Machine Tolerances in Cleaning Insertions

Slides:



Advertisements
Similar presentations
IWBS04 / J. Wenninger1 Orbit Stabilization at the Large Hadron Collider (LHC) Introduction to the LHC Stabilization issues and requirements Expected.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Chamonix 03 / Presentation 5.5 / J. Wenninger1 Orbit control for machine operation and protection Orbit control requirements Feedback performance.
The ATS MD part III (Achromatic Telescopic Squeezing scheme) Participants: Any (active) volunteers Goal: 1)MD1 (S. Fartoukh & R. Assmann  10h): “Pre-squeeze’’
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
14/1/2011 LHC Lumi days - J. Wenninger 1 IP positions and angles, knowledge and correction Acknowledgments: W. White, E. Calvo J. Wenninger BE-OP-LHC.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Collimation Aspects for Crab Cavities? R. Assmann, CERN Thanks to Daniel Wollmann for presenting this talk on my behalf (criticism and complaints please.
Threading / LTC/ JW1 How difficult is threading at the LHC ? When MADX meets the control system … J. Wenninger AB-OP &
Week 13: R. Assmann, J. Wenninger
Luminosity monitor and LHC operation
Alignment and beam-based correction
LHC Wire Scanner Calibration
Ion Commissioning: Thursday & Friday
J. Wenninger AB-OP-SPS for the non-dormant AB feedback team,
Wednesday 8.9 External crossing angles:
1st LHC MD Period Started
Impact of running with LHCf and early Totem 90 m optics
LHC Commissioning with Beam
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Some aspects on: LHC Global Aperture Measurements Ralph J
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Results of the LHC Prototype Chromaticity Measurement
Instrumentation brain-storming
LHC Emittance Measurements and Preservation
Overview on LHC Machine Failure Scenarios
Real-time orbit the LHC
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
LHC Morning Meeting - G. Arduini
Thursday morning – optics correction
Orbit feedback for collimation
Summary of Week 13 G. Arduini, B. Holzer
Tuesday 20 March 2012.
Week 35 – Technical Stop and Restart
Summary of Week 26 Main aims: G. Arduini, B. Holzer, M. Lamont
Planning at 5 o’clock meeting Friday
Thursday :00: Physics fill from the night shift
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Saturday 7th May Sat – Sun night
Collimation margins and *
Orbit Feedback / Chamonix 03 / J. Wenninger
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
450 GeV Preliminary Commissioning: Measurement Programme
Machine plans - CMS startup workshop
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Collimators: Operations - Baseline Assumptions
Machine protection and closed orbit
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
From commissioning to full performance…
MD Planning Fri – Sat (1. – 2.7.)
Monday :00 – 15:00 : Stable beams 15:30 : Recover…
Summary for LPC (March 7th, Ralph Assmann)
Monday :15 fill 3523 dumped by BPMs IP6
Saturday 12 March Morning: problem on RSD1.A12B2 – flow rate problem on the cooling water for the converter. 14:00: Loss map -500 Hz (positive energy offset)
LHC Morning Meeting - G. Arduini
Summary Tuesday h23: Machine closed. Precycle started.
Beam dynamics requirements on MQT
Thursday 22nd March 00:20 – 02:40 on longer squeeze function, orbit and chroma correction at 4 TeV 2:40 – 5:30 second cycle with long squeeze 5:46 – 7:00.
LHC Morning Meeting - G. Arduini
Another Immortal Fill….
Saturday 15th May One bunch 1 e11 per beam 09:57: start ramp
LHC beam orbit and collision position determination & control – performance and issues, prospects for Run 3 Orbit in collision - Luminosity WS - J. Wenninger.
Feedbacks & Stabilization Getting them going
Wednesday :35 : Beam lost because of trip of RCBXH3.L1
What systems request a beam dump? And when do we need them?
Presentation transcript:

Machine Tolerances in Cleaning Insertions J. Wenninger AB-OP SPS Beam Operation Tolerances Orbit stabilization Beam optics 30.06.2004 Collimation Review / J. Wenninger

Collimation Review / J. Wenninger A world of collimators Operation without collimators (‘All OUT’) is only possible at the LHC with very low intensity and around injection : One pilot-ish bunch (5 ×109 p)  no quench expected One nominal bunch (1011 p)  no damage, but risk of quench At high energy use of collimators will be mandatory, but coarse settings are acceptable for ‘low’ intensity … and during the initial phases. This is of course independent of the collimator design issue. 30.06.2004 Collimation Review / J. Wenninger

Getting started at injection The available machine aperture at injection is 8.5s with a margin of  4 mm closed orbit + 20% b-beat + mom. offset + mech. tolerances Protection devices for injection will be set  7s  primary collimators will be set to 5.5-6s Both absolute orbit excursions and b-beat must be under control, or else the collimator settings of 5-6 s must be tightened even more ! 30.06.2004 Collimation Review / J. Wenninger

Constraints on machine changes The following machines changes (wrt a reference situation) lead to a 50% degradation of the nominal betatron cleaning efficiency : 8% b-beating 0.6 s orbit shift 50 mrad angle change Collimation inefficiency versus position error Tolerances are cleary tigher if there is a combined change of b-beat, orbit … as is often the case !  may have to take a factor 2 off from those numbers ! Note : the simulations were made for an older ‘version’ (2002) of the cleaning system ! 30.06.2004 Collimation Review / J. Wenninger

Orbit tolerances for the LHC With time demands for orbit stabilization have poped up everywhere around the LHC. A more or less exhaustive list : Cleaning section IR3/7 <  0.3 s 70 mm TCDQ absorber in IR6 <  0.5 s 200 mm Q-meter and transverse damper in IR4  200 mm Injection points IR2/IR8 200 mm Injection protection devices IR2/IR8 <  0.5 s  500 mm (?) Stabilization for collisions TOTEM experiment IR5 20 mm (!!!) Protection – global orbit ~ 500 mm rms e-cloud(*) – global orbit <1000 mm rms ? 7 TeV Note the expected BPM systematic errors : intensity (pilot  nominal bunch) 100 mm bunch length changes (injection – flat top) 100 mm ? Presently ‘studied’ at the SPS… (*) : not formally expressed – but to be expected from SPS experience… 30.06.2004 Collimation Review / J. Wenninger

Collimation Review / J. Wenninger Expected orbit drifts Phase Total drift / rms Time scale Comment Injection 2 mm 15 min Decay Start ramp 2 mm 20 sec Snapback Ramp few mm 20 min SPS/LEP experience Squeeze 2-20 mm few min Depends on orbit quality in insertions Collisions few mm hours LEP orbit Some drifts (ramp, squeeze) are probably sufficiently reproducible to use feed-forward from one fill to the next for the bulk part. Most drifts become critical on time scales > 1-10 seconds. 30.06.2004 Collimation Review / J. Wenninger

Ground motion at LEP  If the LHC moves like LEP we are safe. f  0.1 Hz : no problem expected… Average ±1s LEP rms orbit drifts in 1998 for 390 fills, normalized to b=1 m f > 0.1 Hz : Amplitudes  O(few mm)  should be OK  If the LHC moves like LEP we are safe. Note : The large time constants of the orbit corrector power converter (10-200 s) and the available voltage limit useful orbit corrections to f  1 Hz (at 7 TeV) ! 30.06.2004 Collimation Review / J. Wenninger

Orbit feedback overview A global real-time orbit stabilization + local ‘refinements’ is considered to satisfy all the demands : Sampling rate 5 – 25 Hz (design is 10 Hz) for corrections at up to 0.2-1 Hz. Upper limit is 50 Hz due to power converter controls. Data transmission from  70 front-end computers (1000 readings/plane) to central feedback over switched Gigabit Ethernet (LHC technical network). Central processing on Linux systems (multi-processor) with (almost) hard real-time capabilities. A total processing delay < 40 ms is feasible. Fan-out of corrections to PC front-end systems (500 correctors/plane). If there are performance problems  local loops in cleaning insertions ! 30.06.2004 Collimation Review / J. Wenninger

Collimation Review / J. Wenninger b-beating With only ~ 8% b-beating change tolerated, a good correction of the optics is required at all stages Ramp (decay & snapback seem OK). Squeeze Dynamic squeeze in collisions for LHCb. Fancy knobies (arrrgh !!). … There are lot’s of distributed sources of b-beat Spool-piece corrector alignement. Orbit in sextupoles. Quadrupole calibrations (nominal accuracy ±2 x 10-4  5% b-beat change during squeeze, Ok but near the limit…).  work ahead ! 30.06.2004 Collimation Review / J. Wenninger

b-beating measurement Careful optics adjustments will have to be made : K-modulation : available (as far as I know !) in cleaning IRs - control of hysteresis effects ? At 7 TeV the quadrupoles will not be far from saturation. - good measurements require continuous / PLL Q measurements. Not expected to be available before some months after startup. Kicks / AC dipoles combined with multi-turn BPM data : - beware of oscillation amplitude limits ! This issue clearly deserves a closer look…. 30.06.2004 Collimation Review / J. Wenninger

On the road to a nominal LHC… Beam cleaning offers new challenges for retired LEP operation cowboys : lot’s of tuning ahead – at least as far as the tight tolerance allow it ! The relatively tight orbit control in the cleaning sections is manageable. Tight optics control is much more tricky. Deserves further studies and … lot’s of work on the beam ! 30.06.2004 Collimation Review / J. Wenninger