Building for Learning Project Photo Progress Report 4 November 2009 – December 2009 Project commencement 21 st September 2009.

Slides:



Advertisements
Similar presentations
PLACE PREPOSITIONS.
Advertisements

Antti Piirto The first EPR under Construction in Finland International Nuclear Forum 2008 ”Bulgarian Nuclear Energy – National, Regional and.
1 Zero Tax Increase Referendum: Community Information Session.
16/05/ prepared by Joan Steele-Mills, Physiotherapist, Classification Officer CPISRA.
This is a partial presentation that I did for an employer who received a 5 million dollar contract from this presentation. The total slide count was over.
Building for Learning Project Photo Progress Report October 2009 Project commencement 21 st September 2009.
Building for Learning Project Photo Progress Report December 2009 Project commencement 21 st September 2009.
Lim Sei cK.  16 th September 2013 – 7 th December 2013  ACADEMIC WEEK 1 – WEEK 11  9 th December 2013 – 4 th January 2014  BRUNEI STUDENT HOLIDAY.
Weekly Attendance by Class w/e 6 th September 2013.
Berwickshire High School Presentation compiled 15 th October 2009.
Welcome to Our House. The Add On Project The tear down The slab Framing the Walls.
Glenn Murcutt Anna James Construction & Structures 2 SRT251.
Building the Rankin Ridge Fire Tower 2006 marked the 50 th anniversary of the construction of the Rankin Ridge Fire Tower. Because of improved fire fighting.
NEW TOWN HEIGHTS DLF – KAKKANAD WORK PROGRESS REPORT FOR THE MONTH OF MAY 2011 Click to proceed……..
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Building for Learning Project Photo Progress Report Month of June 2010 Project commencement 21 st September 2009.
SRT251- Construction and Structures 2 Timber Portal Frame Glenn Murcutt Daniel McLean
TAIPEI FINANCIAL CENTER TAIPEI 101 QUICK FACTS Holds the record as the world’s tallest building. Rises 501 meters (1,667 feet ) above the ground. 101.
DUBAI STAR WORK PROGRESS DATE 23 JULY Material At Site.
Kubota on hand to remove rubble. Farmall H with tilt trailer.
Express Team University of New Mexico February 24, 2006.
Interior Lifestyles Pvt. Ltd Welcome to our six step process for Interior designing of your commercial space. 6 6.
Whole School Attendance Whole School Attendance 94.64% Overall School Absence 5.36%
October 2011 Newsletter Supplement For additional information, please contact: DelDOT Public Relations 800 Bay Road, P.O. Box 778 Dover, DE
Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 03.
December 2010 Newsletter Supplement For additional information, please contact: DelDOT Public Relations 800 Bay Road, P.O. Box 778 Dover, DE
Malawi 2014 Building Progress Administration block and staff toilets internally painted with PVA and 2 topcoats Window frames repainted with 2 coats.
Building for Learning Project Photo Progress Report 6 February 2010– March 2010 Project commencement 21 st September 2009.
Building for Learning Project Photo Progress Report 3 October 2009 – November 2009 Project commencement 21 st September 2009.
Elevator Installation, Window Replacement, HVAC, Sprinklers, Block wall skimcoating (resident rooms & 1 st through 4 th floor resident corridors). New.
The Evolution of the TERRA Crystal Galleries Mineral Showroom.
Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
First installation of SOLARSPOT D900 CTT MAYA – PORTUGAL mq for the main distribution of the Portuguese mail service 206 system installed, in a.
Monday 1 st June 2009 Major Projects Dewar Place Cable Tunnel Works at Gardner’s Crescent Update Meeting.
Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 04.
Marketing & Tendering. Budget Forecasting Profit is the key to Business Success – Profit is amount of money after all expenses Materials Labour Insurances.
Introduction to a Flattop scale The scale to be shown is an Emery/Winslow Flattop Scale Platform is 40’x11’ with site rails. The foundation is a raft.
Building for Learning Project Photo Progress Report Month of May 2010 Project commencement 21 st September 2009.
Building for Learning Project Photo Progress Report 5 December 2009 – February 2010 Project commencement 21 st September 2009.
Vicinity Map Gillis W Long Center, Carville, LA Bldg 15 Stairwell Painting (1 st and 2 nd Floor) September 30, 2015.
High Efficiency Home with full Warehouse/Guesthouse and Cabana House By: Sutton Yanosky.
Bioscience Research Laboratories University of Arizona + DPR Construction Date: 2015 – Construction Work Starting Today for the BSRL Project !! Expansion.
Update to NLAG board 22 nd December Sep Jan MCE Workforce and OD Oct Nov Dec IM&T Estates Finance In hospital Model Out of hospital Model Progress.
The space behind the window sill has to be filled up with concrete and the cavity walls have to be filled up with insulation. One way is to pump the insulation.
Intro to Computers By David Becker. Space Needle For my website I did research on the Space Needle in Seattle. The following slides will tell you about.
Guess our concept... What do you think the concept of our lesson is?
Project: Renovation Works at Ricci Hall at 93 Pok Fu Lam Road C Sub-basement Level VIEW 5 VIEW 3 VIEW 4 VIEW 2 VIEW 1 VIEW 6 PROGRESS PHOTO REPORT - 02.
Unit 210: How to communicate with others
Supporting pin at boom of a Con ’ c pump car broken to hit the victim (Serious Accidents in Construction) Construction The copyright to this material.
ET 494 – Senior Design II Design of a Multi-Office Building BY: WOODROW WILSON INSTRUCTOR: DR. C. KOUTSOUGERAS ADVISOR: MR. R. EDWARD RODE.
Best 20 jobs jobs sites.
Building for Learning Project Photo Progress Report September 2010 Project commencement 21 st September 2009.
LIFE CYCLES OF AIKEN COUNTY PUBLIC SCHOOLS CONSTRUCTION PROJECT October 8, 2013.
What’s with Time Square West? No. of Floors 43 Retail 1st and 2nd floor Parking 5 floors(2 basement, 3rd to 5th floor) No. of units 738 No. of parking.
Design of an integrated 5-Star Hotel
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Victim Hit while Pushing a Cart
History of Pool Construction
TOTAL SWIMMING POOL REFURBISHMENT SOLUTIONS
Organics Waste Processing Facility Construction Progress Update December 15, 2010
Improvements for 2016 & 2017 Todd Harris Maintenance Manager
Building Construction I Sofia Sebastian 1
Christmas Opening Hours
KOMPLEX Investors Report – Q
The Transformation of A Small Company Into A Golden Legend
Toilets In ČRG.
General Membership Meeting
MKCG MEDICAL COLLEGE & HOSPITAL, BEHRAMPUR, ODISHA
How Excavation Companies Help You In Construction Projects In Ooltewah, TN.
Presentation transcript:

Building for Learning Project Photo Progress Report 4 November 2009 – December 2009 Project commencement 21 st September 2009

AWCC Chairperson Kerryn Dwyer-Parish with Graeme Connelly undertaking site inspections Kerryn braved the situation – high heels and all

The 65mm of rain made for 4 internal swimming pools but the task is completed

And no photographic record is complete without some rabbit ears

November Internal Refurbishments continue

Internal Refurbishments Administration Area

New ceilings, plaster, office and painting

Key workers without who the job could not be done.

December new on-site substation for power required.

December – carpet, ceilings and windows in modernised Administration area

December – steel, bond deck arrives for 1 st Floor

December – underground cable boring and concrete footings for stairways and elevator

December – Company Directors tour with Graeme Connelly – girls were happy, boys were serious. L-R. Chairperson Kerryn Dwyer-Parish, Director Jan Wyatt-Brown, Director Alison Mitchell, Corporate Services Manager Pauline Butler, Builder Graeme Connelly, Director Rod Jones, Director David Ryan.

December – bracing underneath bond deck and steel ready for concrete floor above

Final preparations and then concrete pour starting 6am, 22 nd December – 150 tonne concrete

22 nd December – 11 truck loads of concrete