Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager.

Slides:



Advertisements
Similar presentations
State and Local Implementation Grant Program to the Project Certification Committee Jacque Miller Mike Neitzey October 23, 2014.
Advertisements

Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager Department.
Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager Department.
IMPROVING CONNECTIVITY IN CALIFORNIA K-12 PUBLIC SCHOOLS CENIC 2015 Annual Conference March 10, 2015.
George Boersma Center for Shared Solutions and Technology Partnerships September 18, 2009 Broadband in Michigan Make the Connection!
Los Angeles Regional Interoperable Communications System California Public Safety-Safety Radio Association June 20, 2013 Los Angeles Regional Interoperable.
2010 Broadband Resource & Parameters Map Funding Sources Parameters Awards & Projects NTIA Broadband Technologies Opportunity Program (BTOP) Comprehensive.
I-65 Alabama Clean Corridor Grant Program Retailer Workshops September, 2007 Alabama Department of Economic and Community Affairs.
California Public Library Broadband Project Update Jarrid Keller-California State Library Joe Ford-Joe Ford & Associates Diane Satchwell-SCLC Wayne Walker-Califa.
Made Possible by the Broadband Technology Opportunities Program Funded by the American Recovery and Reinvestment Act of 2009 Event Location Date Title.
North Carolina Team North Carolina Department of Public Safety Office of State CIO North Carolina Department of Commerce Criminal Justice Information Network.
Overview and Next Steps 8/27/2015.
Established in 1974 Service Area of 1,200 Square Miles Population of 440,000 People We Answer 700,000 Calls for Service Each Year 3 rd Largest PSAP in.
COMPLIANCE WITH GRANT IMPLEMENTATION PROCEDURES TxDot Grant Fund Project.
Rural Development Rural Utilities Service Telecommunications Program Christopher L. Collins – General Field Representative Telecommunications Program Rural.
Scott Longhurst CalWA Vice Chairman, Education Committee.
Grant Financial Management U.S. Department of Commerce Officer of the Inspector General 1.
Java Net Project BUS517 Project Management September 12,
PLANNING FOR BROADBAND Sponsored by: Broadband Communities American Planning Association Sept, 2015 Presented by: Kathleen McMahon, AICP
SFY 2015 Capital Improvement Grant Opportunity Cayla Lewis, KAMU CRO.
Documents posted at QRIS 2011 Program Quality Improvement Grant RFP Bidder’s Conferences February & March 2011 Wendy Valentine Director,
FirstNet in North Carolina Allan Sadowski Director of Infrastructure Planning – FirstNetNC Office of Digital Infrastructure.
ESPLOST Update Savannah-Chatham County Public Schools May 2, 2007.
June 3, 2007NTIA PSIC Public Meeting1 How to Avoid Audit Problems: Matching Share and Cost Principles National Telecommunications and Information Administration.
Illinois Century Network Illinois Broadband Opportunity Partnership – East Central Project.
STATE AND LOCAL IMPLEMENTATION GRANT PROGRAM 1 December 6, 2012.
CONDITIONAL GRANT EXPENDITURE 3RD QUARTER Select Committee on Appropriations Parliament of the Republic of South Africa 19 May 2010.
1 Cross-Cutting Issues 5310-JARC-New Freedom U.S. Department of Transportation Federal Transit Administration SAFETEAU-LU Curriculum August 7, 2007.
Title III Application Process Maria Garcia-Morales (717) Title III Program Manager Pennsylvania Department of Education.
Department of Administration Office of the Chief Financial Officer ASTRA SEFA Presentation Roger Basinger April 6, 2016 FY 2016 Schedule of Expenditures.
San Francisco Public Safety Communications Systems Budget and Finance Committee April 17, 2013.
2015 Annual Program Evaluation (APE) Status Update July 14, 2015.
California Career Technical Education Incentive Grant Program (CTEIG)
CIRBN Central Illinois Regional Broadband Network
Prospect MAX.
Grant and Contract Accounting Brown Bag April 25, 2017
Budget and finance Ryan Kahlden June 12, 2017.
Illinois Broadband Opportunity Partnership - Southern
SLIGP Update for NPSTC/IACP Public Safety Broadband Forum
GRANT – RECAPITALIZATION OF LIBRARY SERVICES SEPTEMBER 2009
Kitsap County 2019 Annual Budget
FirstNet and the Alabama First Responder Wireless Commission Updates
DEPARTMENT OF PUBLIC SAFETY – Forensic Laboratory
CSES CA GEN 8.0 UPGRADE Closeout
Department Activities
Billing and Electronic Health Record Upgrade Project
Statewide Interoperable Radio. Communication Internet
San Diego County & Imperial County
Public Education Department
ApprenticeshipNC Regional Collaboration and Expansion Project
Catron County/Reserve E-911 System Upgrade
Department of Information Technology (DoIT)
Espanola/Rio Arriba E-911 System Upgrade
DPS-7/Espanola E-911 System Upgrade
FY 2020 Community Grants Training
Project Certification Committee August 28,2013 Presenters:
FCC Narrowband Update June 24, 2004
Capital Improvement Plans
Porterville College College Learning Council April 6, 2015
Tia Citizens’ review panel November 5, 2018
Budget office overview
Q2 Updates on 2019 Board Priorities
Q2 Updates on 2019 Board Priorities
Obtaining & Retaining Funds for RWS Schemes from Outside Sources
Jamie French and Keesha Thompson
SHARE Special Project SHARE Benefits Optimization
P25 Digital Statewide Public Safety Radio System
Voice Upgrade Project Initiation Certification Request
DEPARTMENT OF PUBLIC SAFETY – Forensic Laboratory
Presentation transcript:

Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Mike Neitzey, Program Manager Department of Information Technology July 25, 2012

Project History SIRCITS grant was awarded in August 2010 under the second round of Broadband Technology Opportunity Program (BTOP) grant solicitations from the Department of Commerce. The purpose of the grant is to complete the transition of the statewide public safety microwave system from analog to digital allowing broadband access to anchor institutions and allowing the state and its partners (through sharing agreements) to support broadband service in un-served, underserved and tribal areas. A last mile component will deploy 700 MHz public safety broadband service.

Organization Reorganized effective April 3, 2012 Mike Neitzey - Program Manager Vince Bradley - DMW Operations Manager Bill McMahon – Logistics & Marketing Mike Romero - Financial Coordinator Irene Sanchez - Financial, CertiClear, POC for Grants online Chad Lee - Business Analyst (Contracts & Scheduling)

Organization

Project Status Completed Environmental Assessments on all sites (have FONSI) Price Agreements for construction of the 59 middle mile sites Contracts in place (with amendments) covering Project Management Design Construction Implementation IV&V Legal Hire Term positions

Budget Status Budget status Budget allocated Total - $55,700,000 Federal BTOP - $38,699,997 State Matching - $5,399,999 State In-Kind Matching $11,600,004 Budget status Submitted a budget amendment moving $4,734,501 from LTE to DMW Total LTE Budget - $4,006,500 LTE equipment and build - $2,952,500 (suspended) Design - $1,054,000

Budget Status Estimated budget expenditures for quarter ending 06/30 $29,869,280 Budget expended As of 06/30 - $18,217,366.08 (cash) + $11,600,004 (in kind match) Total $29,817,370 Over $11.1M spent on design, planning, equipment, and construction during the quarter Area   Budget Expended to date Remaining Encumbered Unallocated DMW $37,384,497.00 $17,275,304.62 $15,003,160.41 $5,106,031.97 LTE $4,006,500.00 $0.00 Other Admin $14,309,003.00 $12,542,065.46 $912,335.57 $854,601.97 Total $55,700,000.00 $29,817,370.08 $15,915,495.98 $9,967,133.94

DMW Status Design - Feasibility analysis, RF design, and Construction design are completed for all Sites Construction started at 22 sites 2 sites are ready for final construction walkthrough an addition 4 to 6 sites will be started in July Installation All radio and network equipment has been ordered Factory Acceptance Testing is tentatively scheduled for late July Installation will begin in August

DMW Timeline

LTE Status NTIA directive Do not purchase any LTE equipment Focus on Site Analysis, Site Selection, Design Submit a revamped budget

Risk & Issues Weather and Fire restrictions play a role in upgrade delays encountered at several remote radio sites. Completion of updated site lease agreements can also cause unexpected delays. No funding for Demolition (now included as part of budget revamp) Purchase/move of LMR equipment (separate $1.5M funding)

Thank You……. Questions?