Systems Level Design Review P15010: Arc Wheelchair Swing Maggie Bates –Team Leader Sean Kennelly – Design Lead Owen Breese – Team Facilitator Elizabeth Cutolo – Mechanical Engineer Maggie is doing this Open dialogue feel free to ask questions Maggie Bates, Sean Kennelly, Owen Breese, Elizabeth Cutolo
Agenda General Updates Project Management Risk Analysis Update System and Subsystem Design What? Why? How? Budget and BOM Team Assessment and Questions
Engineering Specifications, Risk Assessment, Project Management BACKGROUND
SUBJECT MATTER EXPERTS RIT Professors: Wellin, DeBartolo, Humphrey SWBR Architects Klein Steel Rob Kraynik Dr. Paige, University of Rochester Dr. Dan Phillips, RIT General Updates Edits to Engineering Specifications Finalized Versions that Reflect Changes Discussed with Customer Customer Relationship Weekly Meetings with Customer Work with Insurance Repetitive, Arc Facilities and Arc Staff to Ensure Project Success Arc of Monroe Day Services program provides opportunities for individuals faced with intellectual and/or developmental disabilities. Learning opportunities occur through mental, emotion, and social stimulation.
Current Market Owen
Current Market
Customer Requirements Owen
Customer Requirements Customer Rqmt. # Importance* Category Description CR2 9 Safety Minimizes distance of the chair off the ground during swinging for safety and size constraints. CR3 Supports the weight of the wheelchair and the occupant. CR15 Swing will remain at a safe speed throughout use. CR7 3 Versatility Arc facilities department has the ability to transport product from indoor areas to outdoor areas using doorways that range from 32" to 36". CR16 Budget Project total cost will not exceed $2,500
Engineering Requirements Sean
Engineering Requirements
Updates Since Last Review Stakeholder Communication Arc of Monroe Outreach Opened Dialogue with Director, Physical Therapist and Facilities Project Champion Dr. Dan Phillips from Biomedical Engineering Customer Requirement and Engineering Specifications Working towards solidifying with all members of the customer team Higher level understanding of vestibular simulation Safety Regulations What Arc will Accept as Product What resources are available for our use Impact on Budget Sean
House of Quality, Functional Decomposition SYSTEMS DESIGN
Functional Decomposition
Functional Decomposition
House of Quality Sean
Morphological Analysis, Pugh Chart, Selected Concepts, System Architecture, Feasibility Analysis, Risk Assessment CONCEPT DEVELOPMENT
Morphological Analysis/Pugh Chart
Concepts Sean
Pugh Chart
Each Concept was used as Datum. Below are the ranking averages. Pugh Chart Each Concept was used as Datum. Below are the ranking averages. Sean
Selected Concept Sean
System Architecture Sean
Force Required (Newtons) Feasibility Analysis Propulsion System Equation Minimum Value Maximum Value Mass (lbs) N/A 650 850 Mass (Newtons) 1 lb = 4.44822 Newtons 2891.3 3781.0 Velocity (m/s) 0.5 1 Time (s) 2 7 Acceleration (m/s^2) a=v/t 0.0714 Force Required (Newtons) F=m*a 206.5 1890.5 Force Required (lbf) 46.43 425 Sean
Feasibility Analysis Braking System Sean
Feasibility Analysis Safety Considerations 1:16 maximum slope for ramp Objects may not protrude 60’’ wide space of an accessible route Designers must consider optimal layout for experience Turning space for wheelchair shall be located immediately adjacent to swing Sean
Risk Analysis Owen
Risk Analysis (Continued)
Project Planning, Subsystem Design Focuses SUBSYSTEM DESIGN PREP
Project Plan Maggie
Subsystem Design Phase Focuses Braking Disc brakes Propulsion Human powered Safety Frame Action item Sean
Questions? Final Questions?