Presentation by: Tshewang Gyeltshen
The SBD is prepared in line with the PRR 2009 & SBD Large Works General principals of procurement to be applied prescribed in the PRR and SBD Large Works Guidance notes are provided which should be removed while preparing the bidding document. The SBD should be used for procurement up to Nu. 4.0 million
The main objectives for the SBDs are: To have a uniform procurement system throughout the country Simplify procurement of smaller works
Modifications for specific Project needs should be provided only in the Bidding Data Sheet and the Special Conditions of Contract, as amendments to the Instructions to Bidders and the General Conditions of Contract respectively. The notes inside boxes, foot notes as well as others intended as guidance for the Employer, are not part of the text, but rather contain instructions for the user. They should not be incorporated in the Bidding Documents.
Generally provides information on the requirement of bidders to fulfill the project requirements. Scope of tender Corrupt, Fraudulent, Collusive or Coercive Practices Legal status – Required Site Visit
Section 1.Instructions to Bidders (ITB) Section 2.Bidding Data Sheet (BDS) Section 3.Evaluation and Qualification Criteria Section 4.Bidding forms Section 5.General Conditions of Contract (GCC) Section 6.Special Conditions of Contract (SCC) Section 7.Contract Forms Section 8. Bill of Quantities Section 9.Drawings Clarification of Bidding Documents Amendment of Bidding Documents
One Bid per Bidder Bid Preparation Costs Language of Bid Documents comprising the Bid (original and copies should contain the bid form, license and certificate, bid security & priced bill of quantities). Letter of Bid and Schedule: should be prepared as per forms of bid, & qualification information. Alternative Bid Bid Price and Discount
Currencies of Bid and Payment Documents comprising the Technical Proposal (WP) Documents establishing the Qualification of the Bidder Bid Validity Bid Security Format and Signing of Bid (O & C, signed by duly authorized person, initialed)
Sealing and Marking of Bids Bid Submission Deadline Late Bids Modification, Substitution or Withdrawal of Bids Bid Opening
Confidentiality Clarification (arithmetical, not change of price or substance) Bidder: Contacting the Employer Determination of Responsiveness (material deviation, reservation & omission) Non Conformities, Errors and Omissions Evaluation and Comparison of Tenders (no. & words, unit price & line item total) Employers Right to Accept or Reject any or all
Award Criteria Notification of Award complaints
This Section consists of provisions that are specific to each object of procurement and that supplements the information or requirements included in Section 1: Instructions to Bidders.
The criteria that the Employer shall use to evaluate bids and qualify Bidders if the bidding was not preceded by a prequalification exercise and post qualifications are applied. No other methods, criteria and factors shall be used. The Bidder shall provide all the information requested in the forms included in Section 4 (Bidding Forms).
This Section provides the standard format for the Bid Form and Bid Security if required, that are to be submitted by the Bidder. This Section also contains the form of the Notification of Award (Form-2) and the Contract Agreement (Form-3) which, when completed, incorporates any corrections or modifications to the accepted Bidder relating to amendments permitted by the ITB, GCC and SCC. The forms for Performance Security (Form-5) and Advance Payment Security (Form-6), when required, are to be completed by the successful Bidder after Contract award.
Interpretation & Documents forming the Contract the signed Contract Agreement. the letter of Notification of Award. the completed Bid form as submitted by the Bidder. the Special Conditions of Contract. the General Conditions of Contract. Specifications the Drawings
Corrupt, Fraudulent, Collusive or Coercive Practices Governing Language and Law Engineers Decision Delegation Communications and Notices (writing, effective when delivered or effective date, which ever is later) Sub- Contracting Contractors Personnel Welfare of Labourers & Child Labour
Safety, Security and Protection of the Environment Access to the site Documents, Information (contractor shall furnish to engineer all information, schedules, calculations & documents requested by engineer) Property (termination) Insurance (as per SCC before start date, employer may effect) Possession of the Site
Commencement of Works Completion of Works Programme of Works Early Warning Compensation Events Non-Scheduled Items of Works Schedule of Works Payment Certificates
Payments and Currency Retention Liquidated Damages Performance Security Price Adjustment Completion Correction of Defects Taking Over (7 days after completion certificate)
Final Account (certify in 21 days, payment within 30 days) Termination (30 days notice) Payment upon Termination Release from Performance (frustrated by war or uncontrollable situation) Force Majeure (war, terrorism, earthquake) Settlement of Disputes
This Section provides clauses specific to the Special Conditions to a particular Contract. This can be modified according to requirements specific to the contract.
This section contains forms which, once completed, will form part of the Contract. The forms for Performance Security and Advance Payment Security, when required, shall only be completed by the successful Bidder after Contract award Contract Forms Form -1: Notification of Award Form -2: Contract Agreement Form -3: Bank Guarantee for Performance Security Form -4:Bank Guarantee for Advance Payment
The documents forming the Contract shall be interpreted in the following order of priority: The signed Contract Agreement; The letter of Acceptance; The completed Bid form as submitted by the Bidder; The Special Conditions of Contract; The General Conditions of Contract; Specifications The Drawings; and Any other document listed in the SCC as forming part of the Contract..
This Section provides the items and estimated quantities of Works and Related Services to be performed, as well as the detailed Technical Specifications that describe the Works to be procured and must be carefully prepared by a Procuring Agency for each object of procurement.
This Section contains any Drawings that supplement the Schedule of Works including Specifications for the Works and Related Services to be procured.