Monday – Morning Fill 3265 stable beams since 1:31

Slides:



Advertisements
Similar presentations
Saturday 7ish – refill for RP set-up 9:15 Going for Roman pot alignment. Stefano is coming. 12:10 TOTEM: Alignment of horizontal RPs B2 finished, short.
Advertisements

08h15: Injection.  Correction injection oscillations.  Transfer line steering.  Losses at 30% of dump threshold, limited by SPS scraping. 12h35: Start.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Monday Recover after trip of RB.A81  Cause of the trip not clear. MP3? 09:00-13:00 Re-inject and Injection verification. In parallel investigations on.
Saturday :12 Stable beams fill 3351 Initial luminosity
Friday 15th June 01:11 Injection.
Wednesday September 14th
Monday 21st January & night
Monday fill with 1092 bunches (6 h stable beams)
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Tuesday 22nd January - morning
Coordination: Gianluigi Arduini & Jan Uythoven
LHC Morning Meeting - G. Arduini
Wednesday Morning 8: :30 end of fill study - octupole polarity inversion (Elias, Tatiana, Alexey, Georges, …): Goal: study the effect of the.
Note: squeeze in Atlas, CMS, LHCb and Alice on going
Friday 31st August & night
Friday day 00:51 Fill #1862 Beams lost to inner triplet skew quad power converter fault. Delivered lumi 33 pb-1 Access required for repair RQSX3.L1 converter.
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Chromaticity can make a difference…
Friday 11/5 08:00 RF communication problem solved. Ready to inject but beam not available from the injectors. Injection line collimators opened from 4.5.
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
LHC Morning Meeting - G. Arduini
Yesterday’s morning’s controls issues
Friday Morning 7:30 injection for fill 2908
Wednesday 9:08 Fill 3214 dumped by OP after 5:26 hours in stable beams
Tuesday morning 09:30 Beam dump, SIS dump due to lost connections with FCG FECs. Coincides with starting a development SIS server to test new interlocks.
Sunday/Monday & :30 Stable beams. Fill #1851.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Wednesday Ramp single nominal bunches for loss maps
Aims for the week Recover from technical stop and precycle at 10A/s
Monday 24 October hours of 25ns MD
LHC Morning Meeting - G. Arduini
Monday 14:00 beam dump Access:
Thu 6/4 End of fill #2470. ~1 pb-1 in 4 hours. Dumped by CMS BCM.
Rocky last 24 hours Losses Q6.R5 Orbit SIS TCDQ OK! Power converters
Tuesday 17/5 10: TeV - colliding. Start roman pot alignment ...
Saturday 3rd November - morning
IP8 aperture measurements (07:30-10:30)
Thursday – Morning Energy matching at injection with H CODs
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Thursday 22 September 2011.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
LHC Morning Meeting - G. Arduini
Tuesday In the morning test cycle with probe for Q’ measurement.
Tuesday 20 September 2011.
Wednesday 23/2 Thanks CRYO!!!.
Another Immortal Fill….
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Monday 27th August & night
Wednesday morning / afternoon
Wednesday morning Waiting for PS – problem on RF cavity.
Monday 14th May 00:03UFO at BLMQI.06R8.B2E10_MQML. Beam dump Re-steering required for TI2 03:28 STABLE BEAMS # e11 ppb, 4.11e33 cm-2s-1 13:36.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Saturday Luminosity production 1380 bunches
Tuesday End of fill 1393 Movement of suspicious Roman pots OK
Friday During the night from Thursday to Friday: by mistake, SPS longitudinal blow-up was not active  Smaller transverse emittance from the.
Saturday 26 November 2011.
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Tuesday
Presentation transcript:

Monday 5.11. – Morning Fill 3265 stable beams since 1:31 13:10 injectors ready to deliver beams 13:30 End of fill study for roman pots TCLs in IP1 and IP5 opened to >60σ Roman pots moved in 14:45 all ALFA pots at final position 15:08 beam dump because of losses when XRPH.A6R5.B1 at 32σ: Losses rising during several seconds after the movement of the RP Dump by RS7, RS8 and RS9 BLMEI.06R5.B1E10_XRP (same one which dumped last time at similar sigma) No scraping at the time of movement; no instability seen

Afternoon Integrated luminosity fill 3265 in 13h36’: ATLAS/CMS: 183 pb-1, LHCb 19 pb-1, ALICE 174 nb-1 15:39 – 17:57 RF line 1B1 LL problem during ramp down Access in UX451 to change a CPU Pre-cycling 19:10 injecting again transfer line steering 19:43 trip of RF line4B1, pre-driver faulty (dump during injection) -> re-injecting 20:27 – 20:39 SPS no extraction B1 (MST and MSE over temperature) 21:00 re-start injection

Night 22:16 stable beams fill 3266 1.55E11 ppb at the start of stable beams Peak luminosity ~6.4 1033 cm-2s-1 Transverse emittance ~2.54 um 2:24 increasing the RF voltage to nominal

Pending No beam from SPS after 5am Tuesday 6.11., technical stop: Magnet repair: estimated Tuesday 19:00 or Wednesday morning Wire scanner repair: estimated Tuesday midnight – Wednesday morning Accesses BLM IP2 installation of 1 Little-IC and 1 Flat-IC (3 hours without beam for DB update) ALICE 4 hours ?