Successfully Integrating NEPA and Environmental Permitting into a DoD Hazardous Waste Treatment Facility Construction Project to Meet Budget and Schedule.

Slides:



Advertisements
Similar presentations
PROJECT STUDY AREA Route Selection. Stage 1 Environmental Assessment Guidelines to underpin the effectiveness of the National Roads Project Management.
Advertisements

Metro Muncipal Agreement Program
Ken Jacobs Airport Planning & Environmental Division March 3, 2010 Federal Aviation Administration Federal Aviation Administration 33.
Finally! – A Process that Looks at Environmental Risk Early J. S. Irving Environmental Compliance Idaho National Laboratory.
EDDIE TERRILL AIR QUALITY DIVISION DEPT. OF ENVIRONMENTAL QUALITY AUGUST 21, 2014 EPA’s 111(d) Clean Power Plan Rule: A DEQ Perspective.
Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519 (1978) Strategic Delay in Derailing Public Policy.
Alternative Project Delivery
1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
Legal Perspective on NDOT Alternative Procurements Geoffrey S. Petrov, Nossaman LLP.
COMPLIANCE WITH GRANT IMPLEMENTATION PROCEDURES TxDot Grant Fund Project.
The Construction Specifications Institute Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT)
Post 2012 Energy Efficiency Planning Schedule: Options and Implications February 16, am - 5 pm CPUC Auditorium.
Water Treatment Plant No. 2 Concentrate Zero Liquid Discharge August 30, 2011.
Steps in the Hazardous Waste Permit Reissuance Process December 10, 2014.
FAR Part 1 The Federal Acquisition Regulation System.
CHAPTER 1 FOUNDATION. 1.1 National Environmental Policy Act (NEPA) “An act to establish a national policy for the environment, to provide for the establishment.
The Intersection of the National Environmental Policy Act and the Magnuson-Stevens Fishery Conservation and Management Act November 4, 2010 Roger Williams.
Shoreline & Waterway Management Section Regulations Governing Beach Protection and the Use of Beaches December 27, 1983 Beach – is that area which extends.
SAFETEA-LU Section 6002 “ Efficient Environmental Reviews for Project Decisionmaking”
Integrated Used Nuclear Fuel Management Regulatory Information Conference U.S. Nuclear Regulatory Commission March 11, 2009 Steven P. Kraft Senior Director.
CIVIL RIGHTS IMPACT ANALYSIS Animal and Plant Health Inspection Service Civil Rights Enforcement and Compliance.
Module 9: Natural Resource Assessment and Damages (NRD)
April 2006 Middle Fork Project Relicensing Process April 25, 2006
PPP Legal & Regulatory Framework. PPP Policy In July 2008 GOK approved the PPP policy directive through which: PPPs are identified as a method for investing.
NRC Environmental Reviews for Uranium Recovery Applicants and Licensees James Park (301)
1 IMPLEMENTING DOE ORDER ENVIRONMENTAL MANAGEMENT SYSTEMS U.S. Department of Energy Richland Operations Office.
Managing the Environmental Impacts of Power Canada Europe Roundtable for Business Toronto, 31 May 2005.
Request for Information & Capability Statements Richland Acquisitions Post-FY 2018 November 17-19, 2015.
1 © 2013 Protiviti Inc. All Rights Reserved. This document has been prepared for use by OOCEA’s management, audit committee, and board of directors. This.
1 Ventilation Systems Capital Asset Projects Safety Significant Confinement Ventilation System (15-D-411) Exhaust Shaft (15-D-412) Ronald.
Proposed Sale Notice (PSN) and Request For Interest (RFI) for New York BOEM NEW YORK TASK FORCE MEETING APRIL 28, 2016 Erin C. Trager New York Project.
PROCUREMENT General Overview of Procurement Process on Dublin Waste to Energy Project.
Southeast Rail Extension FasTracks Monitoring Committee July 14, 2015.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Southeast Rail Extension Update RTD Board of Directors FasTracks Monitoring Committee March 3, 2015.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Acquisition Support New Horizons Consulting Services, LLC’s, premier business unit is an offering of a full range of services and support for acquisition.
Camera PDR/CD1 Planning 19 September 2008
Session objectives After completing this session you will:
Department of Environmental Quality
Energy Huntsville Opportunity Report April 2017
Intent to Apply/Pre-Application Guidance
Municipal Solid Waste Program Update TCEQ Environmental Trade Fair
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
Final Rulemaking Nonattainment Source Review 25 Pa. Code, Chapter 121
PRE-PROPOSAL MEETING, September 19, 2017 Contract No.:
Division of Waste Management
The TRIUMF Gate Review Process
Presented to the Project Certification Committee on June
Facility Operations Contracting Support… Request for Proposals
AX7665D82 Areawide Total Maximum Daily Load (TMDL) Design-Build
General Services Department
National Environmental Policy Act (NEPA)
Environmental Planning in the Army Corps of Engineers
Green Line Extension Project
Vermont Yankee Nuclear Power Corp. v. NRDC, 435 U.S. 519 (1978)
Aberdeen proving ground advanced planning briefing to industry
Pavement Type Selection – Updated Guidance on Use of Alternate Bidding
Julie Woosley, Division of Waste Management
Federal Rulemaking Process for Significant Regulatory Actions
Strategic Environmental Assessment (SEA)
Brackish Water Desalination Project
Environmental Requirements and planning grants
Romania-Bulgaria border. Perspectives for
2013 Preconstruction Managers Meeting
Charter School Legislation HB 1390 and SB 737.
SWAC – Agenda 10/23/18 Chapter 6 – Alternative Technology – Draft Findings 2. Chapter 7 – Draft Landfill Disposal Existing Disposal System Disposal Options.
Right of Way Certification
Brieana Reed-Harmel, Broadband Project Manager
Land Use Planning Community Workshop
Presentation transcript:

Successfully Integrating NEPA and Environmental Permitting into a DoD Hazardous Waste Treatment Facility Construction Project to Meet Budget and Schedule 5-8 April 2004 Presented to: 30th National Defense Industrial Association Environmental and Energy Symposium Presented by: William J. B. Pringle Associate Director, Risk Management

Discussion Points Background Integrating NEPA, Environmental Permitting, Contracting, and Budget Submittals into an Integrated, Realistic and Achievable Schedule Conclusions

Destruction Program was Initiated in 1985 Background Army Authority to Destroy the Nation’s Chemical Warfare Stockpile Rests on Federal Statutes and an International Treaty Destruction Program was Initiated in 1985 Initial Congressionally Mandated Destruction Completion Date for 90% of the Stockpile was 30 September 1994 Several Public Laws Extended this Date to December 2004 The Ratified Treaty Requires the Entire Stockpile to be Destroyed by 29 April 2007, with up to a 5-Year Extension Possible

NEPA is the Initial Critical Path Activity Integrating NEPA, Environmental Permitting, Contracting and Budget Cycle Submittals into a Realistic, Achievable Schedule NEPA is the Initial Critical Path Activity Schedule is Essentially Controlled by the Government No “Proposed Action” Activities May be Taken that Would Have an Adverse Environmental Impact or Limit Alternatives Does Not Preclude Preliminary Planning or Facility Design Work Does not Preclude Submittal of Environmental Permit Applications or Advertising a Systems Contract Request For Proposals (RFP) Systems Contract Award Can Only Occur After the ROD is Signed and Published Prepare Update Reports….Records of Environmental Consideration

Environmental Permitting is the Secondary Critical Path Activity Integrating NEPA, Environmental Permitting, Contracting, and Budget Cycle Submittals into a Realistic, Achievable Schedule Environmental Permitting is the Secondary Critical Path Activity Schedule is Essentially Controlled by the Regulators Submitting Permit Applications is not a “Commitment” But May Create an Appearance of a Pre-ROD Decision To Mitigate any Legal Challenges, State in the Permit Applications that the NEPA Analysis is Still Ongoing and Modification Requests May be Submitted as a Result of the NEPA Process Systems Contracts May Only be Awarded Post-ROD and Pre-Permit Issuance With a Limited Notice to Proceed With Regulatory Approval, Limited Construction, to Include Some Utilities and Support Facilities, May Commence, i.e., Outside of the Regulated Facility Foot Print

Systems Contract Award is the Tertiary Critical Path Activity Integrating NEPA, Environmental Permitting, Contracting, and Budget Cycle Submittals into a Realistic, Achievable Schedule Systems Contract Award is the Tertiary Critical Path Activity Schedule is Controlled by the Government Advertising an RFP is Not an Irreversible, Irretrievable Commitment of Resources and is Therefore Acceptable Pre-ROD and Pre-Permit Issuance The Solicitation Should State That Contract Award Will be Made Post-ROD, Contain a Projected ROD Date, and the Duration Period for Proposal Acceptance Post-ROD Systems Contract Award Must be Post-ROD, but May be Pre-Permit With a Limited Notice to Proceed Budget Requests Overarch all Activities - Must Also be Realistic and Represent NEPA, Permitting, and Procurement Activities That are Based on an Integrated Realistic, Achievable Schedule

Follow Parallel Path Activities with an Integrated Schedule for: Conclusions Ideally the NEPA ROD, Environmental Permits, and Contract Award Should Occur on or Around the Same Date With Sufficient Funds in Place to Initiate Construction Activities Follow Parallel Path Activities with an Integrated Schedule for: NEPA Permitting Contracting Budgeting Know and Follow All Substantive and Procedural Requirements Key is Integrated, Realistic and Achievable Schedule There are Many Opportunities for Environmental Management Success; But Numerous Pitfalls Exist