Change Assurance Dashboard

Slides:



Advertisements
Similar presentations
Senior Stakeholder Forum 04/02/2014. Agenda UK-Link Programme Update –Including Data Cleansing Update Nexus Modification Update Faster Switching EU Reform.
Advertisements

OSF/ISD Project Portfolio Management Framework January 17, 2011.
February 2008 Gemini Incident Overview. Agenda Focus this part of the presentation is on the system elements of last year’s Gemini incident :-  Briefly.
PNISG Update June Xoserve’s UKLP Assessment Principles 1.Maintain current delivery plans where possible and appropriate e.g. don’t just push all.
Continuous Improvement Project (A Guideline For Sponsors)
Programme Management Board
Programme Management Board
Continuous Improvement Projects
Programme Management Board
The Investment Assessment Framework
Wholesale Market Reform
Key Value Indicators (KVIs) ‘Accepted’ Version 1.0
Guidance notes for Project Manager
Change Assurance Dashboard
Overall Project RAG Status
Amendment Invoice Task Force Progress Report
Release 3 Plan Options Decision
Programme Management Board
Overall Project RAG Status:
Recommendations for using this ‘framework’ template
Amendment Invoice Task Force Progress Report
Release 3 Update December 2018.
Cutover & Implementation Aggregated Programme RAG
DSC Change Committee Summary – 7th November
Change Assurance Update
Amendment Invoice Task Force Progress Report
Overall Project RAG Status
Key Value Indicators (KVIs) Version 1.1 (amendments from V1.0 in red)
2019 Release Planning Options inc Modification 0621 / GB Charging Project DSC Change Management Committee update July 2018.
Release 3 Update November 2018.
DSC Change Committee Summary – 11th July
Release 3 Plan Options Analysis
Overall Project RAG Status
Change Assurance Findings for UK Link Release 3 Health-check 2
Key Value Indicators (KVIs) Version 2.2 For Approval at CoMC
For Implementation 1st April 2019
Overall Project RAG Status:
Key Value Indicators (KVIs)
Ofgem Switching Programme: Central Switching Service consequential change update 9th May 2018.
Amendment Invoice Task Force Progress Report
Overall Project RAG Status:
Q1 & Q2 Forecast Update to CoMC
DSC Change Committee Summary – 13th March ‘19
Project delivery RIBA stages Define design deliver Key Objectives 1 2
Release 3 Scope & Proposed Plan
Release 3 Scope Selection and Plans
CoMC 14th March 2018 Michele Downes
Amendment Invoice Task Force Progress Report
Ofgem Switching Programme: Central Switching Service consequential update 16th May 2018.
Overall Project RAG Status
XRN June 19 Release - Status Update
Key Value Indicators (KVIs) Version 3.0
XRN4361 – UK Link Release 2 - Delivery
Programme Management Board
XRN4361 – UK Link Release 2 - Delivery
Overall Project RAG Status:
Change Assurance Report March 2019
Overview Headlines RSP – Progress Overview General progress report
Overview Headlines SIP Summary of progress High level plan
Project Overview.
RSP – Progress Overview General progress report High level plan
CSS Consequential Programme Change Assurance March, 2019
DSC ChMC Switching Programme Update 10th July 2019
XRN4361 – UK Link Release 2 - Delivery
Speaker’s Name, SAP Month 00, 2017
Overall Project RAG Status:
DSC CoMC Switching Programme Update 17th July 2019
DSC ChMC Switching Programme Update 9th October 2019
Customer Issue Management Dashboard CoMC
Customer Issue Management Dashboard CoMC
Presentation transcript:

Change Assurance Dashboard November 2018

Change Assurance Dashboard Summary Comments The majority of our work this quarter has been assurance of internal projects and programmes i.e. TransformUs ERP & D&N, Strategic Hosting Assurance Health check completed got Gemini GB Charging Part A. Assurance Health check underway for R3, will be reported at the next meeting Contributed to CSS Bid response Planned next quarter: MIS delivery framework review, Pre-Go-live Check R3 Cadent Billing, Gemini GB Charging Part B health check, set-up of assurance regime for CSSC and further health checks on internal projects Assurance status Numbers Complete 10 Underway 1 Scoping 3 At Risk

Gemini GB Charging Part A Summary Dashboard Area Date Change Project RAYG by Area CA1 – CA4 Summary Programme Delivery October 2018 Gemini GB Charging Part A – Health check Overall Business Case Team Sponsorship Plan Governance Customer Scope and Solution Other CA1 CA2 CA3 CA4 Gemini GB Charging Part A is planned to deliver five changes on 18th November 2018, with Part B delivering a greater and more complex scope delivering 6th September 2019. The assessment covered Part A only with Part B being assessed in April 2019 The project is running to plan and has passed all of its planned stage gates successfully with well documented evidence of success. The governance and control framework is well established and maintained, with only minor observations in relation to Assumptions and Dependencies The project is being delivered by an experienced team, the majority of who have successfully delivered previous Gemini releases. This applies equally to the Xoserve, Wipro and NG resources. Good collaboration between all parties has also been a key factor in the progress made to date. The plans are clear, generally well-structured and kept up to date. There is a minor finding in relation to the utilisation of dependencies in the plan Customer feedback has been positive and they are all confident that the project should successfully deliver its outcomes Testing is well planned, and supported by a clear and approved strategy. System Testing, Integration Testing and UAT (to date) have had very low defect rates (below1%) Implementation readiness is on track. In addition the team has continued to build on the improvements to the delivery approach that were started following EU Phase 2; introducing further changes, in collaboration with NG transmission, Wipro and NG IS, which have added value. 2 1

Change Assurance reporting RAYG definitions Categorisation of delivery risk is as follows: Red : indicates issues that could entail significant risk to the success of the Programme. Remedial action fundamental to successful outcome of programme, should be implemented as soon as possible; Amber : indicates issues that could entail significant risk to the success of the Programme. Remedial action important to programme outcomes, should be implemented as soon as practical; Yellow : indicates issues within could entail risk to the success of the Programme, but this risk is low Remedial action a good to have for the programme, implementation advised; Green : indicates very minor to no issues, entailing minimal risk to the success of the Programme. Improvement would reduce risk, but the weakness is unlikely to undermine the success of the programme

Change Assurance Findings Severity Category Description CA1 High risk of impacting successful delivery and achieving outcomes – finding needs to be addressed in order for project to succeed   CA2 Moderate risk of impacting successful delivery and achieving of outcomes – finding needs to be addressed in order to protect time, cost and quality CA3 Low risk of impacting successful delivery and outcomes – consider fixing in project and apply to future projects CA4 Minor impact to achieving delivery or outcomes – build in as a lessons learnt for efficient and effective delivery for future projects