Reedy River Basin Sewer Tunnel Project Update

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Beneficial Occupancy Readiness Evaluation Plan Update Brian Heneveld, P.E., CIH NSLS-II BORE Coordinator Conventional.
Advertisements

A3 - dual carriageway link between London and Portsmouth 6.5km new road, 1.77km in bored tunnel £371 million Construction started January 2007 Project.
GROUND TREATMENT WORKS COMPENSATION GROUTING FARRINGDON STATION Client: CrossRail Main Contractor: BFK (Bam-Ferrovial-Kier JV) Site Location: Farringdon.
Presented by NEORSD Richard J. Switalski, P.E. Presented by NEORSD Richard J. Switalski, P.E.
Northern Ireland Water QUESTOR Centre, QUB. Introduction: UK Water Industry 25 water companies in England & Wales 12 water and sewerage providers 13 water.
Introduction to Trenchless Methods
City of Fargo Mickelson Field Area Flood Risk Management – Project 5902 Public Information Meeting July 12, 2012.
City of Bloomfield Hills 2015 Road Improvement Program.
Tunnelling Methods.
Yellow River Diversion Project Use of Tunnel Boring Machines to Divert the Yellow River, China John Train & Philippa Reed.
ENGINEERING GEOLOGY OF THE CHANNEL TUNNEL Richard Rae & Robert Hazelhurst March 2006.
Foundations Excavations
OSHA’s Top 10 The 10 Most Frequently Cited OSHA Violations in General Industry and Construction: 2010 Presented by Safety+Health and OSHA.
Los Angeles County Metropolitan Transportation Authority Metro Green Line Eastern Extension Summary of January 1993 Final Environmental Impact Report.
Presentation to Maxwell Place Homeowners Association 1.
Henderson Mine Site. Henderson Mine Central Campus Shaft Collar Elev 10,400 ft Shaft Bottom Elev 7,500 ft LA Ramp Primary Access Ramp 3600 ft Central.
CFS challenges for a linear collider J.Osborne CERN ILC-GDE Dubna - 4 June 2008 OUTLINE : Introduction Civil Engineering -Geology (water, stability issues.
Partial Underground Analysis– TRTP Project Project Segment 8A Corridor October 29, 2011.
Automotive Brake Drum ME 324 Project Group 9 12/5/05 Jon RichardsonJared Chezik Kelly McGeoughBryan Johnsen Matt Creswick.
Utility Extension Project
Dick McDonald Risk April 16, LCLS Conventional Facilities Dick McDonald Deputy Systems Manager.
Community Liaison Committee May 26, 2015 Bow Lake Wind Project.
3/2011 CFS BTR Global Design Effort 1 Americas Region Civil Design Tom Lackowski.
NATM NEW AUSTRIAN TUNNELING METHOD.
John Osborne GS/SE March 2013
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
Construction and Installation of the CLIC Experimental Area
Title Slide  Importance of process  Comparative cost estimates  Ventilation and other environmental issues 03079/ 2.
CEAL January 31, Existing Alternative (Preferred Align) Objectives SR-76 Corridor Expand Mobility Improve Safety Enhance natural resources Synergy.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
Laughton 7/04 Long Baseline Neutrino Program Tunneling Chris Laughton, Fermilab.
MTA Regional Commuter Rail System. Bringing the LIRR to Grand Central Terminal (GCT) - Route Map.
Start Typical student project Advanced student project Level of final response.
1 8. I MPLEMENTING THE P LAN Objective: To understand the principles of successfully implementing a plan, by communicating the plan to key site personnel,
Global Design Effort - CFS ILC10 Beijing, March, Single-Tunnel Accelerator Configuration Of Asian Region Atsushi Enomoto (KEK)
August 2008 Kissimmee River Updates Photographs by Brent Anderson The Effects of Tropical Storm Fay.
December 3, 2015 TOWN OF MILLBURY DPW, MA Robert McNeil, P.E., Director PARE CORPORATION, FOXBORO, MA Allen R. Orsi, P.E., Managing Engineer This project.
3/20/11 ALCPG11 Global Design Effort 1 CFS Detector Hall Considerations Tom Lackowski.
Campus Change: Help Manage Construction Impacts ▸ General Academic Building No. 1 construction to begin in spring semester ▸ Plans are underway to close.
General Infrastructures Services Department Civil Engineering planning for LSS4 Option, presented at review workshop 30/7/ months Planning and Resources:
Construction Schedule for Baseline and Hybrid A’ Configuration 1 5 th September, 2014 J-POWER MDI-CFS Meeting - Ichinoseki City, JAPAN.
Geothermal Energy System Progress Update. Will cut annual energy use by 50% Will reduce carbon dioxide emissions by 25,000 tons per year Will cut water.
Standard CLG – Pipebursting Method Machine and insertion pits are excavated at the ends of the deviated sewer section and a rod pusher/puller and RSI Rotary.
PRESENTED BY- Namrata M. Lolge (09CM16F) M. Tech. 1 st sem NITK.
Construction Beam Tunnel
Upper Middle Road Grade Separation Construction Project Status Update February 2009.
25 June EHN1 civil engineering project status (MAY) Summary: Updating of the activities carried out on-site (Done) in MAY List activities on going.
SOUTH LAGUNA TUNNEL STABILIZATION & SEWER PIPELINE REPLACEMENT PROJECT Providing Quality Water & Wastewater Services To the Coastal Communities.
RISK ASSESSMENT FCC draft, 2. September 2015.
Middlebelt Transport and Storage Tunnel (MTST) Project
INTRODUCTION TO TRENCHLESS TECHNOLOGY
Visit for more Learning Resources
Bond and Override Report
CLIC Civil Engineering Update
Cost & Schedule between Shaft and Adit for Access of Detector Hall
College West Residence Renewal Project
Risk Management – Correlation and Dependencies for Planning, Design and Construction Philip Sander Alfred Moergeli John Reilly.
National Conference of Regulatory Attorneys
Weighted Interval Scheduling
Brencal Contractors Inc.
Weighted Interval Scheduling
Construction Considerations
Manufacturing Process
The Anschutz Health Sciences Building Construction Update 8 April 2019.
Metropolitan Tunnel Redundancy Program Update
Aquatic Center Rock Excavation Status
Risk Management – Correlation and Dependencies for Planning, Design and Construction Philip Sander Alfred Moergeli John Reilly.
Things You Need to Know about Underground Utility Contractors Dalton GA.
Pre-Proposal Meeting Request for Qualifications
Presentation transcript:

Reedy River Basin Sewer Tunnel Project Update September 27, 2018

What is a Starter Tunnel?   A starter tunnel is the initial tunnel excavation which is typically required to help setup the Tunnel Boring Machine and ancillary equipment for the entire excavation Starter tunnel length depends on: Type of Tunnel Boring Machine Ground Conditions (type and behavior) Contractor Means and Methods Worker safety is the overriding factor for all design and construction in tunnels

Access Shaft Aerial Access Shaft

Ground Conditions Necessitate Change in Construction Approach

Starter Tunnel Construction Excavation will involve drill and blast methods and mechanical excavation

Starter Tunnel – Ground Support Rib and lagging ground support required for mixed face conditions Excavation will involve drill and blast methods and mechanical excavation

Tunnel Shield Tunnel shield serves to protect workers in unstable ground Advanced in 4-foot intervals ahead of excavation

Cleveland Park Impacts Initial closure of public parking in Cleveland Park was 760 days. ReWa has worked with Contractor to reduce days parking lot will be closed to less than 760. Ability to maintain public accessibility to parking lot through Spring 2019 Ability to maintain public accessibility to portion of the parking lot following TBM excavation completion

Current Project Schedule   Commence work at access shaft – September, 2018 Commence work for starter tunnel – Spring, 2019 TBM launch/Starter tunnel completion – Spring/Fall, 2019 Cleveland Park Restoration – TBD after finalizing design and sequencing Current Contractual Final completion –June 25, 2020 Actual Final Completion – TBD after finalizing design and sequencing