LERF Readiness Review Kevin Jordan

Slides:



Advertisements
Similar presentations
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
Advertisements

Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
EPICS on TPS RF System Yu-Hang Lin Radio Frequency Group NSRRC.
RF Unit Test Facility at NML & CM1 Test Plan Bob Kephart Fermilab IWLC-10 October 20, 2010.
Possible Assembly and Test of the Crab cryomodule in SM18 at CERN P. Maesen LHC Crab Cav meeting, 17 Sep’ 09 LHC-CC09Cryomodule Assembly & Test Stand.
Internal Cryomodule Instrumentation Sensors, Actuators, Heaters, and Wiring ERL Main Linac Cryomodule 9/5/2012 Peter Quigley Internal Design Review.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Stephen Schuh Vacuum Controls SCR and 16 November 2005 Vacuum Controls System Concept Review and Preliminary Design Review.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Test plan for SPL short cryomodule O. Brunner, W. Weingarten WW 1SPL cryo-module meeting 19 October 2010.
Managed by UT-Battelle for the Department of Energy SCL Vacuum Control System Upgrade Derrick Williams
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
26 April, 2016 LCLS II Cryomodules and Cryoplant, Joe Preble LCLS-II Overview JLAB Organization for LCLS-II JLAB responsibilities & Schedule and Status.
Status of Vertical Test Stand at RRCAT P Shrivastava, P Mohania,D.Baxy, Vikas Rajput S C Joshi, S Raghavendra,S K Suhane RRCAT, Indore November 26, 2012.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Evolution of Field Emission Characteristics Selected C100 Cryomodules Michael Drury.
ELENA installation progress F. Butin / ELENA collaboration.
LCLS-II Prototype Cryomodule Darryl Orris 21 January 2015 Final Design Review: Instrumentation.
S A Griffiths CM42 June 2015 Electrical & Control.
SRF Operating Experience at JLab
Introduction Six-Month Follow-Up on Action Items of Feb 2016 CEBAF Field Emitter Workshop Rongli Geng September 12, 2016.
LCLS-II Technical Requirements
Cryoplant Controls Installation
RF Systems and Controls for the LERF CM Tests
S1G Experiment Schedule Plan
Cryogenic Plant Electrical and Controls
LCLS-II For LCLS-II Cryomodule Testing at JLab
Preliminary Review of LERF as Cryomodule Testing Facility for LCLS-II
Field Emission Minimization for LCLS-II
Cryomodule test stand at ESS site
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
ATF2 Magnet Power Supplies
Update on HW commissioning
Hongyu Bai LCLS-II 2 K Cold Box FDR March 9, 2017
XFEL Vacuum System Commissioning
Jefferson Lab Low Level RF Controls
SC1R Cold Box PDR Controls
C75 Commissioning Michael Drury SRF Operations Support
Upgraded Injector Test Facility
Scope, Requirements Deliverables & Schedule
Baseline Change Request
LERF Readiness Review: Charge
LCLS Cryomodule Testing in the LERF- OSP
SNS PPU Cryomodule Instrumentation
Cryomodule Assembly Plan
Hall C SHMS & Configuration Status
Report on ATF2 Third Project Meeting ATF2 Magnet Movers ATF2 Q-BPM Electronics Is SLAC ILC Instrumentation Group a good name?
LERF Readiness Review Ed Daly / Matt Marchlik
The spoke CM tests at FREIA
Hall C SHMS & Configuration Status
Status of the ESS High Power RF Systems
RF introduction Anders Sunesson RF group leader
Cryomodule Test Schedule
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
LCLS Control System Personnel Linac & BC2 Controls progress
SNS PPU Cryomodule Instrumentation
LERF CM Supplemental Testing & Change Management
LCLS-II Operations in LERF
Presentation transcript:

LERF Readiness Review Kevin Jordan LERF Cryomodule Test Facility Overview November 12 - 13, 2018

Outline Scope of the LCLS-II conversion Work planning Top level schedule Safety systems & radiation shielding Software, controls & network infrastructure Solid State Amps, LLRF & all that waveguide Cryomodule & tunnel connections Cryogenic connections Summary

Scope of the LCLS-II Conversion Project Modify LERF to enable LCLS-II CM testing Take advantage of Safety System interlocks / shielded vault Install computer services; firewalled network & servers EPICS Software development & test bed for SLAC team PCs with PLC licenses to remotely develop cryo & vacuum PLC controls Install16 SSAs & reroute existing waveguide to LCLS-II modules 1400 feet of new waveguide Install, test & commission LCLS-II production racks (SLAC staff) LLRF, Cryo Controls, SC Magnets (w/Quench protection) & Vacuum Enable testing and running of 2 CMs together, this simulates Linac 1 Operate 2 cryo modules with a similar cryo system rather than CTF Gain invaluable experience cooling down 2 CMs at SLAC tunnel grade

Work Planning Weekly schedule meetings are held in LERF breakroom Work planning for the upcoming week discussed Interferences discussed Long range schedule is posted on white board http://lerfboard.acc.jlab.org/board1.html http://lerfboard.acc.jlab.org/board2.html ATLis is used as work control document https://wiki.jlab.org/lerf/index.php/ATLis SAD is also used Controlled by Steve Suhring SOP for testing, travelers, & procedures Controlled by Mike Drury

Top Level Schedule The test schedule is drive by various scheduled shut downs of the physics program Caveats CHL requires 200 watts + 10%; Either the LERF ¼ CM & FL02 are cold & full and/or the 2 LCLS-II CMs are cold and full The CHL 1 has to be at 4K for LCLS-II U-Tube operations The CHL 1 will be taken to 4 K in Dec. to manage Helium inventory for the first cool down in January. By going to 4 K early there is less of a time constraint for U-Tube operations First cool down is either complete or aborted by January 15 to enable hot check out of CEBAF prior to the February physics run The test cycle is nominally 2 months 1St Break – January 2 to 15, that is followed by 2 weeks of hot check out & start of Physics Feb. 1 2nd Break – April 15 to May 10 3rd Break – August 15 to Sept. 15

Safety System & Shielding Shielding assessment done for the vault with 2 LCLS-II modules, all 16 cavities at full gradient All 26 blocks will be in place for any testing Originally I hoped not to install & remove all 26 shield blocks each time but I gave up on that – it is not a cost driver with the crane already there Rad Group Doc: RCD-DEP-18#002 dated Jan 2018 https://wiki.jlab.org/lerf/images/2/2b/LERF_TRUCK_ENTRANCE_SHIELDING.pdf PSS interlocks are identical to the CMTF in the test lab System duplicated from existing drawing to avoid new design effort Waveguides are pressurized (few psi) for standard interlocks PSS has already been certified, except for waveguide pressure

Software & Controls Servers & network are up & on-line – Wesley Moore’s talk Two PCs are online with Siemens PLC licences Cryo-Con RTD controllers are up and running These are for the Cryo-can & non LCLS-II instrumentation New flow meters will be tied into cryo control system JT electric valve controls are re-assigned channels & cables are relocated to new locations (RT03, SH04, JT03) New high level aps for testing will be developed by JLab This is an opportunity for SLAC software development This will greatly speed the commissioning @SLAC Initial cooldown will be manually – Matt Marchlik’s talk Cavity Testing – Mike Drury’s talk

SSAs & Gallery Waveguide Layout Entire system exists as a 3-D model in Solid Works Total project requires new waveguide ~380 pieces, ~ 1,400 feet + LCW cooling of circulator loads & SSAs Production LCLS-II SSAs, couplers, circulators, & loads are used All waveguide pieces fit (first time!)

Solid State Amps ALL 16 SSAs have been run to full power All waveguide couplers have been calibrated Personnel Safety System (PSS) connections are complete

Raised Floor in Gallery & Cable Tray The RF cable routing will be through the penetrations and along the gallery floor, protected by the raised floor This image is before the heliax cables have been installed, some sections of floor grating needed to be removed All cable & connectors are delivered Cryo rack cable installation ~99% complete (88 cables), all of those have been terminated in racks Tunnel terminations > 90 % complete

LLRF Controls Fully functional LCLSII LLRF control racks (4) are powered up & remotely accessible from SLAC Precision receiver chassis RF Station Resonance/Interlock chassis LO Chassis Power supply EPICS Interface LLRF Rack

Master Reference & LO Distribution in Progress 1300 MHz Reference: Rohde & Schwarz Signal Generator 1320 MHz LO: Derived from 10 MHz and 1300 MHz

Tunnel Waveguide Layout Installation is complete in the gallery & tunnel

Tunnel Waveguide Layout Installation complete

Cryogenic Connections to Transferline Cryo can was late 3 months, it was delivered on Nov. 1, placed Nov. 5, and now in process of having field fit joints tied in & instrumentation checked out See Matt’s talk

Process & Instrumentation Diagram P&ID JL0043630 In approval process Zone 00 Zone 01 Zone 02 Zone 03 CM 1 CM 2

LCLS-II Cryogenic Controls & Interfaces JLab cryo staff controls cryo-can & JT valves for cooldown SLAC has access to CM JT valves & heater controls Two fully assembled sets of cryo-control racks are operational Tunnel terminations done by Jlab staff Rack ‘field’ terminations have been done by SLAC PLCs for cryo control are on line and can be remotely programed from SLAC Cryo racks will provide UPS power to the LLRF racks for backing out tuners during power failure SLAC staff encouraged to be present for cooldown

LCLS-II Cryogenic Controls Racks (1 of 2 sets)

Vacuum Controls & Interfaces Controllers for ion pumps and gauging from SLAC are on-site Gauges are part of CM assembly A LCLS-II vacuum pump cart will be shipped soon as a test of microphonics Roughing pump, turbo, pirani, cold cathode, & PLC controller Jlab provided pump cart will be initially used if SLAC cart is late EPICS control interface to pump cart, gauges & PLC Interlocks to LLRF

Other Instrumentation Faraday cup on both ends Decarad monitors Fermi supplied Total Loss Monitor (TLM) Other radiation detectors Fox - ? Chipmunk - ? Scarecrow - ? TLDs - ?

ES&H issues All radiation shielding blocks will be used for first test Dosimetry will be used between first & second layer to get a total dose Operational Safety Procedure is being finalized Mini review held for running SSAs into shorts ODH Assessment done, needs to be signed Less LHe volume than used in the past Pressure system design authority is Matt Marchlik Egress has been reviewed by Facilities https://wiki.jlab.org/lerf/index.php/Facilities_Documents

Remaining work LLRF There are 4 LLRF racks, one for each 4 SSAs Field wiring downstairs complete – need check out Upstairs ~ 3 Person-Days to finish SSA CM 1; 1 – 4 Complete SSA CM 1; 5 - 8 Complete SSA CM 2; 1 – 4 Need RTD & Stepper SSA CM 2; 5 - 8 Need Stepper

Remaining work JLab Cryo Field fit joints from cryo-can to transferline in progress Complete leak check of system Diode terminations; cables are in place (5 out of 6) 34 diodes need to be terminated – Terminal block + 6 pcs x 32 pins All channels are in EPICS with proper nomenclature There are 3 Coriolis flow meters 3 pcs x 9 wires need terminated in cryo-can + 3 cables to ethernet controllers mounted in the tunnel Diode Terminations Resistors are to simulate T

Remaining work JLab Cryo 3 EV; JT type – reusing existing channels rerouting existing cables One each EV and other flowmeter need to be tied into EPICS Need control screens for ease of operation Installation of Hot Wire Anemometer Complete leak check of system Welding and leak checking – 2 person weeks Hardware connections + software – 4 person weeks

Remaining work Mics. Terminate SC magnet voltage taps in rack – 1 day Connect and test Fluxgate Magnetometers – couple days Compact Rio is setup, it with controllers will be on a cart & used only for degaussing Check out the Deca Rad system – 2 days Finish up vacuum control rack and HV cables – 1 week Finish bridging section clean room

Summary Work control documents are same as CEBAF All waveguide delivered, installation complete Cryo Can delivered and being connected Last piece of the puzzle File & application servers operational, build complete All of the cable and connectors have been delivered & installed Cryo cables terminated in racks RF cables installed and calibrated A few cables including cryo-can instrumentation remaining LLRF & SSA commissioning is on-going Positioned well for cooldown in January Few man-weeks of work remaining for Jlab cryo-can controls SRF support for CM connection to cryo-can and inter-module beam tube