Wednesday 10/5 Cryo recovery until 18:30

Slides:



Advertisements
Similar presentations
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Advertisements

21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
07:30 – 10:30 Asynchronous dump test with Beam 2. No issue found. FIDEL update. Now chromaticity decay corrected. 12:13 Beam dump due to problem in the.
:30 meetingEBH 1  No beam during the morning:  4:15 – 9: V distributor: Recovery after electrical interruption  access for TI services.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
LHC Status Tue Morning 22-Aug
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Summary of week 40 Machine Coordinators: G. Arduini, M. Lamont
Wednesday September 14th
Luminosity lifetime – fill 2932
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
Monday 11/07: Recovery Plenty of accesses.
MD25 ns - 14/12/2012 G. Arduini, H. Bartosik, G. Iadarola, G. Rumolo
Saturday 30th June - Sunday: Rocky !
02/08/ :35: Lost access chain in point 2 (PX24 PAD)  Dump after ~14.5 hours ~100 nb-1.
LHC Morning Meeting - G. Arduini
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Coordination: G. Arduini, E.B. Holzer
Tue :25 Beams dumped due to RF vacuum interlock
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
Saturday 12:00 Fill 1992 in stable beams.
LHC Morning Meeting - G. Arduini
Monday 6th August & night
Fri 29/7 – Sat 30/7 09:00 End of fill 1990, PC trip RCBXV3.R1 (likely SEU on QPS). Integrated Luminosity: 41 pb-1. Access for MKI2 main switch replacement.
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Summary of Week 16 G. Arduini, J. Wenninger
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Mike Lamont, Jorg Wenninger
Thursday 10th May - morning
Sunday morning Recovering from 400 kV disturbance.
Chromaticity can make a difference…
Tuesday Loss maps in the night:
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
04-05/08/2010 End of physics at ~11:00 after 18.5 hours ~120 nb-1.
LHC Morning Meeting - G. Arduini
Finally.... We had to wait a long time.... We had many problems....
Friday Morning 7:30 injection for fill 2908
Friday AM Some oscillations of the cryo conditions in MSR8 perturbed the setup for injection. RF frequency interlock fixed – required a reset of RF controls.
LHC Morning Meeting - G. Arduini
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Friday 25 bunch fill dumped just before (BLM in 5)
Saturday 3rd November - morning
IP8 aperture measurements (07:30-10:30)
LHC Status Tue Morning 22-Aug
07/08/2010 Fill #1264 dump at 02:14:38.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Saturday :42 stable beams fill 3541
LHC Morning Meeting - G. Arduini
Wednesday 23/2 Thanks CRYO!!!.
Thursday
Wednesday 6th April Injection of 50 ns up to 108 bunches (3 x 36).
Mon 2/4 08:00-13:00: Access for: Experiments Power converters BBQ
Coordination: Eva Barbara Holzer, Mike Lamont
Wednesday h18: 228b fill lost just before start of ramp.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Monday 10th December - morning
Monday 27th August & night
Wednesday morning / afternoon
Saturday 6th October 05:38 STABLE BEAMS # :06 OP dump
Tuesday
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Presentation transcript:

Wednesday 10/5 Cryo recovery until 18:30 17:50 Cryo recovery almost completed. Electrical problem in point 1. Temperature interlock on transformer (18kV/400 V) affecting ATLAS and LHC to minor extent (RD1.LR1) 18:30 Cryo OK 19:45 Trip of ROF and ROD during QPS reset (they were at running at 500 A for test since the morning in preparation of their operation at higher current) 20:20 Electrical network in point 1 OK. 20:20 Trip of ALICE dipole and access for flammable gas detection system in US15.

Wednesday 10/5 21:20 ALICE dipole and gas detection system OK. Origin of the ALICE dipole trip not understood. Prepare for pre-cycle. In the shadow RF control problem on cavity 8B2 requiring piquet intervention and reboot of a control crate 21:52 Trip of RB.A12 when starting pre-cycle. 21:56 Finally starting pre-cycle of all the magnets after intervention of power piquet 22:26 Unable to switch ON RF cavity 1B1. Workaround found for the night  Need follow-up by RF controls expert 23:47 Finally injecting.

Squeeze Very smooth after second iteration on orbit correction. No warning between 2.5 and 2 m. Warning levels reached at 0.8 m because of a UFO at MKI2

Collision WE had increased the TFB gain by a factor 2 and the octupoles strength by 10% (now running close to the maximum current)

Instability

Instability At the moment of the instability separation of ~2.1 s in IP1 and ~1.2 s in IP5 and 3.2 s in IP8 (estimated from luminosities at the moment of the dump). The separation in IP1 and 5 is likely the effect of the orbit correction during the squeeze.

Instability Damper pick-up signals Thanks to W. Höfle!!

Instability on B1 H Consistent with observation of losses on several bunches of B1 and B2 from the dump of the previous night. G. Papotti

Actions Went back to low number of bunches but with 50 ns spacing to get as much as possible same orbit Luminosity scan to determine collision offsets and correct them  incorporated for next fill IP1 - H IP5 - V IP5 - H

Ongoing Fill with 1092 bunches and moderate bunch population 1.1-1.2x1011 p to verify the behaviour

Issues Frequent RF control issues requiring piquet intervention Access console: blue screen error BLM sanity check failing (C. Zamantas): The connectivity check was failing due to one SEM detector in SR7.C, i.e. the BLMES.06R7.B2I10_TCSG.A6R7.B2 Since none of the SEMs are part of the protection mechanism have increased the upper limit (from 856  to 1000 bits) to allow it to pass the check. The monitor is connected and responsive to the modulation. Though, it’s response pattern has slightly changed indicating some kind of degradation. Will add it in the list for exchange in the next TS.