MICO Meeting Magnetic Field Shielding Issues 11 th July 2012 Mike Courthold 1.

Slides:



Advertisements
Similar presentations
Slide 1 Insert your own content. Slide 2 Insert your own content.
Advertisements

1 RF Workshop 16 th & 17 th April 2012 Design Layout Alan Grant, STFC.
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
MICE Hall – South Mezzanine Jason Tarrant - STFC l Contents »Device checks with current South Mezzanine »South Mezzanine change summary »Conclusion.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
1 Infrastructure at RAL Iouri Ivaniouchenkov, RAL MICE Collaboration CERN, 29 March 2003.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Major items from field affected component list MICE Magnetic shielding review C.Macwaters 23/9/13.
MICE CM30 Magnetic Shielding Update Mike Courthold 6 th July
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
Shielding the Weiner PSU 7 May 2013 Kiril Marinov ASTeC, MaRS, DL 1.
MICE CM30 Magnetic Shielding Update Mike Courthold 6 th July
MICE MICE Magnet Modelling - Presentation to the Daresbury Magnetics Group Daresbury Laboratory 31 st January 2013 P J Smith University of Sheffield.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MICE Integration Engineering Jason Tarrant - STFC l Contents »South Mezzanine change summary »Integration Envelope Model »A/C Move »Maus Geometry »AFC.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
MICE CM32 8 th February 2012 Magnet Group Report Vicky Bayliss Victoria Blackmore John Cobb Mike Courthold Roy Preece Mike Zisman 1.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
MICE Specification of the Stray Field Issue and the MICE Hall Model P J Smith 23 rd September 2013.
MICE Integration Engineering Jason Tarrant - STFC l Contents »Device Interfaces – General »AFC »Spectrometer Solenoids »RFCC »EMR / KL »South Mezzanine.
1 Layout and Installation MICE Collaboration Meeting, RAL, October 27-29, 2004 Elwyn Baynham, Tom Bradshaw, Paul Drumm, Matthew Hills, Yury Ivanyushenkov,
Some Thoughts on Magnetic Measurements for MICE Michael A. Green Lawrence Berkeley Laboratory Berkeley CA 94720, USA.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Global Magnet Systems including Field Mapping and Infrastructure Vacuum System MICE Project Board 8 th March 2012 M Courthold – RAL R Preece – RAL P Hanlet.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l History l Requirements l Environment l Design l Structural Integrity l Preparation l.
PRY Implementation - Contents l Fit with Experimental Devices (& services connections) l Fit with Tracker Cryo l Fit with Floor & Trench l Fit with Mezzanine.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
MICE CM31 Magnetic Shielding Update Mike Courthold 1.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
PRY Base - Contents l PRY Support/Base/Platform in the MICE Hall l Requirements l Environment l Design l Structural Integrity l Preparation l Installation.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
Andrew Moss ASTeC TIARA Mid term meeting 12 th 14 th June 2012 CIEMAT ICTF Progress on the MICE RF System.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services.
Magnetic Shielding for Tracker components Craig Macwaters – STFC MICE CM33 Glasgow.
MICE CM32 25 th February 2012 Magnet Group Report Vicky Bayliss Victoria Blackmore John Cobb Mike Courthold Roy Preece Mike Zisman 1.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 Implementation at RAL Iouri Ivaniouchenkov on behalf of Elwyn Baynham, Tom Bradshaw, Tony Jones, Jim Rochford Engineering Department, RAL MICE Collaboration.
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
Shielding the turbomolecular pump and the vacuum gauge 11 June 2013 Kiril Marinov ASTeC, MaRS, DL 1.
1 MICE CM29 Engineering Summary Cooling channel moving platforms – Norbert Floor Beams and plates – Andy L Magnetic modelling – Mike RF Engineering – Andy.
S A Griffiths CM42 June 2015 Electrical & Control.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Outcome of the Review and Response to Recommendations
Introduction Jason Tarrant – Integration Engineering Step IV Removal
Interaction Region Design Options e+e- Factories Workshop
Presentation transcript:

MICO Meeting Magnetic Field Shielding Issues 11 th July 2012 Mike Courthold 1

Background to Magnetic Field Shielding Issues MICE Cooling Channel magnets were designed without return yokes. Consequently, the fringe fields have the potential to affect much of the MICE Hall and beyond. The Magnetic-Shielding Walls were designed to protect the public beyond the MICE Hall, and in the MICE & ISIS Control Rooms, from fields in excess of 5 Gauss. An arbitrary maximum of 5 Gauss was also set for the neighbouring ISIS Linac Hall The Magnetic-Shielding Walls do nothing to protect equipment within the MICE Hall, and in fact distort the field locally in ways that create more problems than they solve Once the fields in air for all MICE Steps were determined, attention focussed on: Identifying all magnetically-sensitive components in the Cooling Channel region Determining for each identified area or item: Whether local shielding would be required The type and amount of shielding required (eg US1010 iron and/or Mumetal) 2

Background to Magnetic Field Shielding Issues (cntd) The TRD Magnetic-Shielding model was used to predict the magnetic field in air, and the potential shielding requirements in specific areas and to specific equipment The model was adapted to analyse the effect of inserting significant ferrous objects into the Cooling Channel region, to predict: local distortions of magnetic fields resultant forces on inserted objects 3 Predicted fields without ferrous content Predicted fields with ferrous content

Background to Magnetic Field Shielding Issues (cntd) Previously it was assumed that shielding various magnetically-sensitive items would simply be a case of taking the prediction for the field in air, and employing a suitably- thick Mumetal screen. However, when items such as air-conditioning units and cryocooler compressors were modelled, it became apparent that the magnetic field was massively enhanced on the surface of such steel cabinets from typically 300 Gauss (30 mT) to 1.7 Tesla In hindsight, this effect should have been expected, but was overlooked by those performing the various analysis tasks, and also by various peer reviews, over more than seven years The oversight had at least been identified before the arrival of any Cooling Channel magnets, and work began in earnest to quantify the problem and find engineering solutions, ideally for Steps IV to VI, but at least for Step IV. 4

Magnetic Field Shielding New & Ongoing Activities Find engineering solutions for Step IV 15 compressors involved Control & monitoring racks for the Cooling Channel magnets Other electrical racks on the North Mezzanine extension Recommend options for moving or replacing magnetically-sensitive components and equipment, rather than shielding Consider solutions for Step VI Obtain addition support and effort by employing a consultant Understand the full extent of the shielding issues, by: Gathering information on all ferrous objects in the MICE Hall Identifying all magnetically-sensitive items in the MICE Hall, including any items whose status is unknown Gathering all available literature from manufacturers & suppliers re sensitivity/resistance of individual components (eg relays & transformers) and equipment (eg control & monitoring racks, and compressors) 5

Step VI: Compressors 6

Step VI: Compressors (cntd) Looked at the proposed location for the compressors in Step VI along the base of the south shielding wall. On the preceding slide is an image of the model used, which includes two shielding walls, with compressors shielded in stacks two high. Initially looked at the fields seen by the compressor when shielded by a double thickness of shielding material – 1mm Mumetal and 5mm of US1010 iron. Assuming that the compressors can be subjected to no more than a 50 Gauss field, only the compressors in the far west positions would survive during Step IV. Then steadily increased the shielding levels to find that the amount of shielding that would be required to shield compressors in these locations was a multi-layer comprising 80mm thick US1010 plus 10mm Mumetal. Clearly this is not feasible, and new locations will need to be found in the hall for the compressors in Step VI. Suggested locations include directly behind the Beam-Stop, or stacked against the West and North-East walls. 7

Step IV: Compressors 8

Step IV: Compressors (cntd) Looking at the beamline for Step IV, the magnets are all located at the upstream end of the final beamline, so it is possible to use the compressor locations shown on the preceding slide, provided they are shielded with 5mm US1010 iron plus 1mm Mumetal; which is good because work has already been undertaken to install power and water services to these locations. Both Vector Fields and Oerlikon-Leybold recommended Magnetic Shields Ltd for shielding solutions. Various discussions have since taken place with Steve Locker of Magnetic Shields, who have designed a prototype shielding solution for a single compressor. The prototype shield has been ordered, and the plan is to test the shield with a compressor with the AFC magnet in building R9 (once acceptance tests are complete). 9

Step IV: Magnet Control Racks Simplified solution shows it is possible to shield in 5mm US1010 iron and 5mm Mu-metal, if Aluminium racks are used. In reality, it will be necessary to provide protected access (labyrinth or air-lock style), to allow access during magnet operation for diagnostics. 10 This implies serious modifications to the positions of magnet control racks, their services and the entrance to the trench.

Step IV: Electrical Racks on North Mezzanine racks located on the north mezzanine -5mm US1010 iron and 5mm mu- metal, if Aluminium racks are used. -Estimated weight 3-5 tonnes – requires major modifications to the north mezzanine

Step IV Solutions In summary, for Step IV it is possible in general to shield items – although finding solutions for each magnetically sensitive component is time consuming, and none of the options considered so far are trivial to implement. Moving items further away from the Cooling Channel magnets is an obvious option, but not feasible in every case, for electrical and/or engineering and/or space reasons For the compressors, the options for Step IV are to: shield them with a combination of 5mm US10101 iron plus 1mm Mumetal, and place them all in the downstream locations; Place the compressors against the West and/or North-East walls Place them behind the Beam-Stop For the controls & monitoring racks, the options are to: Move those that can be moved to safer locations, including: Behind the North Magnetic-Shielding Wall (where RF amplifiers will eventually be located for Steps V & VI) Next to the West wall Next to the North-East wall on the upper floor Locally shield those racks that cannot be moved – eg the Tracker Cryostat For the vacuum equipment, the turbo-pumps can be locally shielded (which avoids issues with long vacuum pipes), suitable gauge heads can be selected and screened, and he backing pumps can be located in a low fringe field 12

Step VI Solutions 13 Modelling shows that it is not reasonably possible to shield the compressors or electrical racks in their currently proposed locations. We need to consider: -Compressors moved behind the beam stop, which would still require shielding, or against the west wall -Electrical racks either heavily-shielded or moved elsewhere -What else?

Step VI Solutions Some thought has been given to Step V1: Initially the intention was to find solutions for both Step IV and Step VI, to avoid having to repeat work later. However, initial analysis showed that this would be challenging, for the following reasons: For example, up to 80mm US1010 ion and 10mm Mumetal is required to shield a compressor in its current position. Also, given the space constraints in the hall, space required for additional shielding will need to be considered. For example, it was intended that there would be seven magnet control racks under the north mezzanine, but with shielding there would only be enough space for five. Consequently, MICE Project Board decided that the focus should be on finding a Step IV solution Consequentially, it will be necessary to find new shielding solutions and/or relocate items for Step VI 14

Information Gathering What we know we need to consider: EMR control rack Magnet control racks Vacuum system control racks Power supplies for conventional magnets Tracker system Hydrogen system Vacuum system PPS system Etc... Often quite small items, but critical to the safe operation of MICE, eg: Electro-magnetic actuators Pnematic/control-valve limit switches (Hall-Effect) PPS relays Fire alarms. 15

Conclusions 16 Magnetic Field distortion Previous analysis and reports overlooked massive distortion in magnetic field profile caused by presence of ferrous objects - including the magnetic shielding itself EG: Magnetic field in air in compressor locations ~ 30mT, which becomes 1.7T when ferrous content of cabinet and shielding taken into account. What about a partial yoke Forced to reconsider possibility of partial yoke around Cooling Channel magnets Substantial issues re beam physics, forces, weight, and access for services and maintenance, etc. Focusing on a Step IV solution The plan of action relies on a combination of moving items as much as possible, and then shielding locally, which will still require considerable engineering compromises & effort to achieve, as well as substantial additional analysis