Discussion on TE/CRG equipment at H4IRRAD Marco Pezzetti (A. Tovar – B. Ivens / Support CE for cryo LHC) & TE-CRG-OA – TE-CRG-CI 1TECRGCE M.PEZZETTI
Discussion on TE/CRG equipment at H4IRRAD: - SEU Summary 2011/ AMB introduction - SEU signature protocol on AMB - Discussion on possible November 2012 test at H4IRRAD 2TECRGCE M.PEZZETTI
3
SEU: summary Xmas, not bad! Courtesy A. Suraci TE-CRG-OA QURCB_P8: 3x QURA_P4: 1x QUI_P4 : 1x QURCB_P6: 1x
Xmas, not bad! Relocation during Xmas 2011 P8: QURCB electrical cabinets & CPU of QURA P6: CPUs of: QUI, QURA, QURCA & QURCB P4: CPUs of: QUI, QURA, QURCA, QURCB, QURCACC & QURCBCC
TE/CRG equipment - AMB introduction 6TECRGCE M.PEZZETTI
TE/CRG equipment - AMB introduction 7TECRGCE M.PEZZETTI
LINDE IHI QURC Layout 8TECRGCE M.PEZZETTI
(13/08/2011) P8 stop SEU signature..
(27/08/2012) P4 SEU signature… Rebooting (20s)…
SEU signature protocol… TE/CRG technical procedure for SEU signature identification: 1) Trend analyzing(20 s reboot) 2) AMB Test on TECRGCE test bench 3) Manufacture electronic stressing test In accord with TE/MPE (F. Formenti). TECRGCE M.PEZZETTI
QURCs- AMB UX45 localisation 12TECRGCE M.PEZZETTI PLC Siemens & Profibus network
QURCs- AMB UX45 localisation 13TECRGCE M.PEZZETTI PLC Siemens & Schneider
QURCs- AMB UX45 localisation 14TECRGCE M.PEZZETTI AMB & VFD
Discussion on possible November 2012 test at H4IRRAD. 15TECRGCE M.PEZZETTI H4IRRAD area test No radiation for CCS cartouche.
R2E strategy for P4? -Blindage -Delocalisation <20m -Delocalisation >20m
SEU: Balance END CRG/OA-as
SEU: Balance Number of weeks with Stable Beam > 640 bunches: ~23 weeks ~15 weeks TS CRG/OA-as 640 bunches TS Courtesy A. Suraci TE-CRG-OA
SEU: Balance Actions taken to improve robustness : CV891: automatic reset implemented into PLC (action: cut off 24 Vdc). TT89x: modification of electronics card (capacitor removed), timer PLC: moved into better protected zone (P4-P6-P8 caverns) 24 Vdc: longer term, to be moved into a safer protected zone and better distribution of power consumption to be done. AMB (Magnetic bearing controlers): relocation 2 nd unit of P8 (Phase III), additional shielding required? CRG/OA-as Courtesy A. Suraci TE-CRG-OA
R2E P8 Ph 3 Relocation, long and complex project well prepared a success!!
QURCs- AMB UX45 localisation 21TECRGCE M.PEZZETTI 20 m maximum…
R2E- P8 Ph3 P8 QURCB Transfert US85 to UL84 QURCA- EMC1 QURCA/B&QUICC Valves Positionners Racks US85 QURCB- EM01=US85 Blocs Phoenix Caverne UX85 8 NE48 Cables controle from QURC-EMC1 to EMC4 22 specific Cables controle depuis Blocs Phoenix QURCB-EM01=US85 12 Cables CCS 24VDC/230VAC UPS /400VAC 3 Cables Profibus PA 1 Cables 24VDC I/O depuis rack 24VDC US specific Cables Compr. Froids 2 Cables NE48 vers PLCSiemens + 1 cable NE18 UL84 UJ84 Existing cabinets from US852 new location Cables NE8 QURCA- EMC2 QURCA- EMC3 QURCA- EMC4 QURCA- EM02=UL84 QURC_QUI- EM03=UL84 QUICC- EM02=UL84 Cold Compressors QURCB-Schneider New Cabinet US852 CCS Cabinet QURCA CCS Cabinet QURCB 2 Cables Ethernet depuis Start Point US851 Longueur cables US852 a US85 CCS: 20m Longueur cables de US852 vers UJ84: 70 a 75m Longueur cables Armoires CCS US85 vers UJ84: 40 a 45m US851 QURCB- EMC1 QURCB- EMC2 QURCB- EMC3 QURCB- EMC4 QURCB- EM02=UL84 Realisation new chassis QURA-Existing Schneider Cab. +Turbines cab.- NewLocation Partie elec Vannes CV + 8 EV
P4/P6 PLC CPU relocation