(on behalf of the LHC team)

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

Sat/Sun 26/27 th March Sat 18h20: Stable beams. Fill #1653. Sun 10h02: Stable beams continued. vdM scans. Length calibrations. 16h59: Beam dump. Delivered.
Thursday 21/4 07:30: End of fill #1727. Beam dumped. ALICE compensator magnet fault. Delivered ~6.7 pb -1 in 7.5 h. 11:30 Stable beam # bunches/beam.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Shortened program (2 days), as decided in LMC. MD program worked very well  all MD’s on plan with ~foreseen beam time. LHC in very good shape with excellent.
LHC Machine Operational Status and Plans LHCC, 22nd September 2010 Steve Myers (On behalf of the LHC team and international collaborators)
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Tuesday 7 th August - morning 07:10 Reinjection after loss of fill 2920 to UFO near ALICE  26 pb -1 in 1h16m; peak lumi 6.4e33 cm -2 s -1 08:10 dump at.
Fabio Follin Delphine Jacquet For the LHC operation team
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday 8.9 External crossing angles:
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Wed :55 Fill 2653 stable beams 1.40e11 ppb, cm-2s-1peak lumi, 11.6 pb-1 total lumi delivered. 09:31 Dumped by collimator interlock:
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC Morning Meeting - G. Arduini
Saturday 09:40 Stable beams #1369 (56 bunch scheme)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Monday 6th August & night
Summary of Week 11: 14 – 21 March
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
LHC commissioning Week 38
Summary of Week 16 G. Arduini, J. Wenninger
Wednesday 8th August & night
LHC Operations overview Week 28 – Getting back
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Friday morning 10:30 Optics measurements and corrections.
Thursday :00: Physics fill from the night shift
Saturday – Morning 7:36 beams dumped
Tuesday 9th November 10:02 Fill beams dumped
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday Fill 1364 (24 bunch) dumped at 07h
Saturday Nov Stop proton operation. Switch back to ions
Thursday – Morning Energy matching at injection with H CODs
Programme for Friday 9 July
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Sat morning Until 12:40: Loss maps at injection
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Summary for LPC (March 7th, Ralph Assmann)
Summary Tuesday h23: Machine closed. Precycle started.
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
Fri :52 Stable beams fill #2536
Saturday 06/11 Triplet R8 tripped during ramp for collision setup.
Wednesday h18: 228b fill lost just before start of ramp.
Another Immortal Fill….
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Saturday 15th May One bunch 1 e11 per beam 09:57: start ramp
31/3/2010 Difficult day… but at the end stable beams.
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Tuesday
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
Daniel, Gianluca and Belen (for the Collimator team)
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

(on behalf of the LHC team) LHC Status Report Steve Myers (on behalf of the LHC team) LHCC 7th July, 2010.

Milestones 30 March: first collisions at 3.5TeV/beam 19 April: order of magnitude increase in luminosity doubling the number of particles/bunch β * from 11 to 2m (4b/beam) L ~2x1028. Beam lifetimes of ~1000 hours 22 May another order of magnitude: 13 bunches in each beam (L~ 3x1029) 26 May: Design intensity bunches were brought into collision at 3.5TeV/beam. 2nd July peak luminosity of 1030cm-2s-1.

IP1&5 lumi vs squeeze Raw (online) lumi plots on 10 apr 2010, during the squeeze to 2m in IP1 and IP5 Factor gained (raw numbers): ~4.5 in Pt5 (after min scan) ~4 in Pt1 Not corrected for lumi decay over the ~5h of squeeze and mini scans atlas

Pushing Number of 2e10 Bunches 2 x 2e10  4 x 2e10 6 x 2e10 per beam 48 hours Allowed doubling the integrated luminosity for 2010 within 48 hours! LHC status 2/15/2019

13 bunches: 3x1029 !! LHC status - week 20&21

Recent progress/Changes Until 9 June, machine time shared between physics and machine studies. Physics with ~2x1010 protons/bunch Machine studies to develop 1x1011 protons per bunch Beam Stored energy is the metre stick: (Machine Protection) Lost particles must end up on collimator or dump Following discussions with the 4 spokespersons and the physics coordinator, a decision was unanimously made on 9 June to concentrate on “Machine studies to develop 1x1011 protons per bunch” until it was operational. This meant postponing physics data taking for around 3 weeks. (Minutes LMC 9th June) 2

Getting to Stable beams at 1.1x1011. Instabilities in Collision at 3.5TeV/beam longitudinal emittance control In the SPS During the ramp in the LHC Transverse damper working Collimators set up Injection set up for new high intensity Beam dump set up for higher intensity Started physics data taking under these conditions on Saturday 26th June (almost a week ahead of estimates)

Ramps for Operations set up for 1011 protons/bunch

26th June: 5x1029 with 3 bunches/beam; 1011/b

6-8x1029cm-2s-1 with 3 bunches per beam;1011/b 29th June, new record

2nd July: Colliding 6 bunches per beam; 1011/b

Integrated Luminosity (Linear Scale)

Look back over week 26 (28/6/10) Goals of the week: Reach peak luminosity of 1030 cm-2 s-1 Improve operational procedures (squeeze and collision sequences) Number of accesses: 6 Number of ramps: 12 Number of fills declared for physics: 7 Fastest turnaround: 4h48 (end stable beams to start stable beams) LHC status 2/15/2019

End of fills Reason for end of 6 physics fills: End of fill study and planned dump: x 2 Electrical glitch: x 2 Instability-induced losses Internal beam dump interlock Beam dumps on 5 ramps not making it into physics: Losses from WS above threshold LSA software problems QPS trip Single collimator not ramping No longitudinal blowup during ramp LHC status 2/15/2019

Friday 2/7/10 Went to 7 bunch scheme: 6 colliding, 1 not colliding Bunch intensity: ~ 9e10 Used separation to limit ALICE luminosity Achieved > 1030 cm-2 s-1 in all experiments (except ALICE) Stable for 16 min, then instabilities (mainly bunch 1) Lost after 34 min due to beam losses LHC status 2/15/2019

New Record Lumi > 1e30 cm-2 s-1 LHC status 2/15/2019

Beam Lifetime Collisions ALICE LHC status 2/15/2019

Beam Intensity LHC status 2/15/2019

Tune: Coherent Excitation LHC status 2/15/2019

Bunch Intensity B1 Not colliding LHC status 2/15/2019

Bunch Intensity B2 Not colliding LHC status 2/15/2019

Bunch Intensity versus Time  Beam-beam effects LHC status 2/15/2019

Bunch Intensity versus Time  Beam-beam effects LHC status 2/15/2019

Saturday 3/7/10 Decided to go towards nominal emittance (3.5 um) for limiting beam-beam effects to nominal values. Standard emittances below 2um at injection. Attempt to blow-up emittance with transverse feedback – really needs additional software Switch off TFB – not effective Blow up emittances in SPS via screens in TT10 3.6/4.4 um on offer TFB back on in LHC Too high losses on transfer line collimators different screens - OK B1H B1V B2H B2V 2.8 2.5 3.1 4.2 02-07-2010 LHC status

Lifetime LHC status 02-07-2010

Sunday 4/7/10 Again emittance blow-up at injection. Long physics fill started at 6h27. Longitudinal losses for B1. End of fill studies: Transverse damper: Too high gain broadens the tune peak (probably need to work on improving signal/noise in the damper)Observed about 8 dB reduction of the vertical beam 2 tune peak; little change in the tune spectra for the other beams/planes. Wire scanner: measurements at 3.5 TeV. LHC status 2/15/2019

Better but not perfect stability… Intensity Luminosity Tuning LHC status 2/15/2019

Losses in All Bunches: Not Beam-Beam LHC status 2/15/2019

Momentum Cleaning Very Active: RF Issue LHC status 2/15/2019

Dump of B1 Uncaptured Beam LHC status 2/15/2019

Tuesday 6 July Injection: TDI studies: In parallel with SPS controlled transverse blowup setting-up used the LHC circulating beams to make some checks of LHC injection protection Made scans of TDI settings with +/-1000 urad angles applied to jaws, for B1, as a function of TCP setting. Data to be fully analysed - scale offsets seen with both angles, unlike B2. Find 0.4 mm for downstream end and 1.1 mm for upstream end. B2 TDI scan repeated with the offsets found in previous measurements: results coherent with earlier findings.

Tuesday 6 July Emittance measurements in TL: Chiarra Bracco SPS Beam blown up to emittance of >3um. Emittance was then measured in the TL by means of the BTV finding the following results: TI 8: EH= 2.6um (SPS: 3um) - EV= 2.8um (SPS: 3um) TI 2: EH= 3.4um (SPS: 3.2um) - EV= 2.2um (SPS: 2.9um) Emittance in vertical plane was blown again in order to have > 3um and new measurements were done in TI 2: TI 2: EH = 3.4um (SPS: 3.5um) - EV = 2.5um (SPS: 3.5um) Vertical plane show controversial results --> measure beam in the LHC and more to be done to understand the results.

Tuesday 6July Transverse blowup studies for LHCINDIV on LHCFAST2 in the SPS - Octupoles are used in combination with an excitation by the damper around the tune frequency (small frequency modulation). Tuned the system for providing emittances of 3 um in H and 3.5 um in V with SPS WS. Transfer lines indicate about 3 um in both planes, both beams.

Tuesday 6July Injection: TDI studies: Brennan Goddard In parallel with SPS controlled transverse blowup setting-up used the LHC circulating beams to make some checks of LHC injection protection Made scans of TDI settings with +/-1000 urad angles applied to jaws, for B1, as a function of TCP setting. Data to be fully analysed - scale offsets seen with both angles, unlike B2. Find 0.4 mm for downstream end and 1.1 mm for upstream end. B2 TDI scan repeated with the offsets found in previous measurements: results coherent with earlier findings.

Tuesday 6July Emittance measurements in TL: Chiarra Bracco SPS Beam blown up to emittance of >3um. Emittance was then measured in the TL by means of the BTV finding the following results: TI 8: EH= 2.6um (SPS: 3um) - EV= 2.8um (SPS: 3um) TI 2: EH= 3.4um (SPS: 3.2um) - EV= 2.2um (SPS: 2.9um) Emittance in vertical plane was blown again in order to have > 3um and new measurements were done in TI 2: TI 2: EH = 3.4um (SPS: 3.5um) - EV = 2.5um (SPS: 3.5um) Vertical plane show controversial results --> measure beam in the LHC and more to be done to understand the results.

Tuesday 6 July Transverse blowup studies for LHCINDIV on LHCFAST2 in the SPS Octupoles are used in combination with an excitation by the damper around the tune frequency (small frequency modulation). Tuned the system for providing emittances of 3 um in H and 3.5 um in V with SPS WS. Transfer lines indicate about 3 um in both planes, both beams.

Integrated Luminosity on 2nd July

Integrated Luminosity on 7th July

Presently More physics for 100 nb-1 goal (ICHEP) From experience so far No fundamental issue for 1e30 lumi (16 min OK). Further equalize beam parameters (emittance, intensity, …) while delivering luminosity. Try to get nominal beam and bunch parameters, including variations. As stability is improved, push up again towards 1e30 lumi. If problems persist, try simpler collision scheme with 2 collisions per IP. Bunches with 2 collisions seem less affected. In addition: Cross calibrate emittance measurement devices. Push transverse damper into full operation in collision, however, possibly needs noise reduction. LHC status 2/15/2019