Avoided Cost and E3 Calculator Update Workshop

Slides:



Advertisements
Similar presentations
Avoided Cost and E3 Calculator Update Workshop March 14-15, 2006.
Advertisements

A Comparison of Measure Avoided Cost Calculations using Utility TOU Load Shapes and DEER Hourly Measure Savings 14 March 2006.
1 Illustrative Results Based on E3’s Avoided Cost Model Thursday, April 19, 2012 Marginal Generation Costs.
Power Supply Adequacy Assessment Model/Methodology Review Steering Subcommittee Meeting January 29, 2010.
1 Generation Adequacy Task Force Report to TAC April 7, 2005.
Capacity Valuation.
The Benefits of Dynamic Pricing of Default Electricity Service Bernie Neenan UtiliPoint International Prepared for Assessing the Potential for Demand Response.
Energy and Environmental Economics 1 Avoided Cost and E3 Calculator Workshops Energy and Environmental Economics, Inc. October 3, 2005.
California Energy Commission Resource Adequacy Demand Forecast Coincidence Adjustments R Resource Adequacy Workshop January.
Copyrighted © 2000 PG&E All Rights Reserved CASE Initiative Project TDV Economic Update Brian Horii and Snuller Price Energy & Environmental Economics,
Compare and Contrast ELCC Methodologies Across CPUC Proceedings
Renewable Net Short.
Resource Adequacy Forecast Adjustment(s) Allocation Methodology
2011 Long-Term Load Forecast Review ERCOT Calvin Opheim June 17, 2011.
Avoided Cost and E3 Calculator Workshops Energy and Environmental Economics, Inc. October 3, 2005.
Overview – Non-coincident Peak Demand
1 Demand Response Update April, Strategic Perspective Demand Response  Aligns with PGE’s Strategic Direction; helping to provide exceptional.
1 Quality Control Review of E3 Calculator Inputs Comparison to DEER Database Brian Horii Energy and Environmental Economics, Inc. November 16, 2006.
SM SOUTHERN CALIFORNIA EDISON® Page 1 Discussion on CEC’s and SCE’s Forecast Differences Presentation at CEC Preliminary Demand Forecast Workshop July.
Methodology for Energy Savings claim for Incentive Programs and Codes & Standards(C&S) accounting Presented by: Armen Saiyan P.E. For the California Technical.
1 EE Evaluation Report on 2009 Bridge Funding Period California Public Utilities Commission November 22, 2010 Energy Division Energy Efficiency Evaluation.
NW Resource Adequacy Forum Steering Committee Conference Call November 4, 2010.
Avoided Costs of Generation
Jenell Katheiser Doug Murray Long Term Study Scenarios and Generation Expansion Update January 22, 2013.
California SONGS\OTC Plants Assumptions TEPPC – Data Work Group Call Tuesday, September 15, 2015.
California Energy Commission 2015 IEPR Self-Generation Forecast Sacramento, CA 7/07/2015 Asish Gautam Demand Analysis Office Energy Assessments Division.
1 CPUC Avoided Cost Workshop Introduction and Overview.
1 Issues summary Pre workshop comments. 2 Scope of the 2006 Update 1. Common definition of peak 2. Avoided cost and E3 Calculator updates for peak and.
Avoided Cost and E3 Calculator Workshops Energy and Environmental Economics, Inc. October 4, 2005.
“Demand Response: Completing the Link Between Wholesale and Retail Pricing” Paul Crumrine Director, Regulatory Strategies & Services Institute for Regulatory.
Reliable Power Reliable Markets Reliable People Losses and Ancillary Services: Volume Analysis 2007 Budget Review Process August 28, 2007 Operations Planning.
California’s Proposed DR Cost-Effectiveness Framework January 30, 2008.
Avoided Cost and E3 Calculator Update Workshop March 14-15, 2006.
Avoided Cost Calculator Workshop Day 2 October 4, 2005 Energy and Environmental Economics, Inc.
DR issues in California discussed last year in March Historical DR in California: some background issues –Twenty years of programs/tariffs I/C and AC cycling.
Analysis of Demand Response Modeling in GridView Andy Satchwell and Sarah Smith Modeling Work Group December 21, 2015 The work described in this presentation.
California Energy Commission Retail Electric Rate Projections: Revised Cases 2015 Integrated Energy Policy Report California Energy Commission December.
An Overview of Demand Response in California July 2011.
California Energy Commission 2015 IEPR Self-Generation Forecast Sacramento, CA 12/17/2015 Asish Gautam Demand Analysis Office Energy Assessments Division.
2015 California Statewide Critical Peak Pricing Evaluation DRMEC Spring 2016 Load Impact Evaluation Workshop San Francisco, California May, 2016 Prepared.
1 R Workshop on 2016 RA proposals Energy Division Staff Procurement Oversight and Resource Adequacy California Public Utilities Commission Thursday,
Demand Response 2010 and Beyond April 28, 2011 Pete Pengilly.
Hybrid Forecast for Resource Adequacy Analysis with recommendations Massoud Jourabchi April
2013 Load Impact Evaluation Capacity Bidding Program (CBP) Steve Braithwait, Dan Hansen, and Dave Armstrong Christensen Associates Energy Consulting DRMEC.
April 5, 2016 CPUC. JDRP Proposal  Flexible RA Attributes and requirements should be unbundled from the underlying system RA and Local RA attributes.
DRMEC Spring 2016 Load Impacts Evaluation Workshop San Francisco, California May 10, SDG&E Summer Saver Load Impact Evaluation.
CPUC Avoided Cost DRAFT Results CEWG Workshop May 31, 2016 Brian Horii, Senior Partner Snuller Price, Senior Partner Zach Ming, Consultant Kiran Chawla,
Joint Energy Auction Implementation Proposal of PG&E, SCE and SDG&E California Public Utilities Commission Workshop – November 1, 2006.
Prepared by California Department of Water Resources May 31, 2001
LNBA Subgroup: Avoided Transmission Value
Bypass Distributed Generation (DG) Forecast Methodology
DWG Meeting March 7, 2017 (Update to a Meeting held July 26, 2016)
Self-Generation Forecast CED 2017 Preliminary
Hourly vs TOU Avoided Costs
Emergency Response Service Baselines
Mike Jaske California Energy Commission
Allegheny Power Residential Demand Response Program
Preliminary Electricity Rate and Time of Use Rate Scenarios
PLC = Peak Load Contribution (aka “ICAP”)
California Energy Demand Electricity Forecast (CED 2014) Update: Method and Summary of Results November 5, 2014 Chris Kavalec Demand Analysis.
Independent Load Forecast Workshop
Resource Adequacy Demand Forecast Coincidence Adjustments
Market Design in New England
GENESYS Current Functionality
Behavior Modification Report with Peak Reduction Component
NYS Department of Public Service
Technical Committee Meeting March 18, 2016
Commissioner Anne C. George
EM&V Planning and EM&V Issues
Medium & Heavy Duty Electric Transportation Rate Designs at SCE
Presentation transcript:

Avoided Cost and E3 Calculator Update Workshop March 14-15, 2006

Agenda – Day 1 Introduction 10:00 – 10:25 Discussion of major issues Peak definitions 10:25 – 11:40 Load shape development 11:40 – 12:00 Lunch break Critical and super peak periods 1:00 – 2:30 Break Capacity adder and peak reshaping 2:45 – 4:30 Natural gas price update 4:30- 5:00

Agenda – Day 2 Housekeeping from Day 1 9:30 – 9:45 Miscellaneous issues 9:45 - 11:00 Application of E3 tool Recommendation for future tools Overhead double counting EE forecast in resource plans (net vs. gross) Applicability to demand response Other Recap of consensus / non-consensus 11:00 – 12:00 Lunch Action Plan / Next Steps 1:00 – 2:30 Break Load shape development 2:45 – 5:00

Introduction Scope and purpose for the 2006 update (ALJ Gottstein) See handout entitled Purpose and Scope of 2006 Update (per December 27, 2005 ALJ ruling) Workshop focus and approach (E3) Near term changes for rebalancing, tracking achievements and performance basis setting. Recommendations for longer term changes for the 2009-2011 program cycle. Broader consistency across proceedings/ resource types? Help to identify phase III issues. Working workshop second half of day 2 (load shape development) Approach to discussion Brief summary of E3 findings and recommendations Summary of party positions and discussion Identify areas of consensus / non consensus Alternatives for ALJ consideration Consider both near term and long term

Peak Definitions Peak definitions for EE are needed for MW goals, tracking the achievements of goals, evaluation of portfolios to reach goals, and determining performance basis. Consistency within EE applications Consistency with peak definitions for other resources or in other proceedings (DR, DG, RA). Consider both near and longer term definitions as well as the data requirements.

Peak Metrics – 1 DEER kW Available for measures in the DEER database. For temperature sensitive measures, peak demand is defined as the average grid level impact for the measure from 2pm to 5pm on peak days. Pro: Is currently used by utilities for measures where DEER kW is available, though there are some differences among utilities. Both SCE and SDG&E report DEER kW for all programs. PG&E states that only 60% of its program impacts are based on measures in the DEER database (the rest calculated from larger, complex projects) Cons: Not available for all measures. DEER kW is derived using building simulation tools based on prototypical buildings and as such has some limitation in terms of accuracy. Summer on peak kW Based on old utility studies, or can be calculated from hourly end use or impact shapes Pro: Readily available from old utility studies, which often used load research data and conforms with utility time of use period definitions. Con: On peak periods vary for each utility, so the reported on peak demand reduction for the same measure could differ across utility service territory (even if all other things were equal) On peak demand estimates from the TOU studies can differ from the DEER kW estimates. This fact prompted SDG&E to report DEER kW (also referred to as Deemed kW) for all of their programs.

Peak Metrics – 2 Load Factor based kW (CEC kW) Annual energy reductions multiplied by a fixed conversion factor. Pro: Easy to estimate. Requires little additional M&V effort. Con: Does not recognize the fact that peak load factors vary by measure, and could therefore allow an overemphasis on poor peak-load-factor measures such as residential CFLs. Resource Adequacy (RA) consistent peak kW Early discussions centered around requirements for Demand Response which currently counts peak load as the average reduction over 48 hours of operation, 4 summer months, 4 days per month, 3 hours per operation. According to the newly adopted RA counting rules, the RA value of energy efficiency is 115% of its monthly coincident peak impact. Pro: Might reflect the actual avoided costs of capacity if resource adequacy (RA) counting rules were to apply to energy efficiency measures. Con: RA rules are interim. Requires hourly data. Unclear which hours should be designated as the peak period dispatch hours, or the single hour monthly coincident peak. PG&E also cautions that peak impacts calculated from an RA perspective could be significantly lower than peak impacts estimated from past and current methods.

Peak Metrics – 3 Coincident peak kW Requires hourly load shapes and specification of peak hours. For PG&E’s end use shapes, the peak hours were identified as the five top system load hours in each month. Monthly coincident peak kW = average load during the five peak hours. Coincident peak is the average July through September monthly peak kW. Pro: Provides the most precise metric of peak or critical peak load reduction. Con: Requires hourly load data which is not currently available. May be a challenge for M&V ex-post estimations.

E3 Recommendation for EE Proceedings E3 recommends two options for determining peak demand reduction in the near term: Report DEER kW (deemed kW) where available, and utility best estimates in other cases. Use load factors by end use categories. Longer term: (not addressed in the Draft Report) Move toward a concident peak measure that uses a weighted average of many hours. The number of hours will depend upon the extent to which the impact data and cost data are aligned. The better the alignment, the fewer hours needed.

Summary of Party Positions: Peak Definitions and Load Shapes

Peak Definition across applications Discuss as a group Peak MW Application Granularity needed Potential Peak Definitions Resource Adequacy Single coincident hour each month Long term planning Single annual peak?

Load shape development Requirements for Peak kW metric EE valuation Representation of EE in other applications Calibration issues Working session to develop action plan, second half of day 2.

Load Shapes E3 recommends a research effort to develop calibrated load shapes for use in the 2009-2011 program cycle. Shapes should be impact shapes (not building shapes) that are hourly in resolution Shapes should reflect diversified impacts at the grid level and reflect run time averages Potential data sources DEER CEUS? Building simulations, such as those used for Title-24. Issues Calibration Alignment of loads with generation costs

Sample Impact Shape Results Res A/C is the PG&E residential end use shape DEER AC eff is the DEER impact shape Both shapes normalized so that total annual reductions sum to 1.0

Sample Commercial Impact Shape Office Cool is the PG&E end use shape (CZ 13) DEER Chiller Eff is the corresponding impact shape Note that the DEER reduction is 0 in the second chart

Comparison of TOU Shares Commercial shares are comparable Normalized Residential DEER shape has higher on-peak %, partly because of negative amounts in other periods.

Summary of Party Positions: Load Shapes

Need for critical or super peak periods Definitional needs kW and TOU shares for use in other proceedings? Recommended definitions Valuation issues Adders to TOU average avoided costs? Short term options and long term ideal

E3 Recommendation Critical peak metric not necessary for non-dispatchable (EE) programs. Super peak periods could reduce the undervaluation of measures like Res AC that occur with the use of TOU average costs. BUT this would require that utilities could develop super peak impact profiles. E3 recommends that super peak periods not be used in the near term because Shape development would be difficult The examples in the Draft Report are based on PG&E’s building end use shapes, not impact shapes Value could be added directly to programs such as Res AC without the construction of super peak periods.

Super Peak Results: PG&E Generation Avoided Costs & Building End Use Shapes CZ13 CZ3

Summary of Party Positions: Critical Peak Periods

Capacity adder and peak reshaping Need to increase peak avoided costs? Methods to calculate a capacity adder Peak Reshaping TOD profiles Methods to allocate capacity adder to hours Phase 3 issues?

Draft Report E3 does not believe the LRMC methodology should be modified to require entrant of a CT If the price shapes must accommodate a CT, the capacity adder would be $40-50/kW-yr. This may represent a fundamental change in methodology The LRMC is a full hedged physical product, so no hedge value adder is needed TOD factors should not replace the PX shape because They lack granularity Represent a fundamental change to the avoided cost methodology --- move to phase 3.

Draft Report Residual Capacity Adder Using flat annual gas price Using daily spot gas prices

Impact of $50/kW-yr capacity adder on EE valuation Average avoided costs and hourly shapes Average avoided costs using TOU shapes

Summary of Party Positions: Capacity Adder & Peak Reshaping

Natural Gas Update Updated natural gas forecast with EIA Outlook 2006 forecast and the CEC’s IEPR forecast NYMEX values were not updated in the report (but should be updated with the most recent data available)

Gas Price Change New forecasts are about 6-9% higher than the existing prices.

Generation Avoided Cost Change Updated gas price increases electric generation avoided costs by 4-5% The electric avoided cost increase is dampened by O&M and capital costs that do not change. SP-15

Latest NYMEX Forecasts Note: 60 day average prices for all contract on or after April 2006 have been calculated using 60 calendar days of data up to 3/10/2006, as available.

Summary of Party Positions: Natural Gas Update

Day 2 Other Issues Action Plan / Next Steps Load Shape Development Application of E3 tool Recommendation for future tools Overhead double counting EE forecast in resource plans (net vs. gross) Applicability to demand response Other Action Plan / Next Steps Load Shape Development

Draft Report No need to depart from E3 calculator in near term E3 requires no modifications to conform to SPM Overhead cost double counting is a caused by reporting rules. Calculator improvements such as links to DEER and load shapes should be held until the next program cycle when new load shape data is available.

Summary of Party Positions: Tool-related Comments

Summary of Party Positions: Other Issues