Dollar General site Penners parking area Dolorosa to Commerce EWP 13: Commerce bridge decking, Penners overhang NTP pending
Commerce Street Closure Impacts will delay opening of one lane Projected in mid-November
Phase 1.2 Design Update 100% design plans submitted July 31 Design review meetings Subcommittee: August 28 Executive Committee: September 14 Guaranteed Maximum Price (GMP) submittal September 21 Scope reduction exercise in progress Presentation of design and GMP to Bexar County Commissioners Court in November
Partner Coordination Camaron Street construction Project construction will be added to SDJV contract SAISD administration building Commerce Street construction UTSA downtown campus expansion
Partner Coordination Executive Committee Next Meeting – October 19th David Smith, County Manager, Bexar County Lori Houston, Assistant City Manager, City of San Antonio Mike Frisbie, Director, Transportation and Capital Improvements, City of San Antonio Suzanne Scott, General Manager, San Antonio River Authority Next Meeting – October 19th
QUESTIONS & COMMENTS